Construction News
27/07/2015
Carillion Completes Anfield Installation
Carillion has completed the installation of a large 650 tonne roof truss over Liverpool FC's iconic Anfield Stadium.
The operation, which began at 6am on 24 July, sees the redevelopment of Anfield reach a major milestone.
The steel truss was raised onto two 28 metre high towers at either side of the Main Stand.
The lift, performed by two of the UK's largest cranes the AK680 and AK912, has finished one of the most complex parts of the Main Stand build programme.
The 252ft-high cranes were operated by a specialist team at the Anfield site, working in tandem to raise the 140 metre long truss which took several weeks to assemble.
The lift operation took a full day and follows months of detailed planning by Carillion, the Club's construction partner.
Chris Ruta, Carillion Project Director, said: "Achieving such a milestone "on time" is a just reward for the hard work and efforts of the project team."
Ian Ayre, CEO of Liverpool FC, said: "This is an historic milestone in Anfield's history as the stadium transformation continues to take shape."
The installation of the 20 metre high truss has enabled work to get underway on developing the Main Stand's new roof, as the site's cranes begin the task of lifting and securing steel roof rafters into place.
Significant progress has been made on Anfield's redevelopment since the end of the football season.
Liverpool announced the redevelopment of Anfield in December 2014 and plans to add around 8,500 seats, taking the Main Stand capacity to over 20,000 and increasing the overall capacity of Anfield to around 54,000.
The existing two storey building at the back of the Main Stand has been demolished, to allow the two structures to be connected and a two-storey podium level developed to provide supporter access into the new stand.
The Main Stand expansion project remains on target for completion during the 2016/17 season, with the redeveloped stand set to comprise three tiers and the existing lower tier re-profiled to accommodate a widened player tunnel, new team benches, media platform and wheelchair viewing positions.
(LM)
The operation, which began at 6am on 24 July, sees the redevelopment of Anfield reach a major milestone.
The steel truss was raised onto two 28 metre high towers at either side of the Main Stand.
The lift, performed by two of the UK's largest cranes the AK680 and AK912, has finished one of the most complex parts of the Main Stand build programme.
The 252ft-high cranes were operated by a specialist team at the Anfield site, working in tandem to raise the 140 metre long truss which took several weeks to assemble.
The lift operation took a full day and follows months of detailed planning by Carillion, the Club's construction partner.
Chris Ruta, Carillion Project Director, said: "Achieving such a milestone "on time" is a just reward for the hard work and efforts of the project team."
Ian Ayre, CEO of Liverpool FC, said: "This is an historic milestone in Anfield's history as the stadium transformation continues to take shape."
The installation of the 20 metre high truss has enabled work to get underway on developing the Main Stand's new roof, as the site's cranes begin the task of lifting and securing steel roof rafters into place.
Significant progress has been made on Anfield's redevelopment since the end of the football season.
Liverpool announced the redevelopment of Anfield in December 2014 and plans to add around 8,500 seats, taking the Main Stand capacity to over 20,000 and increasing the overall capacity of Anfield to around 54,000.
The existing two storey building at the back of the Main Stand has been demolished, to allow the two structures to be connected and a two-storey podium level developed to provide supporter access into the new stand.
The Main Stand expansion project remains on target for completion during the 2016/17 season, with the redeveloped stand set to comprise three tiers and the existing lower tier re-profiled to accommodate a widened player tunnel, new team benches, media platform and wheelchair viewing positions.
(LM)
29/01/2025
Caddick Construction has been awarded a £43 million contract to deliver the first phase of Cole Waterhouse's flagship regeneration scheme in Digbeth, Birmingham.
The project, known as Upper Trinity Street, marks a significant step in the area’s transformation.
Spanning 182,986 square feet, the re
29/01/2025
McLaren Construction has been appointed by O&H Properties to deliver the first phase of a £60 million Foster & Partners-designed development at the corner of New Bond Street and Grafton Street in London’s West End.
The seven-storey, 5,400 square metre prime retail and office scheme will feature ret
29/01/2025
GMI Construction Group has been awarded a contract to develop three high-specification warehouse units totalling over 175,000 square feet at Precedent Drive, Milton Keynes.
The £20 million project, commissioned by DV5 Last Mile Developments (UK) Ltd, a joint venture between Coltham and Delancey Re
29/01/2025
Plans for 106 sustainable new homes in Southville, a neighbourhood in South Bristol, have been approved as the city seeks to increase housing delivery to address growing demand.
Top 10 award-winning housebuilder The Hill Group will create a £60 million development on Raleigh Road, on land that was
29/01/2025
Bouygues UK has reached a major milestone in the fourth phase of the Hallsville Quarter regeneration project in Canning Town, London.
The project, part of the £3.7 billion Canning Town and Custom House Regeneration Programme, recently held a topping out ceremony, marking the completion of the 11-s
29/01/2025
Willmott Dixon Interiors is carrying out a significant upgrade to the roof of the National Maritime Museum in Greenwich, one of London's most iconic cultural landmarks.
As part of the £12 million project, the company is installing over 23,000 square feet of sun-protected glazing above the museum’s
29/01/2025
Equans has been appointed by Babergh and Mid Suffolk District Councils to carry out crucial decarbonisation work across the councils' housing stock, using funding secured through the Social Housing Decarbonisation Fund (SHDF).
The councils used the South East Consortium's Zero Carbon Framework to s
29/01/2025
In the world of construction, the quest for energy efficiency and sustainability is ever-evolving. Among the array of solutions available, EPS (Expanded Polystyrene) insulation stands out as a versatile and effective option for enhancing the thermal performance of buildings, particularly when used f
29/01/2025
BCP Council has completed significant coastal protection works at Hamworthy Park, ensuring its resilience against erosion for the next 20 years.
A 200-metre stretch of sea wall along the eastern promenade has been reinforced using low-carbon concrete, while new steps have been constructed to improv
29/01/2025
Geo-environmental consultancy and remediation contractor, The LK Group, has strengthened its team with a trio of recruits.
The multidisciplinary company's latest raft of hires comprises a new director, associate director and remediation manager.
The geo-environmental specialist, headquartered i