Construction News
04/08/2015
Work Continues On Mersey Gateway Project
![Construction News Image](https://www.construction.co.uk/newsimages/2_201307_Mersey-Gateway.jpg)
Construction teams working on the Mersey Gateway Project have started to build three large pylons that will support the Mersey Gateway Bridge.
A major concrete pour began on 03 August for the south pylon foundation, pumping 1,400 cubic metres of concrete into the south cofferdam for approximately 24 hours.
The three pylon foundations will reside below the riverbed, measuring 4.5 metres high and up to 22 metres in diameter.
Development of the foundations involves creating a concrete base layer, or floor, inside the cofferdams.
Following this, a cage made of steel reinforcing bars will be assembled and encased in steel matting, with a working platform also installed to provide access for site workers.
Upright steel reinforcement bars will then be fixed into the centre of the cage to form the beginnings of the pylon shaft, a tall structure rising out of the river bed to support the bridge deck.
Once the assembly work is finished the concrete pour can take place.
Approximately 127,000 cubic metres of concrete will be used across the project, the equivalent of around 20,000 truck mixer loads of concrete.
Merseylink's site agent, George Houston, said: "This is one of the biggest concrete pours that I've ever been involved with. We're using a massive amount of concrete – over 600 truckloads just for the three pylon foundations. It's an extremely technical part of the project and our teams will be working round the clock to get the job done."
As each pylon foundation is completed, work will begin on the pylon shafts.
A metal mould, known as formwork, will be lifted into place by a crane and attached to the pylon foundation for the concrete to be poured into.
The formwork will move up the pylon shaft, allowing the pylon to 'grow'. It is estimated each section of the shaft will take around five days to build.
The three pylons, which will rise out of the riverbed to support the bridge deck, should begin to be visible in the estuary from September 2015.
Hugh O'Connor, General Manager of Merseylink, said: "Starting work on the bridge pylons marks another significant step for this important infrastructure project. Work is progressing at pace now on all sections of the site and a huge amount of activity will be taking place over the next few months."
(LM)
A major concrete pour began on 03 August for the south pylon foundation, pumping 1,400 cubic metres of concrete into the south cofferdam for approximately 24 hours.
The three pylon foundations will reside below the riverbed, measuring 4.5 metres high and up to 22 metres in diameter.
Development of the foundations involves creating a concrete base layer, or floor, inside the cofferdams.
Following this, a cage made of steel reinforcing bars will be assembled and encased in steel matting, with a working platform also installed to provide access for site workers.
Upright steel reinforcement bars will then be fixed into the centre of the cage to form the beginnings of the pylon shaft, a tall structure rising out of the river bed to support the bridge deck.
Once the assembly work is finished the concrete pour can take place.
Approximately 127,000 cubic metres of concrete will be used across the project, the equivalent of around 20,000 truck mixer loads of concrete.
Merseylink's site agent, George Houston, said: "This is one of the biggest concrete pours that I've ever been involved with. We're using a massive amount of concrete – over 600 truckloads just for the three pylon foundations. It's an extremely technical part of the project and our teams will be working round the clock to get the job done."
As each pylon foundation is completed, work will begin on the pylon shafts.
A metal mould, known as formwork, will be lifted into place by a crane and attached to the pylon foundation for the concrete to be poured into.
The formwork will move up the pylon shaft, allowing the pylon to 'grow'. It is estimated each section of the shaft will take around five days to build.
The three pylons, which will rise out of the riverbed to support the bridge deck, should begin to be visible in the estuary from September 2015.
Hugh O'Connor, General Manager of Merseylink, said: "Starting work on the bridge pylons marks another significant step for this important infrastructure project. Work is progressing at pace now on all sections of the site and a huge amount of activity will be taking place over the next few months."
(LM)
![](https://www.construction.co.uk/newsimages/1_315943_stockport.jpg)
05/02/2025
Stockport Mayoral Development Corporation (MDC) and ECF, a joint venture between Homes England, Legal & General, and Muse, have selected Vinci as the preferred contractor for Phase 1 of Stockport 8, a £350 million residential development west of Stockport town centre.
The decision follows a competi
![](https://www.construction.co.uk/newsimages/1_315945_vistry.jpg)
05/02/2025
Vistry Group has finalised contracts for a significant housing development in Hinckley, Leicestershire, securing outline planning permission to deliver 475 new homes in the area.
The development, located east of Stoke Road and north of Normandy Way in the town's northern region, has a projected val
![](https://www.construction.co.uk/newsimages/1_315947_gateway14.jpg)
05/02/2025
Wilten Construction has been awarded a second Design and Build contract at Gateway 14 by client Gateway 14 Ltd and Jaynic.
The project involves the development of a state-of-the-art, three-storey Skills and Innovation Centre spanning 35,000 sq ft in the heart of Gateway 14. Designed to achieve BREE
![](https://www.construction.co.uk/newsimages/1_315958_kirkby.jpg)
05/02/2025
Knowsley Council has approved a major housing development in Kirkby, giving the green light to 800 new energy-efficient homes in the town's centre.
The decision also secures £7.7 million in Section 106 contributions from developer Barratt David Wilson Homes, further boosting local investment.
The
![](https://www.construction.co.uk/newsimages/1_315954_keepmoat.jpg)
05/02/2025
Keepmoat Homes has announced plans to invest over £50 million in three new housing developments across Calderdale, aiming to deliver more than 200 new homes.
The developments, undertaken in partnership with Calderdale Council, form part of the North Halifax Transformation Programme, a local authori
![](https://www.construction.co.uk/newsimages/1_315951_driffield.jpg)
05/02/2025
Essential renewal work at Skerne Road level crossing in Driffield has been completed. Over a six-day period, engineers replaced decades-old equipment, installing a state-of-the-art operating system, replacing the level crossing deck, and resurfacing the road.
The newly installed operating system is
![](https://www.construction.co.uk/newsimages/1_315953_graham.jpg)
05/02/2025
Construction firm GRAHAM is currently carrying out essential restoration work at the National Railway Museum in York, replacing the Grade II listed roof structure at Station Hall.
Originally built between 1875 and 1877 as a goods station, Station Hall now houses the museum’s six royal carriages.
![](https://www.construction.co.uk/newsimages/1_315975_mezzanine.jpg)
05/02/2025
Mezzanine floors are commonly associated with additional storage or expanded floor space, but did you know they can also have a profound impact on employee productivity and morale? At Doity Engineering, we specialise in designing and installing mezzanine floors for
![](https://www.construction.co.uk/newsimages/1_315978_weeton.jpg)
05/02/2025
Construction work is commencing on a new solar array at Weeton Barracks in Lancashire that will generate over one third of the site’s energy needs.
The work has been funded under the British Army’s Project Prometheus, a scheme that is increasing renewable energy across the army estate through inst
![](https://www.construction.co.uk/newsimages/1_315977_hartlepool.jpg)
05/02/2025
The regeneration of Hartlepool's waterfront has reached a significant milestone with a £631,000 grant from The National Lottery Heritage Fund.
The funding will support the development phase of the 'Tides of Change' project, aimed at transforming the visitor experience at the Museum of Hartlepool a