Eliquo Hydrok HydroSlide Used For Louth Flood Alleviation Scheme

Construction News Image
Extract from a paper by David Scopes IEng MICE, Engineer at Atkins Ltd, Peterborough.


The market town of Louth, on the River Lud, has suffered from flooding on many occasions, most recently in 2007. Atkins was commissioned to conduct a feasibility study into the viability of a flood defence scheme.

This paper begins once the preferred option of two online flood storage areas was identified; the brief from this point was to develop their outline design. The maximum allowable outflow (to prevent flooding) for each storage area had been calculated as a part of the preceding hydrological study, and therefore was known at the start of the design. The exact volume of storage, being dependent on the method of controlling flows, had at this stage been calculated assuming no additional flows were impounded.

The control structure design of the project required a balance of two factors: maintenance and storage. Using options with no moving parts (fixed weir, orifice, vortex type flow control etc.), which solely limit the flow, result in increased storage, but are able to offer very low maintenance costs. Conversely, low storage can be achieved through the use of a mechanical and electrical setups, however these would have significant maintenance costs and potential reliability issues. Accepting some moving parts, and therefore some maintenance, allowed the Eliquo Hydrok HydroSlide to be considered.

-- Advertisement --
hss

A HydroSlide consists of a see-saw on a pivot with a plate at one end and a float as the counter balance at the other. As the water level increases the float rises causing the plate to close across the orifice opening and restricting outflow. Although it has a moving part, the discharge curve holds tightly to the optimum discharge, plus or minus five percent.

The other advantage of the HydroSlide is that it is adjustable by up to 30% during an event (via a spindle) to increase or reduce flows as required. This means that if the actual downstream maximum allowable flow is found to be different than that predicted by the mathematical model due to insufficient data, a change in the structures, or a blockage, the problem could be overcome without having to wait for the flood to subside.

The ability to provide the more refined level of flow control, with relatively little maintenance, and the advantage of post-construction in-event adjustment led to the HydroSlide being adopted.

To discuss how the Eliquo Hydrok HydroSlide solutions, contact Dave Armstrong on 01726 861900, or email dave.armstrong@eliquohydrok.co.uk

www.hydrok.co.uk

Latest Construction News

20/11/2024

Construction firm Willmott Dixon has partnered with Westminster City Council on a £36 million project to restore the historic Seymour Centre in Marylebone, a Grade II listed building dating back to the 1930s. The project, procured through the SCF framework, will see the three-storey centre undergo ...
20/11/2024

The Hill Group has commenced work on a new development in Billericay, Essex, which will deliver 179 high-quality homes across a 20-acre site. Designed to blend with Billericay's scenic countryside while addressing the pressing demand for sustainable housing, the project is located on Kennel Lane ...
20/11/2024

Extensive groundwork is underway for a new housing development in Maidstone, where Vistry Group, in partnership with Legal & General Affordable Homes, is set to build 272 properties on the site of the former Tovil Quarry off Farleigh Hill. The project will include 37 affordable homes for low-cost ...
20/11/2024

Stonewater has scooped a new energy efficiency retrofit contract with compliance and energy services provider Correct Contract Services. This work, funded through the Social Housing Decarbonisation Fund (SHDF) Wave 2, will include a range of energy-saving upgrades. Measures such as loft ...
20/11/2024

Kier has been appointed by Cambridgeshire County Council to deliver building, mechanical, and electrical maintenance services across the Council's portfolio of 160 corporate buildings. The contract, which began in November 2024, will run until 2027, with the possibility of two one-year extensions ...
20/11/2024

Builders use water for various functions on the job, they utilise this resource for worker hygiene, hydration, concrete batching, grouting, dust suppression, drilling and piling. If companies mismanage this water use, they can increase their environmental impact. When the industry comes ...
20/11/2024

Edmond Shipway has been appointed to a pioneering initiative tackling homelessness in Greater Manchester, providing project management and cost consultancy services on the second phase of Embassy Village. Set to deliver 40 purpose-built homes for men facing homelessness in Manchester, Embassy ...
20/11/2024

West Sussex County Council is inviting residents to share their views on proposed transport improvements at the Hazelwick and Tushmore junctions on the A2011 Crawley Avenue. The proposals aim to make walking, cycling, and public transport more appealing for short journeys. This initiative is part ...
19/11/2024

McLaren Construction has commenced works at the first UK industrial scheme in the East Midlands for a joint venture with Garbe Industrial Real Estate GmbH and Invesco Real Estate. McLaren will oversee all aspects of construction for the £30 million project located in Shireoaks, Worksop - in the ...
19/11/2024

Pennyfarthing Homes has submitted a planning application for 74 new homes in Fordingbridge as part of its plans to build a neighbourhood of 342 homes on the northern edge of the Hampshire market town. The new development which is part of the wider scheme known as Forde Valley and follows ...
Efco UK LtdThink Construction Skills Ltd.Stuart CanvasAqua Direct LtdT & D Glazing And Installation LimitedLakeside HireBRICOFLOR UKMy Thread Curtains(London) Builder Cambridge LtdElectrical Test Midlands Ltd
Terms and Conditions
2024/11/21 11:47:42