Construction UK Construction Directory
Time and date
CONSTRUCTION DIRECTORY
Share this page
Construction News
31/07/2012

CDM, Paperwork & Competence

Why all the paper?

As a practising health and safety professional and CDM co-ordinator it continues to confound Callsafe Services Limited as to organisations’ and construction projects’ preoccupation with paperwork and the desire to preclude any liabilities.


Callsafe Services Limited has been providing advice, assistance and training to our clients, and our clients’ projects, for nearly 25 years. Our clients have included many central and local government organisations, as well as private industry clients, designers and contractors.

The following article expresses the concerns of Callsafe Services Limited with the application of the Construction (Design and Management) Regulations 2007 (CDM), its Approved Code of Practice, L144, Managing health and safety in construction, and what could be considered to be best practice, with, where possible, suggested improvements to the way construction project health and safety is managed. We concur with the findings of Professor Ragnar Löfstedt, and presented in his report, that the CDM regulations are generally useful and proportionate, but that the application of the regulations on projects are not universally either useful or proportionate. The author’s words, rather than Professor Löfstedt’s.

Our first concern is the method of competence assessment still applied within the industry, based on the requirements L144, Appendix 4. If the elements of Appendix 4 are all questioned and answered as part of a particular project’s procurement, the effort and paper required to achieve this is extraordinary. It is accepted that competence is an essential element of effective health and safety management, but why are many organisations still preferring to utilise their specifically developed assessment systems rather than using industry accreditations, as exemplified by ‘Safety Schemes in Procurement’ (SSIP)?. SSIP only addresses stage 1 of the Appendix 4 competence assessment, but this is the most difficult part of the assessment with regards to effort, cost and paper. If SSIP accreditation is accepted by the majority of procuring organisations we will all be able to concentrate on the specific project issues, such as the competence of proposed personnel to the project and the resources allocated.

-- Advertisement --
hss

The continuing reliance on documents is demonstrated clearly by the methods used to disseminate the pre-construction information (PCI). Most projects still produce the PCI as a document to accompany the contractors’ tender documents. It is the author’s belief that this does not comply with the PCI requirements of CDM. This is because the PCI is not only required to inform the contractors, it is also required to inform the designers and design.

This lack of focus on what is necessary was demonstrated on a ‘design & build’ project for which Callsafe Services Limited was appointed as CDM co-ordinator. The principal contractor had been involved in the project planning and design from commencement of detailed design, but still requested a PCI document prior to him producing the construction phase plan (CPP). The principal contractor, after some discussion, agreed that he did not need a PCI document, as he already had in his possession all of the information. If tenders are being prepared, a PCI document still makes sense, but if the project delivery team are all in place at an early stage in the project, e.g. with early contractor involvement (ECI), a document/information register, with distributions, would make more sense and would actually be useful.

It is also unfortunate that many of these PCI documents contain much ‘generic’ information, and not enough project/site-specific information. Many of these documents contain many pages, sometimes plus 100 pages, which makes it very difficult to extract the important information from that which is already known by competent designers and contractors.

The Approved Code of Practice, L144, is not clear as to the uses of the PCI, as it states in paragraphs 55 and 56 that the PCI must be provided to designers and contractors who may be bidding for the work (or who they intend to engage). If an amendment to the Approved Code of Practice is to be made, this could usefully be clarified to include ‘all designers and contractors tendering for the work or working on the project’.

Designers are producing many and varied ‘design risk assessments’, ‘design risk registers’, ‘design hazard inventories’, and many other varieties of paper evidence of their compliance with the designers’ duties under CDM. The question has to be asked as to why they are doing this? The regulations do not require these documents to be produced, only that the designers should supply information to any person affected about the design, the significant residual risks, the designers’ assumptions and any difficulties associated with materials specified, subsequent to attempting, so far as reasonably practicable, to eliminate and reduce risks by their design decisions. Most of this documentation is produced to be able to demonstrate to anyone criticising the design or attempting to prosecute or sue the designer that they have considered the risks. This is understandable, and the documents can be useful when performing design co-ordination and design review, although it is suggested that they could be simplified and made more useful. The other questions relating to the designers’ duties are why so many aspects of the design are incorporated just because they had been used before; and the extent to which designers have to inform competent contractors of significant risks remaining? Do we really need to inform the competent contractor that falling 5 metres is likely to cause harm?

