05/08/2013
Construction Firm And Director Fined For House Failings
A Buckinghamshire construction company and its managing director have been fined for multiple safety failings following the total collapse of two large properties in Westminster.
The buildings, on Fulham Road, were reduced to rubble in January 2011 and neighbouring properties sustained serious structural damage.
Ethos Construction Solutions Limited, of Chesham, and sole director Pritish Lad, from Middlesex, were prosecuted by the Health and Safety Executive (HSE) after an investigation revealed a catalogue of serious issues.
Westminster Magistrates' Court heard that Ethos Construction, led by Mr Lad, was the principal contractor for a major project to renovate and refurbish a self-contained block of 14 buildings on Fulham Road to create 56 new apartments and 13 commercial units.
Numbers 270 and 280, adjoining properties, collapsed without warning on Sunday 23 January. The weekend timing meant there was no work activity and nobody was on site.
The fallen rubble and debris took several days to clear and Fulham Road was partially closed for several weeks while neighbouring buildings, some of which were left in a 'dangerous' state, were checked and made safe.
A Prohibition Notice was put in place to stop the resumption of the renovation project until the site was declared as safe and stable.
HSE inspectors identified a number of safety failings in investigating the collapse. They included:
• Allowing existing structures to become weak and unstable. There was evidence of renovation activity within the collapsed buildings, including work on party walls and the demolition of rear extensions.
• Not assessing whether there was any evidence of a collapse risk.
• No temporary works plan for workers and no checks on whether workers were sufficiently trained and competent to undertake the work.
• The storage of large piles of bricks on several floors of still-standing buildings, which posed a potential over-loading risk.
• The poor installation and positioning of building props.
In addition, HSE also identified further issues elsewhere, including: an unsafe excavation up to three metres deep running the entire length of the development site; risks concerning working at height; fire risks because flammable materials were poorly stored and controlled; a failure to provide suitable emergency exits; insufficient fire detection and fire fighting equipment; and inadequate site security.
Two further Prohibition Notices were served to immediately stop unsafe activity.
Magistrates were told there was overwhelming evidence of dangerous working practices and poor planning and management, for which the principal contractor and director were ultimately responsible as duty holders.
Ethos Construction Solutions Limited, of High Street, Chesham, Bucks, was fined a total of £14,000 and ordered to pay a further £9,000 in costs after pleading guilty to six separate breaches of the Construction (Design and Management) Regulations 2007 and a single breach of Work at Height Regulations 2005.
Pritish Lad, 34, of The Avenue, Hatch End, Pinner, Middlesex, pleaded guilty to five separate breaches of the Construction (Design and Management) Regulations 2007 and the same Work at Height breach. He was fined a total of £9,500 with costs of £6,750.
(CD/MH)
The buildings, on Fulham Road, were reduced to rubble in January 2011 and neighbouring properties sustained serious structural damage.
Ethos Construction Solutions Limited, of Chesham, and sole director Pritish Lad, from Middlesex, were prosecuted by the Health and Safety Executive (HSE) after an investigation revealed a catalogue of serious issues.
Westminster Magistrates' Court heard that Ethos Construction, led by Mr Lad, was the principal contractor for a major project to renovate and refurbish a self-contained block of 14 buildings on Fulham Road to create 56 new apartments and 13 commercial units.
Numbers 270 and 280, adjoining properties, collapsed without warning on Sunday 23 January. The weekend timing meant there was no work activity and nobody was on site.
The fallen rubble and debris took several days to clear and Fulham Road was partially closed for several weeks while neighbouring buildings, some of which were left in a 'dangerous' state, were checked and made safe.
A Prohibition Notice was put in place to stop the resumption of the renovation project until the site was declared as safe and stable.
HSE inspectors identified a number of safety failings in investigating the collapse. They included:
• Allowing existing structures to become weak and unstable. There was evidence of renovation activity within the collapsed buildings, including work on party walls and the demolition of rear extensions.
• Not assessing whether there was any evidence of a collapse risk.
