Crossrail has begun drilling wells at Connaught Tunnel to draw down the water table ahead of works to deepen and widen the 130 year old tunnel in east London.
Once the wells are completed, drawing down of the water table will begin next month which is required ahead of works to widen and deepen the central section of the Connaught Tunnel so it can accommodate Crossrail's larger trains. The water table is also being lowered to allow for the pump house shaft to be deepened by another seven metres to 25 metres in order for it to accommodate modern pumping equipment that will work to keep the tunnel dry.
During the coming weeks the 130 year old pump house will be removed brick by brick and will be donated to Newham Council. This attractive Victorian building is too small to accommodate the larger modern pumping equipment that will be installed as part of the tunnel’s major refurbishment. Demolition of the former North London Line station at Silvertown has now commenced.
Works in Connaught Tunnel are well underway with the ballast – loose stone ground cover – and rail tracks already removed. Major piling works are also underway at the western approach to the tunnel in order to strengthen the ground. Survey work for to identify potential unexploded ordnance from World War II has been completed in the tunnel’s western approach with the all clear given. Crossrail’s archaeologists have opened their fourth and final trench for the site, searching for possible evidence of human activity dating back 6,000 years.
Connaught Tunnel Project Manager Linda Miller said: "Works are progressing extremely well and we are on track for turning this Victorian railway tunnel into modern infrastructure that will service London well into the next century. Major works will begin early next year after the London Boat Show, which will include placing coffer dams in the passage between Royal Victoria and Royal Albert docks, pumping out the water and performing engineering open heart surgery to widen and deepen the central section of the tunnel."
Connaught Tunnel in the Royal Docks was built in 1878 and was part of the North London Line until 2006. The tunnel will be extensively refurbished as part of works to construct Crossrail’s new Abbey Wood branch.
Sections of the existing tunnel are in a poor structural condition. In 1935, larger ships began scraping the bottom of the Royal Victoria Dock which sits above Connaught Tunnel. As part of work to deepen the dock, the central section of the tunnel was narrowed with brickwork removed and steel segments installed.
(CD/GK)
Time and date
CONSTRUCTION DIRECTORY
Latest Construction News
21/11/2024
Europe's leading online cleanroom consumables supplier, Cleanroomshop, has recently launched a brand-new website, giving its users an improved user experience. The new website continues to offer over 2,000 products from more than 40 brands, whilst incorporating a new look and more efficient ...
21/11/2024
At Ecomerchant, we offer a carefully curated selection of sustainable weatherproofing solutions, including natural lime renders, mineral finishes, and vapour-open waterproofing materials. They help prevent structural damage while ensuring your building can breathe naturally. Our eco-friendly ...
20/11/2024
Construction firm Willmott Dixon has partnered with Westminster City Council on a £36 million project to restore the historic Seymour Centre in Marylebone, a Grade II listed building dating back to the 1930s. The project, procured through the SCF framework, will see the three-storey centre undergo ...
20/11/2024
The Hill Group has commenced work on a new development in Billericay, Essex, which will deliver 179 high-quality homes across a 20-acre site. Designed to blend with Billericay's scenic countryside while addressing the pressing demand for sustainable housing, the project is located on Kennel Lane ...
20/11/2024
Extensive groundwork is underway for a new housing development in Maidstone, where Vistry Group, in partnership with Legal & General Affordable Homes, is set to build 272 properties on the site of the former Tovil Quarry off Farleigh Hill. The project will include 37 affordable homes for low-cost ...
20/11/2024
Stonewater has scooped a new energy efficiency retrofit contract with compliance and energy services provider Correct Contract Services. This work, funded through the Social Housing Decarbonisation Fund (SHDF) Wave 2, will include a range of energy-saving upgrades. Measures such as loft ...
20/11/2024
Kier has been appointed by Cambridgeshire County Council to deliver building, mechanical, and electrical maintenance services across the Council's portfolio of 160 corporate buildings. The contract, which began in November 2024, will run until 2027, with the possibility of two one-year extensions ...
20/11/2024
Builders use water for various functions on the job, they utilise this resource for worker hygiene, hydration, concrete batching, grouting, dust suppression, drilling and piling. If companies mismanage this water use, they can increase their environmental impact. When the industry comes ...
20/11/2024
Edmond Shipway has been appointed to a pioneering initiative tackling homelessness in Greater Manchester, providing project management and cost consultancy services on the second phase of Embassy Village. Set to deliver 40 purpose-built homes for men facing homelessness in Manchester, Embassy ...
20/11/2024
West Sussex County Council is inviting residents to share their views on proposed transport improvements at the Hazelwick and Tushmore junctions on the A2011 Crawley Avenue. The proposals aim to make walking, cycling, and public transport more appealing for short journeys. This initiative is part ...