National Grid Begins Second Phase Of £30m Project
National Grid has started the second phase of a £30m project to upgrading a power line across Cumbria and Lancashire.
New wires are being installed and steelwork repaired and renewed on the 345 pylons which make up the 116km long electricity transmission line which runs south from a substation at Harker, near Carlisle to a substation at Old Hutton near Kendal and then on to a point on the national grid system at Quernmore in Lancashire.
Once the project is complete, more than 300 tons of steelwork will have been replaced and more than 1,000km of new wires suspended on the pylons.
Work to replace the wires on one side of the pylons is now complete and engineers have just started work on the wires on the other side. The project is very challenging, given that much of the line is in countryside exposed to the elements. The line also crosses five rail lines including the West Coast Main Line and the M6 motorway in two places.
At present, a total of 200 engineers are currently working on the project and, through efficient working practices, will complete the upgrade in just one year, instead of the two which work on this scale would normally take. This will result in a saving to the company of around £10m.
This line is just a small part of the massive network of overhead lines, underground cables and substations that carry high voltage electricity across the country. The investment will keep the lines in good working order to ensure that everyone has the power they need, safely, and at the touch of a button.
The work will also allow National Grid to increase the efficiency of the line once a project to install some new equipment at the substation at Old Hutton is also complete.
The work on the line is expected to be completed by November and temporary offices and working areas around pylons removed by April next year. There will be no interruption to electricity supplies during the work.
In preparing for work on the overhead line, National Grid has liaised with local authorities, the Environment Agency and Natural England, amongst others.
William Fenton, Project Manager said: "We are delighted with the progress we are making to date on this project. By using our teams of engineers and their ground support teams more efficiently, we’re on target to complete this job in just a year – quite an undertaking when you consider the length of the line and the terrain it crosses.
"We're grateful for the patience people have shown during our work – particularly the local landowners who have pylons situated on their land."
(CD/JP)
New wires are being installed and steelwork repaired and renewed on the 345 pylons which make up the 116km long electricity transmission line which runs south from a substation at Harker, near Carlisle to a substation at Old Hutton near Kendal and then on to a point on the national grid system at Quernmore in Lancashire.
Once the project is complete, more than 300 tons of steelwork will have been replaced and more than 1,000km of new wires suspended on the pylons.
Work to replace the wires on one side of the pylons is now complete and engineers have just started work on the wires on the other side. The project is very challenging, given that much of the line is in countryside exposed to the elements. The line also crosses five rail lines including the West Coast Main Line and the M6 motorway in two places.
At present, a total of 200 engineers are currently working on the project and, through efficient working practices, will complete the upgrade in just one year, instead of the two which work on this scale would normally take. This will result in a saving to the company of around £10m.
This line is just a small part of the massive network of overhead lines, underground cables and substations that carry high voltage electricity across the country. The investment will keep the lines in good working order to ensure that everyone has the power they need, safely, and at the touch of a button.
The work will also allow National Grid to increase the efficiency of the line once a project to install some new equipment at the substation at Old Hutton is also complete.
The work on the line is expected to be completed by November and temporary offices and working areas around pylons removed by April next year. There will be no interruption to electricity supplies during the work.
In preparing for work on the overhead line, National Grid has liaised with local authorities, the Environment Agency and Natural England, amongst others.
William Fenton, Project Manager said: "We are delighted with the progress we are making to date on this project. By using our teams of engineers and their ground support teams more efficiently, we’re on target to complete this job in just a year – quite an undertaking when you consider the length of the line and the terrain it crosses.
"We're grateful for the patience people have shown during our work – particularly the local landowners who have pylons situated on their land."
(CD/JP)
05/02/2025
Stockport Mayoral Development Corporation (MDC) and ECF, a joint venture between Homes England, Legal & General, and Muse, have selected Vinci as the preferred contractor for Phase 1 of Stockport 8, a £350 million residential development west of Stockport town centre.
The decision follows a competi
05/02/2025
Vistry Group has finalised contracts for a significant housing development in Hinckley, Leicestershire, securing outline planning permission to deliver 475 new homes in the area.
The development, located east of Stoke Road and north of Normandy Way in the town's northern region, has a projected val
05/02/2025
Wilten Construction has been awarded a second Design and Build contract at Gateway 14 by client Gateway 14 Ltd and Jaynic.
The project involves the development of a state-of-the-art, three-storey Skills and Innovation Centre spanning 35,000 sq ft in the heart of Gateway 14. Designed to achieve BREE
05/02/2025
Knowsley Council has approved a major housing development in Kirkby, giving the green light to 800 new energy-efficient homes in the town's centre.
The decision also secures £7.7 million in Section 106 contributions from developer Barratt David Wilson Homes, further boosting local investment.
The
05/02/2025
Keepmoat Homes has announced plans to invest over £50 million in three new housing developments across Calderdale, aiming to deliver more than 200 new homes.
The developments, undertaken in partnership with Calderdale Council, form part of the North Halifax Transformation Programme, a local authori
05/02/2025
Essential renewal work at Skerne Road level crossing in Driffield has been completed. Over a six-day period, engineers replaced decades-old equipment, installing a state-of-the-art operating system, replacing the level crossing deck, and resurfacing the road.
The newly installed operating system is
05/02/2025
Construction firm GRAHAM is currently carrying out essential restoration work at the National Railway Museum in York, replacing the Grade II listed roof structure at Station Hall.
Originally built between 1875 and 1877 as a goods station, Station Hall now houses the museum’s six royal carriages.
05/02/2025
Mezzanine floors are commonly associated with additional storage or expanded floor space, but did you know they can also have a profound impact on employee productivity and morale? At Doity Engineering, we specialise in designing and installing mezzanine floors for
05/02/2025
Construction work is commencing on a new solar array at Weeton Barracks in Lancashire that will generate over one third of the site’s energy needs.
The work has been funded under the British Army’s Project Prometheus, a scheme that is increasing renewable energy across the army estate through inst
05/02/2025
The regeneration of Hartlepool's waterfront has reached a significant milestone with a £631,000 grant from The National Lottery Heritage Fund.
The funding will support the development phase of the 'Tides of Change' project, aimed at transforming the visitor experience at the Museum of Hartlepool a