Construction News
23/10/2017
Companies Prosecuted For Carbon Monoxide Safety Failings
Two companies have been prosecuted after carbon monoxide (CO) entered a property during work to remove redundant flue pipes from a flat block.
Wates Construction pleaded guilty to breaching Section 3(1) of the Health and Safety at Work etc Act 1974. It has been fined £640,000 with more than £20,862 in costs.
R J Fitters also pleaded guilty to the same charge and was fined £30,000 with over £10,431 in costs.
Cambridge Crown Court heard how a mistake regarding the correct floor level resulted in a live flue being blocked on 19 December 2014.
Scaffolding was erected outside a 13-storey block of flats without marked lift levels and the external wall of the building had no markings to identify floor levels or flat numbers. Operatives from from R J Fitters were given a diagram marked with the redundant flues and were expected to find the redundant flues amongst live flues.
However, the problem was only discovered when a CO monitor activated inside a property and the homeowner and her son investigated. The damaged boiler was switched off before potentially any serious ill-health could occur.
A Health and Safety Executive (HSE) investigation into the incident found both Wates and R J Fitters failed to manage the risk involved with the project.
Investigators found the companies could have marked the levels on the scaffold and the levels/flat numbers on the external wall of the building. A supervisor could have marked the redundant flue pipes to ensure the correct cowls were removed and flue pipes blocked up.
In addition, the companies could have instead of blocking the redundant flue pipes put a cage around the cowls to ensure they did not fall.
HSE inspector Sandra Dias said: "It is the responsibility of both the principal contractor and subcontractor to ensure that safe systems of work have been identified and adopted. When there is risk of death to members of the public, the safe systems should be well thought through and robust.
"The risks associated with blocking a live flue could result in carbon monoxide entering properties and potentially killing all occupants."
(LM/MH)
Wates Construction pleaded guilty to breaching Section 3(1) of the Health and Safety at Work etc Act 1974. It has been fined £640,000 with more than £20,862 in costs.
R J Fitters also pleaded guilty to the same charge and was fined £30,000 with over £10,431 in costs.
Cambridge Crown Court heard how a mistake regarding the correct floor level resulted in a live flue being blocked on 19 December 2014.
Scaffolding was erected outside a 13-storey block of flats without marked lift levels and the external wall of the building had no markings to identify floor levels or flat numbers. Operatives from from R J Fitters were given a diagram marked with the redundant flues and were expected to find the redundant flues amongst live flues.
However, the problem was only discovered when a CO monitor activated inside a property and the homeowner and her son investigated. The damaged boiler was switched off before potentially any serious ill-health could occur.
A Health and Safety Executive (HSE) investigation into the incident found both Wates and R J Fitters failed to manage the risk involved with the project.
Investigators found the companies could have marked the levels on the scaffold and the levels/flat numbers on the external wall of the building. A supervisor could have marked the redundant flue pipes to ensure the correct cowls were removed and flue pipes blocked up.
In addition, the companies could have instead of blocking the redundant flue pipes put a cage around the cowls to ensure they did not fall.
HSE inspector Sandra Dias said: "It is the responsibility of both the principal contractor and subcontractor to ensure that safe systems of work have been identified and adopted. When there is risk of death to members of the public, the safe systems should be well thought through and robust.
"The risks associated with blocking a live flue could result in carbon monoxide entering properties and potentially killing all occupants."
(LM/MH)
29/01/2025
Caddick Construction has been awarded a £43 million contract to deliver the first phase of Cole Waterhouse's flagship regeneration scheme in Digbeth, Birmingham.
The project, known as Upper Trinity Street, marks a significant step in the area’s transformation.
Spanning 182,986 square feet, the re
29/01/2025
McLaren Construction has been appointed by O&H Properties to deliver the first phase of a £60 million Foster & Partners-designed development at the corner of New Bond Street and Grafton Street in London’s West End.
The seven-storey, 5,400 square metre prime retail and office scheme will feature ret
29/01/2025
GMI Construction Group has been awarded a contract to develop three high-specification warehouse units totalling over 175,000 square feet at Precedent Drive, Milton Keynes.
The £20 million project, commissioned by DV5 Last Mile Developments (UK) Ltd, a joint venture between Coltham and Delancey Re
29/01/2025
Plans for 106 sustainable new homes in Southville, a neighbourhood in South Bristol, have been approved as the city seeks to increase housing delivery to address growing demand.
Top 10 award-winning housebuilder The Hill Group will create a £60 million development on Raleigh Road, on land that was
29/01/2025
Bouygues UK has reached a major milestone in the fourth phase of the Hallsville Quarter regeneration project in Canning Town, London.
The project, part of the £3.7 billion Canning Town and Custom House Regeneration Programme, recently held a topping out ceremony, marking the completion of the 11-s
29/01/2025
Willmott Dixon Interiors is carrying out a significant upgrade to the roof of the National Maritime Museum in Greenwich, one of London's most iconic cultural landmarks.
As part of the £12 million project, the company is installing over 23,000 square feet of sun-protected glazing above the museum’s
29/01/2025
Equans has been appointed by Babergh and Mid Suffolk District Councils to carry out crucial decarbonisation work across the councils' housing stock, using funding secured through the Social Housing Decarbonisation Fund (SHDF).
The councils used the South East Consortium's Zero Carbon Framework to s
29/01/2025
In the world of construction, the quest for energy efficiency and sustainability is ever-evolving. Among the array of solutions available, EPS (Expanded Polystyrene) insulation stands out as a versatile and effective option for enhancing the thermal performance of buildings, particularly when used f
29/01/2025
BCP Council has completed significant coastal protection works at Hamworthy Park, ensuring its resilience against erosion for the next 20 years.
A 200-metre stretch of sea wall along the eastern promenade has been reinforced using low-carbon concrete, while new steps have been constructed to improv
29/01/2025
Geo-environmental consultancy and remediation contractor, The LK Group, has strengthened its team with a trio of recruits.
The multidisciplinary company's latest raft of hires comprises a new director, associate director and remediation manager.
The geo-environmental specialist, headquartered i