It is incumbent on ALL designers to co-operate with, and co-ordinate their designs with, other designers. This not only applies between the permanent works designers, but includes temporary works designers. Client procurement arrangements must allow this design co-operation and co-ordination to take place, e.g. where there is a design interface the designers of that interface need to be working on the project at the same time, or at least with an overlap.

David Carr, PgD, FIIRSM, DipSM, RFaPS, Registered Consultant

Callsafe Services Limited, Yardley House, 11 Horsefair, Rugeley, Staffordshire. WS15 2EJ

enquiries@callsafe-services.co.uk

www.callsafe-servcies.co.uk

Latest Construction News

21/11/2024

Europe's leading online cleanroom consumables supplier, Cleanroomshop, has recently launched a brand-new website, giving its users an improved user experience. The new website continues to offer over 2,000 products from more than 40 brands, whilst incorporating a new look and more efficient ...
20/11/2024

Construction firm Willmott Dixon has partnered with Westminster City Council on a £36 million project to restore the historic Seymour Centre in Marylebone, a Grade II listed building dating back to the 1930s. The project, procured through the SCF framework, will see the three-storey centre undergo ...
20/11/2024

The Hill Group has commenced work on a new development in Billericay, Essex, which will deliver 179 high-quality homes across a 20-acre site. Designed to blend with Billericay's scenic countryside while addressing the pressing demand for sustainable housing, the project is located on Kennel Lane ...
20/11/2024

Extensive groundwork is underway for a new housing development in Maidstone, where Vistry Group, in partnership with Legal & General Affordable Homes, is set to build 272 properties on the site of the former Tovil Quarry off Farleigh Hill. The project will include 37 affordable homes for low-cost ...
20/11/2024

Stonewater has scooped a new energy efficiency retrofit contract with compliance and energy services provider Correct Contract Services. This work, funded through the Social Housing Decarbonisation Fund (SHDF) Wave 2, will include a range of energy-saving upgrades. Measures such as loft ...
20/11/2024

Kier has been appointed by Cambridgeshire County Council to deliver building, mechanical, and electrical maintenance services across the Council's portfolio of 160 corporate buildings. The contract, which began in November 2024, will run until 2027, with the possibility of two one-year extensions ...
20/11/2024

Builders use water for various functions on the job, they utilise this resource for worker hygiene, hydration, concrete batching, grouting, dust suppression, drilling and piling. If companies mismanage this water use, they can increase their environmental impact. When the industry comes ...
20/11/2024

Edmond Shipway has been appointed to a pioneering initiative tackling homelessness in Greater Manchester, providing project management and cost consultancy services on the second phase of Embassy Village. Set to deliver 40 purpose-built homes for men facing homelessness in Manchester, Embassy ...
20/11/2024

West Sussex County Council is inviting residents to share their views on proposed transport improvements at the Hazelwick and Tushmore junctions on the A2011 Crawley Avenue. The proposals aim to make walking, cycling, and public transport more appealing for short journeys. This initiative is part ...
19/11/2024

McLaren Construction has commenced works at the first UK industrial scheme in the East Midlands for a joint venture with Garbe Industrial Real Estate GmbH and Invesco Real Estate. McLaren will oversee all aspects of construction for the £30 million project located in Shireoaks, Worksop - in the ...
T & D Glazing And Installation LimitedBRICOFLOR UKThink Construction Skills Ltd.Stuart CanvasEfco UK LtdLakeside HireAqua Direct LtdPear StairsPTP Architects London LtdQRMS
Terms and Conditions
2024/11/21 11:51:28