Construction News
31/03/2015
Exceeding Building Acoustic Regulations Despite Challenging Height Constraints
Soundproofing is simple. In Theory. All you have to do is put several inches of sound resistant material in the floor or wall cavities of adjoining rooms or properties. Simple.
In reality, things tend to get a little more complicated. The fact is most cavities are just not big enough to accommodate several inches of soundproofing material. The contemporary value-engineering ethos is, quite understandably, determined to reduce the quantities of materials used and, where possible within Building Regulation controls, to reduce the heights and widths of floors and walls respectively. All of this is done in the name of delivering greater value to the customer.
This is a perfectly laudable activity but it can present a challenge to acousticians and soundproofing solutions suppliers, particularly where height constraints are applied to floors.
At McTaggart and Mickel’s award-winning Greenan Views development on the Ayrshire coastline, these height constraints presented a significant challenge. For the cottage flats that formed part of the development, a non-typical 195mm-deep I-joist was used. This meant that the typical solution of installing 78mm FFT1 acoustic bearers to meet Section 5 of the Scottish Building Standards was not possible.
Working closely with the McTaggart and Mickel team, along with Chris Steel, Senior Acoustic Consultant at the multiple award-winning Robin Mackenzie Partnership, CMS Danskin not only offered their innovative SoundDeck CLD system as a potential solution, they also offered to adapt it to meet the challenge of the development’s height restrictions.
Designed specifically for new-build, timber-frame apartment floors and ceilings, SoundDeck CLD uses the principles of Constrained Layer Damping (CLD) and comprises a timber-based, high-performance acoustic overlay board combined with an acoustic ceiling hanger. In this case, however, the ceiling hangers were replaced with resilient battens.
Installation of the 98 systems was quick and easy, with the boards installed on top of the OSB deck, with flanking strips around the perimeter, and resilient bars installed below to form the acoustic ceiling component of the system. The boards were simply glued together at the tongue and groove joints using CMS Danskin’s D3 Adhesive.
Not only did the adapted SoundDeck CLD provide the crucial 75mm height saving, it also exceeded sound insulation requirements. The project only needed to meet the pre-2010 regulations, but would have easily met the revised 2010 acoustic performance requirements.
What’s more, because it is a system and not one of a number of disparate elements, the number of deliveries, and subsequent loading-out times, was reduced, as was the amount of material on-site.
With such a positive experience of the SoundDeck CLD System on the prestigious Greenan Views development, McTaggart and Mickel and other timber-frame apartment builders could benefit from future applications of this innovative system, with the potential to reduce brick courses or enhance ceiling-to-floor heights on subsequent timber-frame apartment projects.
www.cmsdanskin.co.uk/floor-and-ceiling-soundproofing-system
In reality, things tend to get a little more complicated. The fact is most cavities are just not big enough to accommodate several inches of soundproofing material. The contemporary value-engineering ethos is, quite understandably, determined to reduce the quantities of materials used and, where possible within Building Regulation controls, to reduce the heights and widths of floors and walls respectively. All of this is done in the name of delivering greater value to the customer.
This is a perfectly laudable activity but it can present a challenge to acousticians and soundproofing solutions suppliers, particularly where height constraints are applied to floors.
At McTaggart and Mickel’s award-winning Greenan Views development on the Ayrshire coastline, these height constraints presented a significant challenge. For the cottage flats that formed part of the development, a non-typical 195mm-deep I-joist was used. This meant that the typical solution of installing 78mm FFT1 acoustic bearers to meet Section 5 of the Scottish Building Standards was not possible.
Working closely with the McTaggart and Mickel team, along with Chris Steel, Senior Acoustic Consultant at the multiple award-winning Robin Mackenzie Partnership, CMS Danskin not only offered their innovative SoundDeck CLD system as a potential solution, they also offered to adapt it to meet the challenge of the development’s height restrictions.
