Construction News
18/02/2014
Early Handover Of Western Ticket Hall Box
The Costain Skanska joint venture's (CSJV) record of success on Crossrail has continued with the early hand over of the Western Ticket Hall Box at Bond Street.
The handover was accomplished six weeks ahead of schedule. The earlier Eastern Ticket Hall, completed in 2012, was four weeks ahead of plan.
Bond Street will be one of six new central London stations serving the new high-frequency rail route which will stretch from Maidenhead in the west to Shenfield and Abbey Wood in the east. It is due to become operational in 2018.
The Western Ticket Hall descends through five levels, in a vast concrete construction measuring 70m x 30m x 26m in the heart of London’s West End.
Work on the hall began in August 2011 with an intensive 12-month diaphragm walling and piling programme, followed by 17 months of complex dewatering, temporary works, and top-down construction earthworks and reinforced concrete works.
During construction some 220,000 tonnes of London clay was excavated from the 30m deep box, and 70,000m³ of concrete was used for diaphragm walling, piling and slab construction works.
These works were undertaken in the heart of London's Mayfair Conservation Area and came within one metre of London Underground’s Jubilee Line tunnels. The joint venture team has also had to cope with the problems of logistics and proximity to occupied buildings common to central London contracts.
(CD/MH)
The handover was accomplished six weeks ahead of schedule. The earlier Eastern Ticket Hall, completed in 2012, was four weeks ahead of plan.
Bond Street will be one of six new central London stations serving the new high-frequency rail route which will stretch from Maidenhead in the west to Shenfield and Abbey Wood in the east. It is due to become operational in 2018.
The Western Ticket Hall descends through five levels, in a vast concrete construction measuring 70m x 30m x 26m in the heart of London’s West End.
Work on the hall began in August 2011 with an intensive 12-month diaphragm walling and piling programme, followed by 17 months of complex dewatering, temporary works, and top-down construction earthworks and reinforced concrete works.
During construction some 220,000 tonnes of London clay was excavated from the 30m deep box, and 70,000m³ of concrete was used for diaphragm walling, piling and slab construction works.
These works were undertaken in the heart of London's Mayfair Conservation Area and came within one metre of London Underground’s Jubilee Line tunnels. The joint venture team has also had to cope with the problems of logistics and proximity to occupied buildings common to central London contracts.
(CD/MH)
29/01/2025
Caddick Construction has been awarded a £43 million contract to deliver the first phase of Cole Waterhouse's flagship regeneration scheme in Digbeth, Birmingham.
The project, known as Upper Trinity Street, marks a significant step in the area’s transformation.
Spanning 182,986 square feet, the re
29/01/2025
McLaren Construction has been appointed by O&H Properties to deliver the first phase of a £60 million Foster & Partners-designed development at the corner of New Bond Street and Grafton Street in London’s West End.
The seven-storey, 5,400 square metre prime retail and office scheme will feature ret
29/01/2025
GMI Construction Group has been awarded a contract to develop three high-specification warehouse units totalling over 175,000 square feet at Precedent Drive, Milton Keynes.
The £20 million project, commissioned by DV5 Last Mile Developments (UK) Ltd, a joint venture between Coltham and Delancey Re
29/01/2025
Plans for 106 sustainable new homes in Southville, a neighbourhood in South Bristol, have been approved as the city seeks to increase housing delivery to address growing demand.
Top 10 award-winning housebuilder The Hill Group will create a £60 million development on Raleigh Road, on land that was
29/01/2025
Bouygues UK has reached a major milestone in the fourth phase of the Hallsville Quarter regeneration project in Canning Town, London.
The project, part of the £3.7 billion Canning Town and Custom House Regeneration Programme, recently held a topping out ceremony, marking the completion of the 11-s
29/01/2025
Willmott Dixon Interiors is carrying out a significant upgrade to the roof of the National Maritime Museum in Greenwich, one of London's most iconic cultural landmarks.
As part of the £12 million project, the company is installing over 23,000 square feet of sun-protected glazing above the museum’s
29/01/2025
Equans has been appointed by Babergh and Mid Suffolk District Councils to carry out crucial decarbonisation work across the councils' housing stock, using funding secured through the Social Housing Decarbonisation Fund (SHDF).
The councils used the South East Consortium's Zero Carbon Framework to s
29/01/2025
In the world of construction, the quest for energy efficiency and sustainability is ever-evolving. Among the array of solutions available, EPS (Expanded Polystyrene) insulation stands out as a versatile and effective option for enhancing the thermal performance of buildings, particularly when used f
29/01/2025
BCP Council has completed significant coastal protection works at Hamworthy Park, ensuring its resilience against erosion for the next 20 years.
A 200-metre stretch of sea wall along the eastern promenade has been reinforced using low-carbon concrete, while new steps have been constructed to improv
29/01/2025
Geo-environmental consultancy and remediation contractor, The LK Group, has strengthened its team with a trio of recruits.
The multidisciplinary company's latest raft of hires comprises a new director, associate director and remediation manager.
The geo-environmental specialist, headquartered i