24/03/2014
London Bridge Station Refurb Remains On Schedule
Work on the project to completely refurbish London Bridge Station is proceeding on schedule.
The scope of the contract includes removal of the existing roof, complete demolition of all the platforms and the formation of a new concourse at ground level that will be the size of the pitch at Wembley Stadium. This will not only increase the capacity of the station but also make it suitable for 21st century travellers.
"We're rebuilding the whole station through nine phases of work," said Delivery Director Clive Loosemore. "We've demolished three platforms completely, as well as demolishing the existing brick arches that supported these platforms, as part of Stage 1.
"To ensure that both the schedule and quality are maintained, major sections of the new platforms and the iconic 'eyebrow' canopies are being prefabricated off-site.
"Our canopy steel subcontractors, Prater/Watsons, created a 60-metre mock-up of the canopy steelwork and cladding at their premises at Thirsk about six months ago and used it as both a training ground for the people who would be erecting it and also allowing all stakeholders including the end-user to have the opportunity of viewing it and contributing to the final design.
"They put it together in a couple of weeks. We were then able to take the end-users, the railway systems and maintenance people up there to have a look, as well as the architects, and get it agreed. Then we went into fabrication. The canopy prefabrication takes place in Bolton."
Work on the canopy is split between three subcontractors, Watsons handling the steelwork and Praters constructing the roof 'cassettes' or panels that have all the containment for the wiring systems. The containment and fittings are installed by NG Bailey. The new canopy will eventually cover 15 platforms; the sections, if laid end-to-end, would stretch 4km.
(CD/JP)
The scope of the contract includes removal of the existing roof, complete demolition of all the platforms and the formation of a new concourse at ground level that will be the size of the pitch at Wembley Stadium. This will not only increase the capacity of the station but also make it suitable for 21st century travellers.
"We're rebuilding the whole station through nine phases of work," said Delivery Director Clive Loosemore. "We've demolished three platforms completely, as well as demolishing the existing brick arches that supported these platforms, as part of Stage 1.
"To ensure that both the schedule and quality are maintained, major sections of the new platforms and the iconic 'eyebrow' canopies are being prefabricated off-site.
"Our canopy steel subcontractors, Prater/Watsons, created a 60-metre mock-up of the canopy steelwork and cladding at their premises at Thirsk about six months ago and used it as both a training ground for the people who would be erecting it and also allowing all stakeholders including the end-user to have the opportunity of viewing it and contributing to the final design.
"They put it together in a couple of weeks. We were then able to take the end-users, the railway systems and maintenance people up there to have a look, as well as the architects, and get it agreed. Then we went into fabrication. The canopy prefabrication takes place in Bolton."
Work on the canopy is split between three subcontractors, Watsons handling the steelwork and Praters constructing the roof 'cassettes' or panels that have all the containment for the wiring systems. The containment and fittings are installed by NG Bailey. The new canopy will eventually cover 15 platforms; the sections, if laid end-to-end, would stretch 4km.
(CD/JP)
29/01/2025
Caddick Construction has been awarded a £43 million contract to deliver the first phase of Cole Waterhouse's flagship regeneration scheme in Digbeth, Birmingham.
The project, known as Upper Trinity Street, marks a significant step in the area’s transformation.
Spanning 182,986 square feet, the re
29/01/2025
McLaren Construction has been appointed by O&H Properties to deliver the first phase of a £60 million Foster & Partners-designed development at the corner of New Bond Street and Grafton Street in London’s West End.
The seven-storey, 5,400 square metre prime retail and office scheme will feature ret
29/01/2025
GMI Construction Group has been awarded a contract to develop three high-specification warehouse units totalling over 175,000 square feet at Precedent Drive, Milton Keynes.
The £20 million project, commissioned by DV5 Last Mile Developments (UK) Ltd, a joint venture between Coltham and Delancey Re
29/01/2025
Plans for 106 sustainable new homes in Southville, a neighbourhood in South Bristol, have been approved as the city seeks to increase housing delivery to address growing demand.
Top 10 award-winning housebuilder The Hill Group will create a £60 million development on Raleigh Road, on land that was
29/01/2025
Bouygues UK has reached a major milestone in the fourth phase of the Hallsville Quarter regeneration project in Canning Town, London.
The project, part of the £3.7 billion Canning Town and Custom House Regeneration Programme, recently held a topping out ceremony, marking the completion of the 11-s
29/01/2025
Willmott Dixon Interiors is carrying out a significant upgrade to the roof of the National Maritime Museum in Greenwich, one of London's most iconic cultural landmarks.
As part of the £12 million project, the company is installing over 23,000 square feet of sun-protected glazing above the museum’s
29/01/2025
Equans has been appointed by Babergh and Mid Suffolk District Councils to carry out crucial decarbonisation work across the councils' housing stock, using funding secured through the Social Housing Decarbonisation Fund (SHDF).
The councils used the South East Consortium's Zero Carbon Framework to s
29/01/2025
In the world of construction, the quest for energy efficiency and sustainability is ever-evolving. Among the array of solutions available, EPS (Expanded Polystyrene) insulation stands out as a versatile and effective option for enhancing the thermal performance of buildings, particularly when used f
29/01/2025
BCP Council has completed significant coastal protection works at Hamworthy Park, ensuring its resilience against erosion for the next 20 years.
A 200-metre stretch of sea wall along the eastern promenade has been reinforced using low-carbon concrete, while new steps have been constructed to improv
29/01/2025
Geo-environmental consultancy and remediation contractor, The LK Group, has strengthened its team with a trio of recruits.
The multidisciplinary company's latest raft of hires comprises a new director, associate director and remediation manager.
The geo-environmental specialist, headquartered i