Two More Blocks Structurally Complete On Olympic Village
Progress continues on the build of the Olympic Village with three of the 11 residential plots now structurally complete.
The Village will accommodate athletes and officials during the London 2012 Games, and will provide 2,800 new homes for east London after 2012. Construction work began on site in summer 2008 with the first residential plot completed in October 2009.
Two further residential plots, comprising nearly 600 new homes, are also now structurally complete.
Work will now begin on the external cladding of the structurally completed buildings, with work inside the buildings due to start later in 2010. Construction work is also well underway on the remaining eight residential plots with more than 2,800 people now working on the Village site.
Olympic Delivery Authority Chief Executive David Higgins said: "The sheer scale of the Olympic Village development means this will become one of the busiest parts of our construction programme in 2010 and the completion of a further two residential plots keeps us firmly on track."
(CD/GK)
The Village will accommodate athletes and officials during the London 2012 Games, and will provide 2,800 new homes for east London after 2012. Construction work began on site in summer 2008 with the first residential plot completed in October 2009.
Two further residential plots, comprising nearly 600 new homes, are also now structurally complete.
Work will now begin on the external cladding of the structurally completed buildings, with work inside the buildings due to start later in 2010. Construction work is also well underway on the remaining eight residential plots with more than 2,800 people now working on the Village site.
Olympic Delivery Authority Chief Executive David Higgins said: "The sheer scale of the Olympic Village development means this will become one of the busiest parts of our construction programme in 2010 and the completion of a further two residential plots keeps us firmly on track."
(CD/GK)
29/01/2025
Caddick Construction has been awarded a £43 million contract to deliver the first phase of Cole Waterhouse's flagship regeneration scheme in Digbeth, Birmingham.
The project, known as Upper Trinity Street, marks a significant step in the area’s transformation.
Spanning 182,986 square feet, the re
29/01/2025
McLaren Construction has been appointed by O&H Properties to deliver the first phase of a £60 million Foster & Partners-designed development at the corner of New Bond Street and Grafton Street in London’s West End.
The seven-storey, 5,400 square metre prime retail and office scheme will feature ret
29/01/2025
GMI Construction Group has been awarded a contract to develop three high-specification warehouse units totalling over 175,000 square feet at Precedent Drive, Milton Keynes.
The £20 million project, commissioned by DV5 Last Mile Developments (UK) Ltd, a joint venture between Coltham and Delancey Re
29/01/2025
Plans for 106 sustainable new homes in Southville, a neighbourhood in South Bristol, have been approved as the city seeks to increase housing delivery to address growing demand.
Top 10 award-winning housebuilder The Hill Group will create a £60 million development on Raleigh Road, on land that was
29/01/2025
Bouygues UK has reached a major milestone in the fourth phase of the Hallsville Quarter regeneration project in Canning Town, London.
The project, part of the £3.7 billion Canning Town and Custom House Regeneration Programme, recently held a topping out ceremony, marking the completion of the 11-s
29/01/2025
Willmott Dixon Interiors is carrying out a significant upgrade to the roof of the National Maritime Museum in Greenwich, one of London's most iconic cultural landmarks.
As part of the £12 million project, the company is installing over 23,000 square feet of sun-protected glazing above the museum’s
29/01/2025
Equans has been appointed by Babergh and Mid Suffolk District Councils to carry out crucial decarbonisation work across the councils' housing stock, using funding secured through the Social Housing Decarbonisation Fund (SHDF).
The councils used the South East Consortium's Zero Carbon Framework to s
29/01/2025
In the world of construction, the quest for energy efficiency and sustainability is ever-evolving. Among the array of solutions available, EPS (Expanded Polystyrene) insulation stands out as a versatile and effective option for enhancing the thermal performance of buildings, particularly when used f
29/01/2025
BCP Council has completed significant coastal protection works at Hamworthy Park, ensuring its resilience against erosion for the next 20 years.
A 200-metre stretch of sea wall along the eastern promenade has been reinforced using low-carbon concrete, while new steps have been constructed to improv
29/01/2025
Geo-environmental consultancy and remediation contractor, The LK Group, has strengthened its team with a trio of recruits.
The multidisciplinary company's latest raft of hires comprises a new director, associate director and remediation manager.
The geo-environmental specialist, headquartered i