Construction News
05/07/2017
A14 Cambridge To Huntingdon Upgrade Takes Shape
Work is continuing on a £1.5 billion road upgrade project on the A14 between Cambridge and Huntingdon.
The scheme, which started in November last year, includes widening a total of seven miles of the A14 in each direction (across two sections) a major new bypass south of Huntingdon, widening a three-mile section of the A1 and demolition of a viaduct at Huntingdon, which will support improvements in the town.
So far, some of the scheme's 34 new bridges have been installed, while the outline for the 12-mile long Huntingdon bypass has emerged through the Cambridgeshire landscape.
In addition, the earthworks team has been stripping top soil over more than 17 miles out of the project's total length of 21 miles to create several sections of the future new road including: the Huntingdon bypass, the new Swavesey junction, and the five-mile long local access road, which will link local communities between Huntingdon and Cambridge without the need to use the A14.
Steel-reinforced concrete columns for some of the 34 bridges to be built throughout the project have now started appearing along Ermine Street (A1198), the A1 and at the site of the future, 750-metre long River Great Ouse viaduct.
Elsewhere, the piling team drilled under the layers of clay and silt either side of the River Great Ouse to ensure the foundations and the viaduct columns themselves are stable enough to carry the 800 concrete bridge deck panels, weighing 25 tonnes each, on which the new carriageway will be built. While work continues to install the foundations and columns for some of the bridges, work has started to cast cast the concrete panels for the bridge decks including the 800 needed for the viaduct alone.
Chris Griffin, A14 project manager at Highways England, said the team is continuing to make "good progress" throughout the scheme.
"We have had mild and dry weather this winter and spring and have been making the most of it to move the project forward quickly and safely," he said.
"I am pleased that the outline for most of the new road's path has now been created and it won't be long before some of our first structures are completed.
"With construction gathering pace, we have now started tackling some of the biggest challenges on the project and it is exciting to see our innovative plans take shape on the ground, including the foundations and some of the columns for the viaduct on both sides of the River Great Ouse."
The project is scheduled to be fully completed by March 2021.
(LM/MH)
The scheme, which started in November last year, includes widening a total of seven miles of the A14 in each direction (across two sections) a major new bypass south of Huntingdon, widening a three-mile section of the A1 and demolition of a viaduct at Huntingdon, which will support improvements in the town.
So far, some of the scheme's 34 new bridges have been installed, while the outline for the 12-mile long Huntingdon bypass has emerged through the Cambridgeshire landscape.
In addition, the earthworks team has been stripping top soil over more than 17 miles out of the project's total length of 21 miles to create several sections of the future new road including: the Huntingdon bypass, the new Swavesey junction, and the five-mile long local access road, which will link local communities between Huntingdon and Cambridge without the need to use the A14.
Steel-reinforced concrete columns for some of the 34 bridges to be built throughout the project have now started appearing along Ermine Street (A1198), the A1 and at the site of the future, 750-metre long River Great Ouse viaduct.
Elsewhere, the piling team drilled under the layers of clay and silt either side of the River Great Ouse to ensure the foundations and the viaduct columns themselves are stable enough to carry the 800 concrete bridge deck panels, weighing 25 tonnes each, on which the new carriageway will be built. While work continues to install the foundations and columns for some of the bridges, work has started to cast cast the concrete panels for the bridge decks including the 800 needed for the viaduct alone.
Chris Griffin, A14 project manager at Highways England, said the team is continuing to make "good progress" throughout the scheme.
"We have had mild and dry weather this winter and spring and have been making the most of it to move the project forward quickly and safely," he said.
"I am pleased that the outline for most of the new road's path has now been created and it won't be long before some of our first structures are completed.
"With construction gathering pace, we have now started tackling some of the biggest challenges on the project and it is exciting to see our innovative plans take shape on the ground, including the foundations and some of the columns for the viaduct on both sides of the River Great Ouse."
The project is scheduled to be fully completed by March 2021.
(LM/MH)
29/01/2025
Caddick Construction has been awarded a £43 million contract to deliver the first phase of Cole Waterhouse's flagship regeneration scheme in Digbeth, Birmingham.
The project, known as Upper Trinity Street, marks a significant step in the area’s transformation.
Spanning 182,986 square feet, the re
29/01/2025
McLaren Construction has been appointed by O&H Properties to deliver the first phase of a £60 million Foster & Partners-designed development at the corner of New Bond Street and Grafton Street in London’s West End.
The seven-storey, 5,400 square metre prime retail and office scheme will feature ret
29/01/2025
GMI Construction Group has been awarded a contract to develop three high-specification warehouse units totalling over 175,000 square feet at Precedent Drive, Milton Keynes.
The £20 million project, commissioned by DV5 Last Mile Developments (UK) Ltd, a joint venture between Coltham and Delancey Re
29/01/2025
Plans for 106 sustainable new homes in Southville, a neighbourhood in South Bristol, have been approved as the city seeks to increase housing delivery to address growing demand.
Top 10 award-winning housebuilder The Hill Group will create a £60 million development on Raleigh Road, on land that was
29/01/2025
Bouygues UK has reached a major milestone in the fourth phase of the Hallsville Quarter regeneration project in Canning Town, London.
The project, part of the £3.7 billion Canning Town and Custom House Regeneration Programme, recently held a topping out ceremony, marking the completion of the 11-s
29/01/2025
Willmott Dixon Interiors is carrying out a significant upgrade to the roof of the National Maritime Museum in Greenwich, one of London's most iconic cultural landmarks.
As part of the £12 million project, the company is installing over 23,000 square feet of sun-protected glazing above the museum’s
29/01/2025
Equans has been appointed by Babergh and Mid Suffolk District Councils to carry out crucial decarbonisation work across the councils' housing stock, using funding secured through the Social Housing Decarbonisation Fund (SHDF).
The councils used the South East Consortium's Zero Carbon Framework to s
29/01/2025
In the world of construction, the quest for energy efficiency and sustainability is ever-evolving. Among the array of solutions available, EPS (Expanded Polystyrene) insulation stands out as a versatile and effective option for enhancing the thermal performance of buildings, particularly when used f
29/01/2025
BCP Council has completed significant coastal protection works at Hamworthy Park, ensuring its resilience against erosion for the next 20 years.
A 200-metre stretch of sea wall along the eastern promenade has been reinforced using low-carbon concrete, while new steps have been constructed to improv
29/01/2025
Geo-environmental consultancy and remediation contractor, The LK Group, has strengthened its team with a trio of recruits.
The multidisciplinary company's latest raft of hires comprises a new director, associate director and remediation manager.
The geo-environmental specialist, headquartered i