Subscribe to our Construction Newsfeed
UK Construction Directory
Search our 157,098 companies....

Construction News

31/08/2010

Blackwall Tunnel Ahead Of Schedule

The Blackwall Tunnel northbound refurbishment is to be completed six months early, Transport for London (TfL) has announced.

The project is now expected to be completed before the London 2012 Games.

TfL has praised the engineers whose rapid progress now means those works may be able to finish six months earlier than scheduled.

When work started in February, it was expected to take three years to complete the £70m refurbishment of the 113-year-old tunnel.
-- Advertisement --
hss



However, TfL and its contractor, BAM Nuttall, have made excellent progress on the refurbishment which means the safety upgrade will be finished in time for the London 2012 Olympic and Paralympic Games in July 2012.

Work completed so far includes the installation of new ventilation fans and concrete floors in two of the tunnel's four shafts, and the installation of temporary lighting, CCTV and communications systems throughout the tunnel, which will allow the old systems to be removed.

Work to install the permanent systems, which will bring the tunnel up to current standards, will begin later this year.

(CD/KMcA)

Latest Construction News

25/04/2025
Aston Villa Football Club has unveiled plans to refurbish and expand the iconic North Stand at Villa Park, a major step in the wider regeneration of the North Grounds. The redevelopment will raise the stadium's total capacity to over 50,000, with the North Stand alone increasing to more than 12,00
25/04/2025
Morgan Sindall Construction's Southern Home Counties team has officially handed over the newly completed Crawley Innovation Centre to Crawley Borough Council (CBC). The transformation of the former TUI travel house into a cutting-edge innovation, economic and technology hub drew local leaders, busi
25/04/2025
Clowes Developments has confirmed that construction will soon commence on five new trade counter, warehouse and industrial units at Stud Brook Business Park in Castle Donington, following planning approval from North West Leicestershire District Council. The new development, Plot 1, will feature fi
25/04/2025
A historic 18th-century landmark has been carefully restored as part of the major Garendon Park housing development in Loughborough. The Grade II* listed Obelisk, located within the grounds of the former Garendon Hall estate, had endured years of weathering before undergoing a sensitive restoration
25/04/2025
Mace has appointed industry heavyweight, Gary Sweeney, to head up its European team working across the Healthcare, Life Sciences and Technology sectors. Gary joins Mace following a spell as Interim Director in Turner & Townsend’s Advanced Manufacturing, Industrial and Logistics division in the UK
25/04/2025
A groundbreaking ceremony has recently marked the start of a £5.5 million extension project at Thorp Academy in Ryton, Gateshead. The development, aimed at accommodating the growing student population, is being delivered by Morgan Sindall Construction on behalf of the Northern Education Trust (NET
25/04/2025
Wakefield-based Henley Stone Specialists has been appointed to deliver Glass Reinforced Concrete (GRC) elements for the first phase of 'Our Cultural Heart', Kirklees Council’s flagship project aimed at revitalising Huddersfield town centre. Part of the Henley Construction Management Group, Henley S
25/04/2025
More than 2,500 Nottingham homes are set to benefit from energy efficiency improvements as part of a major £153 million regional initiative to cut household bills and carbon emissions. Nottingham City Council's Executive Board has approved the acceptance of nearly £76 million in Government funding
25/04/2025
Introduction: What Is a Fitted Hoist? A fitted hoist is a mechanical lifting device installed in the home to help safely move individuals with limited mobility. Commonly found in bedrooms, bathrooms and living spaces, these systems make it easier and safer to transfer someone between a bed, chair,
25/04/2025
Rail services between Hereford and Shrewsbury are facing significant disruption following the collapse of an underground culvert, forcing the closure of the line in both directions. Emergency engineering works are underway to ensure the safety of the railway. Network Rail's engineering teams are
T & D Glazing And Installation LimitedStuart CanvasAqua Direct LtdEfco UK LtdLakeside HirerooostSphion ArchitectureParoc Panel SystemClean Room Construction LtdAlpha Recruitment