NFB And npower Join Forces To Improve New Connections Process
The National Federation of Builders (NFB) and leading energy supplier npower are working together to help improve the gas and power connection process for new builds.
The two organisations hope to streamline the new connections process by highlighting the importance of good communication channels between contractors and utility companies.
The collaboration follows separate research from both the NFB and npower that highlighted delays in getting newly built or refurbished sites connected to the gas or power network due to a lack of communication between contractors and utility companies. Research released in November 2011 by npower found that nearly a quarter of businesses moving into new properties are facing delays because the connection process had not been factored in early enough.
An NFB report released in January 2012 showed that construction firms feel disconnected from utility companies and nearly three quarters, 73 per cent, of construction sites run by members of the NFB are experiencing problems and delays when seeking new connections to water, gas and electricity networks.
Nick Lewis, new connections manager at npower, said: "We are pleased to be working with the NFB to highlight the importance of good communication and forward planning when it comes to new connections. Given the current economic climate, building contractors and businesses moving into new properties cannot afford to face avoidable delays.
"As such, both npower and the NFB are committed to improving the new connections process. That’s why at npower, we provide a single point of contact so communication is clear throughout the process, ensuring it runs smoothly and on time."
Julia Evans, chief executive of the NFB, added: "It is welcoming to see a key player in the utilities sector address some of the issues raised by the NFB report. Ensuring better communication is a fundamentally important step to improving standards in the industry and we are pleased to be working in partnership with npower when it comes to avoiding delays in new connections - our priority is to ensure better communications and a more reliable service for the construction industry."
(CD)
The two organisations hope to streamline the new connections process by highlighting the importance of good communication channels between contractors and utility companies.
The collaboration follows separate research from both the NFB and npower that highlighted delays in getting newly built or refurbished sites connected to the gas or power network due to a lack of communication between contractors and utility companies. Research released in November 2011 by npower found that nearly a quarter of businesses moving into new properties are facing delays because the connection process had not been factored in early enough.
An NFB report released in January 2012 showed that construction firms feel disconnected from utility companies and nearly three quarters, 73 per cent, of construction sites run by members of the NFB are experiencing problems and delays when seeking new connections to water, gas and electricity networks.
Nick Lewis, new connections manager at npower, said: "We are pleased to be working with the NFB to highlight the importance of good communication and forward planning when it comes to new connections. Given the current economic climate, building contractors and businesses moving into new properties cannot afford to face avoidable delays.
"As such, both npower and the NFB are committed to improving the new connections process. That’s why at npower, we provide a single point of contact so communication is clear throughout the process, ensuring it runs smoothly and on time."
Julia Evans, chief executive of the NFB, added: "It is welcoming to see a key player in the utilities sector address some of the issues raised by the NFB report. Ensuring better communication is a fundamentally important step to improving standards in the industry and we are pleased to be working in partnership with npower when it comes to avoiding delays in new connections - our priority is to ensure better communications and a more reliable service for the construction industry."
(CD)
05/02/2025
Stockport Mayoral Development Corporation (MDC) and ECF, a joint venture between Homes England, Legal & General, and Muse, have selected Vinci as the preferred contractor for Phase 1 of Stockport 8, a £350 million residential development west of Stockport town centre.
The decision follows a competi
05/02/2025
Vistry Group has finalised contracts for a significant housing development in Hinckley, Leicestershire, securing outline planning permission to deliver 475 new homes in the area.
The development, located east of Stoke Road and north of Normandy Way in the town's northern region, has a projected val
05/02/2025
Wilten Construction has been awarded a second Design and Build contract at Gateway 14 by client Gateway 14 Ltd and Jaynic.
The project involves the development of a state-of-the-art, three-storey Skills and Innovation Centre spanning 35,000 sq ft in the heart of Gateway 14. Designed to achieve BREE
05/02/2025
Knowsley Council has approved a major housing development in Kirkby, giving the green light to 800 new energy-efficient homes in the town's centre.
The decision also secures £7.7 million in Section 106 contributions from developer Barratt David Wilson Homes, further boosting local investment.
The
05/02/2025
Keepmoat Homes has announced plans to invest over £50 million in three new housing developments across Calderdale, aiming to deliver more than 200 new homes.
The developments, undertaken in partnership with Calderdale Council, form part of the North Halifax Transformation Programme, a local authori
05/02/2025
Essential renewal work at Skerne Road level crossing in Driffield has been completed. Over a six-day period, engineers replaced decades-old equipment, installing a state-of-the-art operating system, replacing the level crossing deck, and resurfacing the road.
The newly installed operating system is
05/02/2025
Construction firm GRAHAM is currently carrying out essential restoration work at the National Railway Museum in York, replacing the Grade II listed roof structure at Station Hall.
Originally built between 1875 and 1877 as a goods station, Station Hall now houses the museum’s six royal carriages.
05/02/2025
Mezzanine floors are commonly associated with additional storage or expanded floor space, but did you know they can also have a profound impact on employee productivity and morale? At Doity Engineering, we specialise in designing and installing mezzanine floors for
05/02/2025
Construction work is commencing on a new solar array at Weeton Barracks in Lancashire that will generate over one third of the site’s energy needs.
The work has been funded under the British Army’s Project Prometheus, a scheme that is increasing renewable energy across the army estate through inst
05/02/2025
The regeneration of Hartlepool's waterfront has reached a significant milestone with a £631,000 grant from The National Lottery Heritage Fund.
The funding will support the development phase of the 'Tides of Change' project, aimed at transforming the visitor experience at the Museum of Hartlepool a