JP Concrete and Toro Shelters have completed the design and construction of a new building that increases salt availability for Central Bedfordshire's roads by 20%.
The 5,000 tonne Salt Barn was delivered on time and within budget for main contractor Morgan Sindall.
The lightweight yet robust building combines Toro's latticed galvanised steel structure with JP Concrete's precast retaining walls.
Initially, the design was set out for a traditional steel framed structure, with internal retaining walls to contain the grit salt. However, when Morgan Sindall wanted to explore an alternative method of construction, JP Concrete and Toro teamed up to bring about a far more cost-effective solution that will also prevent up to 1,000 tonnes of salt from leaching into the environment every year.
Working closely alongside Modular Cubed (who carried out the installation of the concrete elements) JPG (structural engineers) and main contractor, Morgan Sindall, the complete works package for the salt barn is part of a major new infrastructure project in Houghton Regis, near Dunstable.
Modular Cubed installed a total of 110 (3.2m high) of JP Concrete's precast L-shape retaining wall units. These were specially coated to make them resistant to aggressive saline solutions. Resistance to corrosion was also enhanced by utilising fibres instead of steel reinforcements. Toro then constructed its 28m x 35m shelter with tensioned composite membrane, before JP Concrete's 30m x 20m integral floor slab was put in place.
Tom Martin, Project Manager for Morgan Sindall, commented: "Together, the pro-active work of JP Concrete, Toro Shelters, Modular Cubed and JPG has resulted in a smooth-running and cost-effective job that looks very good indeed. From start to finish, everything has gone well, with a great turnaround from an innovative team who quickly understood our deadline and what we needed to achieve."
Edd Gowlett, Business Development Manager at Toro Corporation, added: "The design solution was clearly well thought out, with JP Concrete and Modular Cubed working tirelessly to deliver a seamless and extremely high quality installation that represents real value for the customer. There is clearly an ethos of helpfulness and professionalism that runs through both companies - and this is the reason that we will be asking them to quote for our future projects."
During the contract, JP Concrete and Toro Shelters also received Morgan Sindall's coveted Health & Safety award.
www.jpconcrete.co.uk
The 5,000 tonne Salt Barn was delivered on time and within budget for main contractor Morgan Sindall.
The lightweight yet robust building combines Toro's latticed galvanised steel structure with JP Concrete's precast retaining walls.
Initially, the design was set out for a traditional steel framed structure, with internal retaining walls to contain the grit salt. However, when Morgan Sindall wanted to explore an alternative method of construction, JP Concrete and Toro teamed up to bring about a far more cost-effective solution that will also prevent up to 1,000 tonnes of salt from leaching into the environment every year.
Working closely alongside Modular Cubed (who carried out the installation of the concrete elements) JPG (structural engineers) and main contractor, Morgan Sindall, the complete works package for the salt barn is part of a major new infrastructure project in Houghton Regis, near Dunstable.
Modular Cubed installed a total of 110 (3.2m high) of JP Concrete's precast L-shape retaining wall units. These were specially coated to make them resistant to aggressive saline solutions. Resistance to corrosion was also enhanced by utilising fibres instead of steel reinforcements. Toro then constructed its 28m x 35m shelter with tensioned composite membrane, before JP Concrete's 30m x 20m integral floor slab was put in place.
Tom Martin, Project Manager for Morgan Sindall, commented: "Together, the pro-active work of JP Concrete, Toro Shelters, Modular Cubed and JPG has resulted in a smooth-running and cost-effective job that looks very good indeed. From start to finish, everything has gone well, with a great turnaround from an innovative team who quickly understood our deadline and what we needed to achieve."
Edd Gowlett, Business Development Manager at Toro Corporation, added: "The design solution was clearly well thought out, with JP Concrete and Modular Cubed working tirelessly to deliver a seamless and extremely high quality installation that represents real value for the customer. There is clearly an ethos of helpfulness and professionalism that runs through both companies - and this is the reason that we will be asking them to quote for our future projects."
During the contract, JP Concrete and Toro Shelters also received Morgan Sindall's coveted Health & Safety award.
www.jpconcrete.co.uk
17/01/2025
Leeds Trinity University has officially opened its newly refurbished City Campus at 1 Trevelyan Square in Leeds.
Completed by GRAHAM Interior Fit-Out, the transformation of the central Leeds site introduces state-of-the-art facilities designed to improve learning and collaborate with industry partn
17/01/2025
Trammell Crow Company (TCC) has secured planning permission for a Grade A logistics scheme in Heywood, Greater Manchester, following a successful planning appeal.
The development will feature two state-of-the-art industrial and logistics buildings. One building will house two units measuring 4,796
17/01/2025
Poole-based developer AJC Group has celebrated a record-breaking 2024, delivering 100 affordable homes, a significant increase from the 72 units completed in the previous year.
Since 2023, AJC Group has completed and handed over 172 affordable homes across five sites.
In 2024 alone, the developer
17/01/2025
Plans for one of the most ambitious parks projects in London have taken a significant step forward, with Haringey Council securing nearly two additional acres of land around The Paddock nature reserve in Tottenham Hale.
The agreement with Thames Water marks a major milestone in the transformation o
17/01/2025
Islington Council has unveiled two draft guidance documents aimed at helping residents, businesses, and developers combat climate change by making buildings more energy efficient and fostering a greener, healthier borough.
The consultation seeks feedback on the draft Climate Action Supplementary Pl
17/01/2025
The City of Wolverhampton Council has unveiled a £98 million investment plan over the next five years to develop around 500 new homes across the city.
The proposal, part of the Housing Revenue Account (HRA) Business Plan, received Cabinet approval this week and now moves to Full Council for final
17/01/2025
Croydon Council has announced a significant milestone in the redevelopment of the Purley Pool site, with revised proposals submitted for a new leisure centre, later living housing, and the regeneration of the surrounding area.
A planning application for the site was initially submitted in 2024, pro
17/01/2025
The City of Wolverhampton Council has announced that demolition work has commenced on the New Park Village estate, marking the start of a major £40 million redevelopment project to transform outdated council housing.
Contractor DSM Demolition has begun pulling down poor-quality bungalows on Valley
17/01/2025
Hillingdon Council has acquired 12 new homes at Carpenters Court in Uxbridge.
Leader of Hillingdon Council, Cllr Ian Edwards and Cllr Steve Tuckwell, Cabinet Member for Planning, Housing and Growth, visited the site to officially mark the handover of the properties from local developer Kearns Devel
17/01/2025
Organisers of UK Construction Week (UKCW) have announced another major coup for the show's 10th anniversary year, with the news that UKCW London will be co-locating with the 14th edition of The Stone Show & Hard Surfaces, the principal industry event for surface design.
Established 26 years ago, th