Construction News
02/06/2011
Firm Fined After Scaffold Collapse
A Surrey-based company has been fined after a large section of scaffolding collapsed at a site in Walton-on-Thames.
The Health and Safety Executive (HSE) prosecuted Johnson Scaffold Services Ltd, of Chaldon in Surrey, for breaching health and safety laws which led to the incident on the 18 December 2009.
Staines Magistrates' Court heard how Johnson Scaffold Services Ltd erected sheeted scaffolding around a building in Copenhagen Way, Surrey, to enable a separate contractor to refurbish the roof.
Once the work was completed, the structure was partially removed on 17 December 2009, leaving some of the sheeted scaffolding still standing. During the early hours of the following morning, a 200 foot long, 40 foot high section of the scaffolding was blown to the ground.
The HSE investigation showed the scaffolding was not installed according to the original drawings and had not been adequately tied. It was left in an unsafe condition overnight while being dismantled.
Johnson Scaffold Services Ltd, of Chaldon in Surrey, pleaded guilty of breaching Section 2(1) and Section 3(1) of the Health and Safety at Work Act 1974. It was fined £7,500 and ordered to pay costs of £7,000.
After the hearing, HSE's inspector Denis Bodger said: "This was a serious incident that could have resulted in severe injury or worse, it was sheer luck that meant no one was in the way of the scaffolding when it collapsed.
"Scaffolds should be designed by a competent person or built to a recognised standard. At no stage during erection, use or removal should they be left in an unstable state where they could collapse. They should be adequately tied or other effective means taken.
"This should serve as a warning to other companies that HSE will not hesitate to take action against anyone that fails to build safe scaffolding."
(CD/GK)
The Health and Safety Executive (HSE) prosecuted Johnson Scaffold Services Ltd, of Chaldon in Surrey, for breaching health and safety laws which led to the incident on the 18 December 2009.
Staines Magistrates' Court heard how Johnson Scaffold Services Ltd erected sheeted scaffolding around a building in Copenhagen Way, Surrey, to enable a separate contractor to refurbish the roof.
Once the work was completed, the structure was partially removed on 17 December 2009, leaving some of the sheeted scaffolding still standing. During the early hours of the following morning, a 200 foot long, 40 foot high section of the scaffolding was blown to the ground.
The HSE investigation showed the scaffolding was not installed according to the original drawings and had not been adequately tied. It was left in an unsafe condition overnight while being dismantled.
Johnson Scaffold Services Ltd, of Chaldon in Surrey, pleaded guilty of breaching Section 2(1) and Section 3(1) of the Health and Safety at Work Act 1974. It was fined £7,500 and ordered to pay costs of £7,000.
After the hearing, HSE's inspector Denis Bodger said: "This was a serious incident that could have resulted in severe injury or worse, it was sheer luck that meant no one was in the way of the scaffolding when it collapsed.
"Scaffolds should be designed by a competent person or built to a recognised standard. At no stage during erection, use or removal should they be left in an unstable state where they could collapse. They should be adequately tied or other effective means taken.
"This should serve as a warning to other companies that HSE will not hesitate to take action against anyone that fails to build safe scaffolding."
(CD/GK)
29/01/2025
Caddick Construction has been awarded a £43 million contract to deliver the first phase of Cole Waterhouse's flagship regeneration scheme in Digbeth, Birmingham.
The project, known as Upper Trinity Street, marks a significant step in the area’s transformation.
Spanning 182,986 square feet, the re
29/01/2025
McLaren Construction has been appointed by O&H Properties to deliver the first phase of a £60 million Foster & Partners-designed development at the corner of New Bond Street and Grafton Street in London’s West End.
The seven-storey, 5,400 square metre prime retail and office scheme will feature ret
29/01/2025
GMI Construction Group has been awarded a contract to develop three high-specification warehouse units totalling over 175,000 square feet at Precedent Drive, Milton Keynes.
The £20 million project, commissioned by DV5 Last Mile Developments (UK) Ltd, a joint venture between Coltham and Delancey Re
29/01/2025
Plans for 106 sustainable new homes in Southville, a neighbourhood in South Bristol, have been approved as the city seeks to increase housing delivery to address growing demand.
Top 10 award-winning housebuilder The Hill Group will create a £60 million development on Raleigh Road, on land that was
29/01/2025
Bouygues UK has reached a major milestone in the fourth phase of the Hallsville Quarter regeneration project in Canning Town, London.
The project, part of the £3.7 billion Canning Town and Custom House Regeneration Programme, recently held a topping out ceremony, marking the completion of the 11-s
29/01/2025
Willmott Dixon Interiors is carrying out a significant upgrade to the roof of the National Maritime Museum in Greenwich, one of London's most iconic cultural landmarks.
As part of the £12 million project, the company is installing over 23,000 square feet of sun-protected glazing above the museum’s
29/01/2025
Equans has been appointed by Babergh and Mid Suffolk District Councils to carry out crucial decarbonisation work across the councils' housing stock, using funding secured through the Social Housing Decarbonisation Fund (SHDF).
The councils used the South East Consortium's Zero Carbon Framework to s
29/01/2025
In the world of construction, the quest for energy efficiency and sustainability is ever-evolving. Among the array of solutions available, EPS (Expanded Polystyrene) insulation stands out as a versatile and effective option for enhancing the thermal performance of buildings, particularly when used f
29/01/2025
BCP Council has completed significant coastal protection works at Hamworthy Park, ensuring its resilience against erosion for the next 20 years.
A 200-metre stretch of sea wall along the eastern promenade has been reinforced using low-carbon concrete, while new steps have been constructed to improv
29/01/2025
Geo-environmental consultancy and remediation contractor, The LK Group, has strengthened its team with a trio of recruits.
The multidisciplinary company's latest raft of hires comprises a new director, associate director and remediation manager.
The geo-environmental specialist, headquartered i