19/11/2010

Highways PFI 'Could Have Been Better Value'

A National Audit Office (NAO) examination of the Highways Agency's PFI contract to widen the M25 as a way of reducing congestion has concluded that it could have been materially better value for money.

The slowness with which it was taken forward resulted in higher financing costs in the credit crisis. Moreover, the Agency was slow to investigate a potentially cheaper alternative to widening.

An 18-month delay in preparing and finalizing the widening procurement meant that the contract was let in May 2009 at the height of the credit crisis. This increased the net present cost of the deal by £660 million (24 per cent) to £3.4 billion. The case for PFI was less convincing than the Agency thought owing to shortcomings in its cost estimation process.

The Government had announced in 2003 its intention to reduce congestion on the M25. The Agency was starting to carry out trials at that time of an alternative, potentially cheaper solution of hard shoulder running (allowing drivers to use the hard shoulder at times of peak congestion), first tested in Europe in 1996.

-- Advertisement --
hss

The report to Parliament recognises that, at each stage of the widening procurement, the Agency assessed the value for money of the project based on the information it had available. However, had the Agency investigated hard shoulder running earlier and been more flexible, it could have seriously considered the savings potential that hard shoulder running can offer together with any effect on benefits.

The NAO estimates the savings from a conventionally procured hard shoulder running solution might range between £400 million and £1.1 billion. The Agency, however, doubted the technique’s suitability for one of the sections of the M25 being widened which has high traffic flow and whether operation and maintenance savings could be achieved through conventional procurement. The slow progress on testing hard shoulder running, and the Agency’s commitment to widening, meant that the Agency limited its options. As a result, it did not give itself the opportunity to secure a better price for the taxpayer. The Agency is now using hard shoulder running on a number of major roads.

The full expected congestion-reducing benefits of the M25 widening project depend on the completion of techniques for managing traffic demand. Despite starting to consider these in 2003, the Agency is still testing their viability in 2010 and does not expect results until May 2012. This creates risks to maintaining the long-term benefits of the project and its potential value in cutting congestion.

Amyas Morse, Head of the NAO, said: "The Highways Agency's PFI project to widen the M25 could have achieved a materially better value for money outcome. This was partly because the slowness with which the project was taken forward subjected it to the cost effects of the credit crisis.

"The Agency should have adopted a more agile approach to procurement, recognizing the potential for making savings using an alternative method of relieving congestion, hard shoulder running. The Agency should have kept its contracting approach open to allow the use of this method."

(CD)

Latest Construction News

21/11/2024

Europe's leading online cleanroom consumables supplier, Cleanroomshop, has recently launched a brand-new website, giving its users an improved user experience. The new website continues to offer over 2,000 products from more than 40 brands, whilst incorporating a new look and more efficient ...
21/11/2024

At Ecomerchant, we offer a carefully curated selection of sustainable weatherproofing solutions, including natural lime renders, mineral finishes, and vapour-open waterproofing materials. They help prevent structural damage while ensuring your building can breathe naturally. Our eco-friendly ...
20/11/2024

Construction firm Willmott Dixon has partnered with Westminster City Council on a £36 million project to restore the historic Seymour Centre in Marylebone, a Grade II listed building dating back to the 1930s. The project, procured through the SCF framework, will see the three-storey centre undergo ...
20/11/2024

The Hill Group has commenced work on a new development in Billericay, Essex, which will deliver 179 high-quality homes across a 20-acre site. Designed to blend with Billericay's scenic countryside while addressing the pressing demand for sustainable housing, the project is located on Kennel Lane ...
20/11/2024

Extensive groundwork is underway for a new housing development in Maidstone, where Vistry Group, in partnership with Legal & General Affordable Homes, is set to build 272 properties on the site of the former Tovil Quarry off Farleigh Hill. The project will include 37 affordable homes for low-cost ...
20/11/2024

Stonewater has scooped a new energy efficiency retrofit contract with compliance and energy services provider Correct Contract Services. This work, funded through the Social Housing Decarbonisation Fund (SHDF) Wave 2, will include a range of energy-saving upgrades. Measures such as loft ...
20/11/2024

Kier has been appointed by Cambridgeshire County Council to deliver building, mechanical, and electrical maintenance services across the Council's portfolio of 160 corporate buildings. The contract, which began in November 2024, will run until 2027, with the possibility of two one-year extensions ...
20/11/2024

Builders use water for various functions on the job, they utilise this resource for worker hygiene, hydration, concrete batching, grouting, dust suppression, drilling and piling. If companies mismanage this water use, they can increase their environmental impact. When the industry comes ...
20/11/2024

Edmond Shipway has been appointed to a pioneering initiative tackling homelessness in Greater Manchester, providing project management and cost consultancy services on the second phase of Embassy Village. Set to deliver 40 purpose-built homes for men facing homelessness in Manchester, Embassy ...
20/11/2024

West Sussex County Council is inviting residents to share their views on proposed transport improvements at the Hazelwick and Tushmore junctions on the A2011 Crawley Avenue. The proposals aim to make walking, cycling, and public transport more appealing for short journeys. This initiative is part ...
Think Construction Skills Ltd.Stuart CanvasLakeside HireBRICOFLOR UKT & D Glazing And Installation LimitedEfco UK LtdAqua Direct LtdForge Lifts LtdAtlas Winch & Hoist Services Ltd (UK)Landscaping Cambridge
Terms and Conditions
2024/11/21 12:11:09