• No temporary works plan for workers and no checks on whether workers were sufficiently trained and competent to undertake the work.
• The storage of large piles of bricks on several floors of still-standing buildings, which posed a potential over-loading risk.
• The poor installation and positioning of building props.
In addition, HSE also identified further issues elsewhere, including: an unsafe excavation up to three metres deep running the entire length of the development site; risks concerning working at height; fire risks because flammable materials were poorly stored and controlled; a failure to provide suitable emergency exits; insufficient fire detection and fire fighting equipment; and inadequate site security.
Two further Prohibition Notices were served to immediately stop unsafe activity.
Magistrates were told there was overwhelming evidence of dangerous working practices and poor planning and management, for which the principal contractor and director were ultimately responsible as duty holders.
Ethos Construction Solutions Limited, of High Street, Chesham, Bucks, was fined a total of £14,000 and ordered to pay a further £9,000 in costs after pleading guilty to six separate breaches of the Construction (Design and Management) Regulations 2007 and a single breach of Work at Height Regulations 2005.
Pritish Lad, 34, of The Avenue, Hatch End, Pinner, Middlesex, pleaded guilty to five separate breaches of the Construction (Design and Management) Regulations 2007 and the same Work at Height breach. He was fined a total of £9,500 with costs of £6,750.
(CD/MH)
29/01/2025
Caddick Construction has been awarded a £43 million contract to deliver the first phase of Cole Waterhouse's flagship regeneration scheme in Digbeth, Birmingham.
The project, known as Upper Trinity Street, marks a significant step in the area’s transformation.
Spanning 182,986 square feet, the re
29/01/2025
McLaren Construction has been appointed by O&H Properties to deliver the first phase of a £60 million Foster & Partners-designed development at the corner of New Bond Street and Grafton Street in London’s West End.
The seven-storey, 5,400 square metre prime retail and office scheme will feature ret
29/01/2025
GMI Construction Group has been awarded a contract to develop three high-specification warehouse units totalling over 175,000 square feet at Precedent Drive, Milton Keynes.
The £20 million project, commissioned by DV5 Last Mile Developments (UK) Ltd, a joint venture between Coltham and Delancey Re
29/01/2025
Plans for 106 sustainable new homes in Southville, a neighbourhood in South Bristol, have been approved as the city seeks to increase housing delivery to address growing demand.
Top 10 award-winning housebuilder The Hill Group will create a £60 million development on Raleigh Road, on land that was
29/01/2025
Bouygues UK has reached a major milestone in the fourth phase of the Hallsville Quarter regeneration project in Canning Town, London.
The project, part of the £3.7 billion Canning Town and Custom House Regeneration Programme, recently held a topping out ceremony, marking the completion of the 11-s
29/01/2025
Willmott Dixon Interiors is carrying out a significant upgrade to the roof of the National Maritime Museum in Greenwich, one of London's most iconic cultural landmarks.
As part of the £12 million project, the company is installing over 23,000 square feet of sun-protected glazing above the museum’s
29/01/2025
Equans has been appointed by Babergh and Mid Suffolk District Councils to carry out crucial decarbonisation work across the councils' housing stock, using funding secured through the Social Housing Decarbonisation Fund (SHDF).
The councils used the South East Consortium's Zero Carbon Framework to s
29/01/2025
In the world of construction, the quest for energy efficiency and sustainability is ever-evolving. Among the array of solutions available, EPS (Expanded Polystyrene) insulation stands out as a versatile and effective option for enhancing the thermal performance of buildings, particularly when used f
29/01/2025
BCP Council has completed significant coastal protection works at Hamworthy Park, ensuring its resilience against erosion for the next 20 years.
A 200-metre stretch of sea wall along the eastern promenade has been reinforced using low-carbon concrete, while new steps have been constructed to improv
29/01/2025
Geo-environmental consultancy and remediation contractor, The LK Group, has strengthened its team with a trio of recruits.
The multidisciplinary company's latest raft of hires comprises a new director, associate director and remediation manager.
The geo-environmental specialist, headquartered i