Subscribe to our Construction Newsfeed
UK Construction Directory
Search our 157,067 companies....

Construction News

09/08/2016

Groundforce Provides Hire Fleet For Glasgow Shieldhall Tunnel Project

Construction News Image
Construction equipment supplier Groundforce is providing its large hire fleet for a major water infrastructure project in Glasgow.

Scottish Water is building a 3.1 mile-long waste water tunnel in the south of Glasgow as part of the biggest upgrade of the city's waste water network in more than a century. 

The Shieldhall Strategic Tunnel, which will run between Craigton and Queen's Park area of Glasgow, forms part of a £250 million, five-year programme of work to upgrade the waste water network in the Greater Glasgow area.

The scheme is the biggest investment in Glasgow's waste water network since Victorian times and is designed to handle increased rainwater flows and improve water quality in the River Clyde and its tributaries.

The 4.7m diameter Shieldhall Strategic Tunnel is a vital link in this upgraded sewer network. Under construction by Costain Vinci JV (a joint venture of Costain and Vinci Construction Grands Projects) the tunnel is mostly developed using a tunnel boring machine (TBM).

The tunnel begins and is launched in Craigton with Costain Vinci JV is using a cut-and-cover method of tunnel construction, with this section of tunnel, extending some 190m in length, is being constructed in an excavation approximately 8m deep and 5.7m wide, within contiguous concrete bored pile retaining walls.

The construction method involved sinking the piles, then excavating the first metre or so before installing temporary works to withstand the lateral forces and prevent the piled walls collapsing as the excavation was dug to its final depth. The temporary support was required to remain in place while Costain Vinci JV cast the tunnel invert.

Groundforce was awarded the hire contract for equipment to provide this support. The company proposed a system comprising of its modular Megabrace beams installed as a continuous waling beam braced with MP125 hydraulic props spanning the excavation.
-- Advertisement --
hss



Costain Vinci JV site manager Ian Bowley said: "The original plan was to excavate in sections, casting the tunnel invert before striking the temporary supports and 'leap-frogging' along to the next section. But we re-phased the operation so that the excavation progressed more quickly than originally planned."

The new arrangement meant that instead of the excavation being opened in sections, the entire 190m-long trench was excavated at once. This accelerated the programme, but in order for this method to work, Groundforce had to ensure that it could supply enough equipment to support the entire 190m excavation. The original plan was to supply sufficient support for no more than 60% of the excavation at any one time.

The support system designed by Groundforce comprised two levels of Mega Brace waling, one approximately 0.75m from the top of the contiguous piles, the other at the bottom of the excavation, approximately 4.5m below.

In total, this arrangement required about 720m of Mega Brace and 112 props to be supplied.

Groundforce Major Projects Manager, Mark Whitmore, said: "This meant that we had to divert some of the hire fleet to Shieldhall and manufacture additional props to avoid shortfalls elsewhere."

Mega Brace beams can span substantial lengths, but the majority of the units employed at Shieldhall were 7m long. The reason for this was that instead of following a straight line, the excavation is curved, following a radius of 150m. Long beams would describe a chord, creating wide segments across the radius of the curve. This would have the effect of narrowing the excavation and creating gaps between the bracing and the piled retaining wall that would need substantial packing.

Using more, but shorter, beams allowed the curve to be followed more smoothly, minimising the size of these gaps and requiring minimal packing to distribute the loads evenly. Each Mega Brace beam was supported with an MP125 hydraulic prop at either end and the beams were located and supported vertically by bespoke gallows brackets bolted into the concrete piles.

An additional complication was that, due to this curve, the outer side of the frame had to be marginally longer than the inner side. This was accomplished by assembling the waling beam so that nine of the 27 bays incorporated 7.5m Mega Brace beams to provide the extra 4.5m of waling beam to accommodate the larger outer radius.

As one of the UK's leading specialists in the hire of temporary works equipment, Groundforce was able to offer the Costain Vinci JV a turnkey service which involved the supply of a temporary bridge to span the open excavation.

Installed in January 2016, two months after installation of the trench support system, this comprised an 8m modular bridge with protective canopy that follows the line of an existing footpath that provides access to a pedestrian underpass underneath the adjacent M8 motorway.

Groundforce Bridge Manager, Terry Mead, added: "The contractor required a pedestrian bridge with a roof to ensure additional safety for personnel. Groundforce Bridge designed and fabricated a unit specifically for this project."

This section of project will be completed in Q3 2016, with the tunnel completion set for early 2018.

www.vpgroundforce.com

Latest Construction News

22/04/2025
Construction company Kier has completed the redevelopment of Crescent at Temple Quay in Bristol, delivering a modern, sustainability-focused workspace on behalf of investment and development firm CEG. The transformation includes a striking new two-storey façade, a rooftop extension, and three priva
22/04/2025
McPhillips has been awarded a £10 million contract by Hereford Council to construct the city’s new Transport Hub. The project is part of a broader strategy to improve travel and connectivity across the city, encouraging a shift away from car dependency and supporting more sustainable transport opti
22/04/2025
Network Rail has delivered a wide-ranging programme of engineering works across south London, Kent and Sussex over the Easter weekend, completing critical upgrades aimed at improving safety, reliability and long-term performance of the railway network. Despite the scale of the operation, more than
22/04/2025
Indurent has submitted a planning application for the final phase of development at Indurent Park Longbridge West, marking a major milestone in the ongoing regeneration of one of Birmingham's most historically significant industrial sites. Located 12km south-west of Birmingham city centre, the site
22/04/2025
Notting Hill Genesis has agreed to sell 10,000 square feet of new high-quality workspace to long-term partner Bow Arts Trust in the heart of Hackney Wick. The space will deliver 38 affordable studio units, designed to support local creatives and small enterprises. Currently under construction and
22/04/2025
Ireland's largest independent manufacturer of concrete products Kilsaran, have entrusted Wilsons Auctions to sell over 150 assets of quarry equipment and construction machinery this May. The upcoming auction is set to take place on Friday 16th May at Wilsons Auctions Dublin, with the first lot gett
22/04/2025
Developer Chancerygate has appointed Caddick Construction as the main contractor for its latest urban logistics development, T45, located just off the A63 in Leeds. The project is expected to complete in early 2026 and will deliver 23 state-of-the-art commercial units to support the growing needs
22/04/2025
Construction firm G F Tomlinson has completed the complex and highly specialised task of removing and replacing the original roof of the Grade II Listed Central Building at the University of Nottingham\s Castle Meadow Campus. The project is part of a major refurbishment to safeguard and enhance the
22/04/2025
Broadland District Councillor Caroline Karimi-Ghovanlou and Chairman of Sprowston Town Council Bill Couzens officially reopened the Viking Community Building, marking the beginning of a new era for the historic site. Originally built in 1956 as the Viking Pub, the building has undergone a major tra
22/04/2025
Wates has submitted a planning application for the redevelopment of Farnham and Hilldene. The scheme represents the third phase of the wider Harold Hill Town Centre regeneration and proposes the delivery of 481 new homes, alongside upgraded retail and community spaces. The plans support a broader a
Stuart CanvasT & D Glazing And Installation LimitedLakeside HireAqua Direct LtdEfco UK LtdRocburn LtdMrs Joseph BradleyScrabo KitchensCarlisle Construction Materials LtdCarter Plant Hire