Designed specifically for new-build, timber-frame apartment floors and ceilings, SoundDeck CLD uses the principles of Constrained Layer Damping (CLD) and comprises a timber-based, high-performance acoustic overlay board combined with an acoustic ceiling hanger. In this case, however, the ceiling hangers were replaced with resilient battens.
Installation of the 98 systems was quick and easy, with the boards installed on top of the OSB deck, with flanking strips around the perimeter, and resilient bars installed below to form the acoustic ceiling component of the system. The boards were simply glued together at the tongue and groove joints using CMS Danskin’s D3 Adhesive.
Not only did the adapted SoundDeck CLD provide the crucial 75mm height saving, it also exceeded sound insulation requirements. The project only needed to meet the pre-2010 regulations, but would have easily met the revised 2010 acoustic performance requirements.
What’s more, because it is a system and not one of a number of disparate elements, the number of deliveries, and subsequent loading-out times, was reduced, as was the amount of material on-site.
With such a positive experience of the SoundDeck CLD System on the prestigious Greenan Views development, McTaggart and Mickel and other timber-frame apartment builders could benefit from future applications of this innovative system, with the potential to reduce brick courses or enhance ceiling-to-floor heights on subsequent timber-frame apartment projects.
www.cmsdanskin.co.uk/floor-and-ceiling-soundproofing-system
29/01/2025
Caddick Construction has been awarded a £43 million contract to deliver the first phase of Cole Waterhouse's flagship regeneration scheme in Digbeth, Birmingham.
The project, known as Upper Trinity Street, marks a significant step in the area’s transformation.
Spanning 182,986 square feet, the re
29/01/2025
McLaren Construction has been appointed by O&H Properties to deliver the first phase of a £60 million Foster & Partners-designed development at the corner of New Bond Street and Grafton Street in London’s West End.
The seven-storey, 5,400 square metre prime retail and office scheme will feature ret
29/01/2025
GMI Construction Group has been awarded a contract to develop three high-specification warehouse units totalling over 175,000 square feet at Precedent Drive, Milton Keynes.
The £20 million project, commissioned by DV5 Last Mile Developments (UK) Ltd, a joint venture between Coltham and Delancey Re
29/01/2025
Plans for 106 sustainable new homes in Southville, a neighbourhood in South Bristol, have been approved as the city seeks to increase housing delivery to address growing demand.
Top 10 award-winning housebuilder The Hill Group will create a £60 million development on Raleigh Road, on land that was
29/01/2025
Bouygues UK has reached a major milestone in the fourth phase of the Hallsville Quarter regeneration project in Canning Town, London.
The project, part of the £3.7 billion Canning Town and Custom House Regeneration Programme, recently held a topping out ceremony, marking the completion of the 11-s
29/01/2025
Willmott Dixon Interiors is carrying out a significant upgrade to the roof of the National Maritime Museum in Greenwich, one of London's most iconic cultural landmarks.
As part of the £12 million project, the company is installing over 23,000 square feet of sun-protected glazing above the museum’s
29/01/2025
Equans has been appointed by Babergh and Mid Suffolk District Councils to carry out crucial decarbonisation work across the councils' housing stock, using funding secured through the Social Housing Decarbonisation Fund (SHDF).
The councils used the South East Consortium's Zero Carbon Framework to s
29/01/2025
In the world of construction, the quest for energy efficiency and sustainability is ever-evolving. Among the array of solutions available, EPS (Expanded Polystyrene) insulation stands out as a versatile and effective option for enhancing the thermal performance of buildings, particularly when used f
29/01/2025
BCP Council has completed significant coastal protection works at Hamworthy Park, ensuring its resilience against erosion for the next 20 years.
A 200-metre stretch of sea wall along the eastern promenade has been reinforced using low-carbon concrete, while new steps have been constructed to improv
29/01/2025
Geo-environmental consultancy and remediation contractor, The LK Group, has strengthened its team with a trio of recruits.
The multidisciplinary company's latest raft of hires comprises a new director, associate director and remediation manager.
The geo-environmental specialist, headquartered i