Fire Safety Lab Tests 'Utterly Inadequate' - FPA

Construction News Image
Laboratory tests currently used to check the fire safety of building materials have been described as "utterly inadequate", by the Fire Protection Association (FPA).

The FPA was commissioned by the Association of British Insurers (ABI) to carry out a series of carefully controlled experiments recreating more realistic building conditions than those in which the standard tests are done, in an effort to measure what difference these factors could make in the event of a fire.

The real-life factors overlooked by the official testing regime include:

• Test fires which are only made up of wood. In modern blazes, around 20% of the materials involved are plastic.

• Cladding materials are sometimes tested as a sealed unit, whereas when fitted on a building they often include gaps, and cover a far more extensive area.

• Materials tested will be in manufacturer condition, but during their actual use will often be pierced by things such as vents or ducts.

In its submission to the Hackitt review, the ABI called for an end to the use of all but non-combustible materials in construction, and a reformed testing regime that replicates real world conditions to provide genuine evidence of how materials perform in a fire. The results of these latest tests all reinforce the importance of urgent reform.

Huw Evans, Director General of the ABI, said: "Dame Judith Hackitt's important work post-Grenfell has already recognised the building control system is broken. This latest research is yet more evidence that fundamental reform is needed to keep our homes and commercial premises safe from fire. It is a matter of urgency that we create the right testing regime that properly replicates real world conditions and keeps pace with building innovation and modern design."

Tests conducted by the FPA include:

THE ISSUE: Test fires are only made up of wood. In modern blazes, around 20% of the materials involved are plastic.

-- Advertisement --
hss

Test 1: Two fires were created with the same energy content, one purely built out of wood, the other containing 20% plastic.

The results: The flames created by the fire containing plastic had a flame length around 1 metre longer than the wooden fire; the temperatures involved were 100 degrees hotter and still increasing when the plastic-containing fire had to be extinguished because it was exceeding lab safety conditions.

The implications: As well as the ability of the fire containing plastic to spread faster and create higher temperatures, building materials such as aluminium lose a lot of their strength at higher temperatures. A lot of cladding, including that used on Grenfell Tower, is made up of aluminium composite panels.

THE ISSUE: Cladding materials can be tested as a sealed unit, whereas when fitted on a building they often include gaps, and cover a far more extensive area.

Test 2: Fires were started at the bottom of three columns. One had no cladding or cover at all, the second had cladding fitted to create a void but with sealed edges and ends, the third was clad with a void, leaky sides and some ventilation at the top and bottom.

The results: Fire climbed 1.5 metres up the open face before burning out and self-extinguishing; the sealed cladding unit also saw fire climb a similar distance before it ran out of oxygen and self-extinguished; the unit where the cladding had gaps rapidly caught fire up the entire 6 metre height of the testing column.

The implications: The availability of oxygen makes a massive difference to how materials respond to fire. In well-ventilated voids, such as behind some cladding systems, the rate at which fire spreads can be greatly increased by a chimney effect. Any tests which restrict the availability of oxygen in a way that doesn't happen on a full scale building will not be able to correctly assess how the materials will behave in practice.

THE ISSUE: Materials tested will be in manufacturer condition, but during their actual use will often be pierced by things such as vents or ducts

Test 3: A section of wall and cladding was set up with a plastic vent installed – a common feature - and a fire started beneath the structure.

The results: Temperatures inside the vent indicated it was providing an almost instantaneous route for fire directly into the void between the wall and cladding, long before the time it would take fire to break through the outside cladding panels.

Implications: Fire safety, particularly in high rise buildings, often relies upon assumptions about how long it will take fire to penetrate certain areas of the building. The presence of fittings such as vents can make a big difference to how materials perform and how a fire will spread, and needs to be realistically modelled in testing.

Further tests examining the real-life performance of cavity barriers and the differences made by materials being unrealistically strengthened during the testing process were also carried out and are detailed in the full report.

This research has been provided in full to the Dame Judith Hackitt review into building regulations and fire safety, established in the wake of the devastating Grenfell Tower blaze.

Jonathan O'Neill, Managing Director of the Fire Protection Association said: "The results of this important research confirm long-held concerns by many in the fire sector that the current cladding test standard requires urgent review to ensure that systems that pass are reflective of the systems that are installed and of the risks to which they are exposed. We urge BSI (British Standards Institution) to urgently reconvene the group responsible for this standard to consider the results of this research and to make changes to the standard as required."

(MH)

Latest Construction News

20/11/2024

Construction firm Willmott Dixon has partnered with Westminster City Council on a £36 million project to restore the historic Seymour Centre in Marylebone, a Grade II listed building dating back to the 1930s. The project, procured through the SCF framework, will see the three-storey centre undergo ...
20/11/2024

The Hill Group has commenced work on a new development in Billericay, Essex, which will deliver 179 high-quality homes across a 20-acre site. Designed to blend with Billericay's scenic countryside while addressing the pressing demand for sustainable housing, the project is located on Kennel Lane ...
20/11/2024

Extensive groundwork is underway for a new housing development in Maidstone, where Vistry Group, in partnership with Legal & General Affordable Homes, is set to build 272 properties on the site of the former Tovil Quarry off Farleigh Hill. The project will include 37 affordable homes for low-cost ...
20/11/2024

Stonewater has scooped a new energy efficiency retrofit contract with compliance and energy services provider Correct Contract Services. This work, funded through the Social Housing Decarbonisation Fund (SHDF) Wave 2, will include a range of energy-saving upgrades. Measures such as loft ...
20/11/2024

Kier has been appointed by Cambridgeshire County Council to deliver building, mechanical, and electrical maintenance services across the Council's portfolio of 160 corporate buildings. The contract, which began in November 2024, will run until 2027, with the possibility of two one-year extensions ...
20/11/2024

Builders use water for various functions on the job, they utilise this resource for worker hygiene, hydration, concrete batching, grouting, dust suppression, drilling and piling. If companies mismanage this water use, they can increase their environmental impact. When the industry comes ...
20/11/2024

Edmond Shipway has been appointed to a pioneering initiative tackling homelessness in Greater Manchester, providing project management and cost consultancy services on the second phase of Embassy Village. Set to deliver 40 purpose-built homes for men facing homelessness in Manchester, Embassy ...
20/11/2024

West Sussex County Council is inviting residents to share their views on proposed transport improvements at the Hazelwick and Tushmore junctions on the A2011 Crawley Avenue. The proposals aim to make walking, cycling, and public transport more appealing for short journeys. This initiative is part ...
19/11/2024

McLaren Construction has commenced works at the first UK industrial scheme in the East Midlands for a joint venture with Garbe Industrial Real Estate GmbH and Invesco Real Estate. McLaren will oversee all aspects of construction for the £30 million project located in Shireoaks, Worksop - in the ...
19/11/2024

Pennyfarthing Homes has submitted a planning application for 74 new homes in Fordingbridge as part of its plans to build a neighbourhood of 342 homes on the northern edge of the Hampshire market town. The new development which is part of the wider scheme known as Forde Valley and follows ...
Efco UK LtdAqua Direct LtdT & D Glazing And Installation LimitedThink Construction Skills Ltd.Lakeside HireBRICOFLOR UKStuart Canvas123v PlcForge Lifts LtdAtlas Winch & Hoist Services Ltd (UK)
Terms and Conditions
2024/11/21 10:32:37