Construction News
13/05/2014
Balfour Beatty Finishes Concrete Pours
Balfour Beatty has completed the concrete pours for a feeder line box which will provide a route for freight as part of Network Rail's £45 million Reading Viaduct project to relieve rail traffic congestion in the area.
The box, which will allow freight lines from Southampton to run beneath the east-west main line railway passing over the new viaduct, requires six 900mm thick reinforced concrete decks using 3030m³ of concrete.
An additional 2000m³ of concrete has already been poured during construction of seventeen 900mm thick walls and pile caps that support the decks.
In line with Balfour Beatty's commitment to sustainability, the team used concrete with a 40% cement replacement from ground granulated blast-furnace slag (GBBS) and used recycled water in its production process. In the course of the project Balfour Beatty has been able to recycle the majority of materials generated from the site, diverting over 90% of waste from landfill.
William Smith, Balfour Beatty Project Director, said: "The team is working tirelessly to manage the concrete pours on this project. At peak we poured more than 1800m³ in one week on 13 individual key elements. We are pleased to be making such excellent progress despite the adverse weather over the winter."
All six decks that make up the feeder line box are due for completion by the end of this month.
Balfour Beatty's contract to build the new 2km viaduct commenced in January 2013 and will complete in March 2015. The main viaduct structure will be finished during the summer of 2014 and the new lines will be operational in January 2015. Over 400 people worked on the project at its peak.Balfour Beatty has completed the concrete pours for a feeder line box which will provide a route for freight as part of Network Rail's £45 million Reading Viaduct project to relieve rail traffic congestion in the area.
The box, which will allow freight lines from Southampton to run beneath the east-west main line railway passing over the new viaduct, requires six 900mm thick reinforced concrete decks using 3030m³ of concrete.
An additional 2000m³ of concrete has already been poured during construction of seventeen 900mm thick walls and pile caps that support the decks.
In line with Balfour Beatty's commitment to sustainability, the team used concrete with a 40% cement replacement from ground granulated blast-furnace slag (GBBS) and used recycled water in its production process. In the course of the project Balfour Beatty has been able to recycle the majority of materials generated from the site, diverting over 90% of waste from landfill.
(CD)
The box, which will allow freight lines from Southampton to run beneath the east-west main line railway passing over the new viaduct, requires six 900mm thick reinforced concrete decks using 3030m³ of concrete.
An additional 2000m³ of concrete has already been poured during construction of seventeen 900mm thick walls and pile caps that support the decks.
In line with Balfour Beatty's commitment to sustainability, the team used concrete with a 40% cement replacement from ground granulated blast-furnace slag (GBBS) and used recycled water in its production process. In the course of the project Balfour Beatty has been able to recycle the majority of materials generated from the site, diverting over 90% of waste from landfill.
William Smith, Balfour Beatty Project Director, said: "The team is working tirelessly to manage the concrete pours on this project. At peak we poured more than 1800m³ in one week on 13 individual key elements. We are pleased to be making such excellent progress despite the adverse weather over the winter."
All six decks that make up the feeder line box are due for completion by the end of this month.
Balfour Beatty's contract to build the new 2km viaduct commenced in January 2013 and will complete in March 2015. The main viaduct structure will be finished during the summer of 2014 and the new lines will be operational in January 2015. Over 400 people worked on the project at its peak.Balfour Beatty has completed the concrete pours for a feeder line box which will provide a route for freight as part of Network Rail's £45 million Reading Viaduct project to relieve rail traffic congestion in the area.
The box, which will allow freight lines from Southampton to run beneath the east-west main line railway passing over the new viaduct, requires six 900mm thick reinforced concrete decks using 3030m³ of concrete.
An additional 2000m³ of concrete has already been poured during construction of seventeen 900mm thick walls and pile caps that support the decks.
In line with Balfour Beatty's commitment to sustainability, the team used concrete with a 40% cement replacement from ground granulated blast-furnace slag (GBBS) and used recycled water in its production process. In the course of the project Balfour Beatty has been able to recycle the majority of materials generated from the site, diverting over 90% of waste from landfill.
(CD)
29/01/2025
Caddick Construction has been awarded a £43 million contract to deliver the first phase of Cole Waterhouse's flagship regeneration scheme in Digbeth, Birmingham.
The project, known as Upper Trinity Street, marks a significant step in the area’s transformation.
Spanning 182,986 square feet, the re
29/01/2025
McLaren Construction has been appointed by O&H Properties to deliver the first phase of a £60 million Foster & Partners-designed development at the corner of New Bond Street and Grafton Street in London’s West End.
The seven-storey, 5,400 square metre prime retail and office scheme will feature ret
29/01/2025
GMI Construction Group has been awarded a contract to develop three high-specification warehouse units totalling over 175,000 square feet at Precedent Drive, Milton Keynes.
The £20 million project, commissioned by DV5 Last Mile Developments (UK) Ltd, a joint venture between Coltham and Delancey Re
29/01/2025
Plans for 106 sustainable new homes in Southville, a neighbourhood in South Bristol, have been approved as the city seeks to increase housing delivery to address growing demand.
Top 10 award-winning housebuilder The Hill Group will create a £60 million development on Raleigh Road, on land that was
29/01/2025
Bouygues UK has reached a major milestone in the fourth phase of the Hallsville Quarter regeneration project in Canning Town, London.
The project, part of the £3.7 billion Canning Town and Custom House Regeneration Programme, recently held a topping out ceremony, marking the completion of the 11-s
29/01/2025
Willmott Dixon Interiors is carrying out a significant upgrade to the roof of the National Maritime Museum in Greenwich, one of London's most iconic cultural landmarks.
As part of the £12 million project, the company is installing over 23,000 square feet of sun-protected glazing above the museum’s
29/01/2025
Equans has been appointed by Babergh and Mid Suffolk District Councils to carry out crucial decarbonisation work across the councils' housing stock, using funding secured through the Social Housing Decarbonisation Fund (SHDF).
The councils used the South East Consortium's Zero Carbon Framework to s
29/01/2025
In the world of construction, the quest for energy efficiency and sustainability is ever-evolving. Among the array of solutions available, EPS (Expanded Polystyrene) insulation stands out as a versatile and effective option for enhancing the thermal performance of buildings, particularly when used f
29/01/2025
BCP Council has completed significant coastal protection works at Hamworthy Park, ensuring its resilience against erosion for the next 20 years.
A 200-metre stretch of sea wall along the eastern promenade has been reinforced using low-carbon concrete, while new steps have been constructed to improv
29/01/2025
Geo-environmental consultancy and remediation contractor, The LK Group, has strengthened its team with a trio of recruits.
The multidisciplinary company's latest raft of hires comprises a new director, associate director and remediation manager.
The geo-environmental specialist, headquartered i