BAM Nuttall Helps Test Flood Alleviation Scheme In Leeds
BAM Nuttall has helped carry out a virtual test of a flood alleviation scheme in Leeds.
The contractor worked in partnership with the Environment Agency (EA) to ensure work to install a moveable weir on the River Aire is ready for this winter.
The scheme at Crown Point was carried out as part of the first phase of Leeds' flood alleviation scheme.
Works involved blocking half of the river with 1,500 tonnes of rock, creating a platform for heavy plant vehicles to drive in sheet piles and create a dry working place. Once this was completed, work to remove the existing weir could begin.
In addition, a penstock has been installed to act as a gate to manage water levels. It was also used to mitigate the risk of flooding during the construction phase of the moveable weir. When raised, upstream river levels can be lowered when high flows are expected in the river.
Construction is now underway to replace Knostrop Weir with the third weir gate currently being installed. Once complete, the moveable weirs at Crown Point and Knostrop will be capable of lowering river levels during flood conditions.
Work to install flood walls on the River Aire is now also complete, including glazed flood panels in locations such as the former KPMG building and Victoria Quays. Work to install flood defences along Hol Beck has also now started.
(LM/JP)
The contractor worked in partnership with the Environment Agency (EA) to ensure work to install a moveable weir on the River Aire is ready for this winter.
The scheme at Crown Point was carried out as part of the first phase of Leeds' flood alleviation scheme.
Works involved blocking half of the river with 1,500 tonnes of rock, creating a platform for heavy plant vehicles to drive in sheet piles and create a dry working place. Once this was completed, work to remove the existing weir could begin.
In addition, a penstock has been installed to act as a gate to manage water levels. It was also used to mitigate the risk of flooding during the construction phase of the moveable weir. When raised, upstream river levels can be lowered when high flows are expected in the river.
Construction is now underway to replace Knostrop Weir with the third weir gate currently being installed. Once complete, the moveable weirs at Crown Point and Knostrop will be capable of lowering river levels during flood conditions.
Work to install flood walls on the River Aire is now also complete, including glazed flood panels in locations such as the former KPMG building and Victoria Quays. Work to install flood defences along Hol Beck has also now started.
(LM/JP)
29/01/2025
Caddick Construction has been awarded a £43 million contract to deliver the first phase of Cole Waterhouse's flagship regeneration scheme in Digbeth, Birmingham.
The project, known as Upper Trinity Street, marks a significant step in the area’s transformation.
Spanning 182,986 square feet, the re
29/01/2025
McLaren Construction has been appointed by O&H Properties to deliver the first phase of a £60 million Foster & Partners-designed development at the corner of New Bond Street and Grafton Street in London’s West End.
The seven-storey, 5,400 square metre prime retail and office scheme will feature ret
29/01/2025
GMI Construction Group has been awarded a contract to develop three high-specification warehouse units totalling over 175,000 square feet at Precedent Drive, Milton Keynes.
The £20 million project, commissioned by DV5 Last Mile Developments (UK) Ltd, a joint venture between Coltham and Delancey Re
29/01/2025
Plans for 106 sustainable new homes in Southville, a neighbourhood in South Bristol, have been approved as the city seeks to increase housing delivery to address growing demand.
Top 10 award-winning housebuilder The Hill Group will create a £60 million development on Raleigh Road, on land that was
29/01/2025
Bouygues UK has reached a major milestone in the fourth phase of the Hallsville Quarter regeneration project in Canning Town, London.
The project, part of the £3.7 billion Canning Town and Custom House Regeneration Programme, recently held a topping out ceremony, marking the completion of the 11-s
29/01/2025
Willmott Dixon Interiors is carrying out a significant upgrade to the roof of the National Maritime Museum in Greenwich, one of London's most iconic cultural landmarks.
As part of the £12 million project, the company is installing over 23,000 square feet of sun-protected glazing above the museum’s
29/01/2025
Equans has been appointed by Babergh and Mid Suffolk District Councils to carry out crucial decarbonisation work across the councils' housing stock, using funding secured through the Social Housing Decarbonisation Fund (SHDF).
The councils used the South East Consortium's Zero Carbon Framework to s
29/01/2025
In the world of construction, the quest for energy efficiency and sustainability is ever-evolving. Among the array of solutions available, EPS (Expanded Polystyrene) insulation stands out as a versatile and effective option for enhancing the thermal performance of buildings, particularly when used f
29/01/2025
BCP Council has completed significant coastal protection works at Hamworthy Park, ensuring its resilience against erosion for the next 20 years.
A 200-metre stretch of sea wall along the eastern promenade has been reinforced using low-carbon concrete, while new steps have been constructed to improv
29/01/2025
Geo-environmental consultancy and remediation contractor, The LK Group, has strengthened its team with a trio of recruits.
The multidisciplinary company's latest raft of hires comprises a new director, associate director and remediation manager.
The geo-environmental specialist, headquartered i