Construction News
04/10/2018
No-Dig Storm Water Pipe Scheme Complete In Aylesbury
A no-dig storm water pipe scheme has been successfully completed in Aylesbury, Buckinghamshire.
The scheme was delivered on the site of a new large community housing development.
Olney-based drilling and boring specialists, Chiltern Thrust Bore undertook a 23 metres pipe-jacking drive for a construction and ground works company as part of the in-line flood management programme of works.
The 23 metres crossing could not be undertaken by conventional open-cut method as overhead power lines prohibited the use of ground excavation equipment.
FP McCann's DN450mm precast concrete jacking pipe was installed using Chiltern Thrust Bore's guided auger boring trenchless technology, typically utilised in deep pipeline drives.
Trenchless work is far less intrusive than the traditional open-cut method of pipe laying and is particularly suited to areas where utilities, water courses or transport infrastructure has to be crossed. From the construction of a five-metre deep shuttered drive and reception shaft, to the piloting of the tunnel and main auger drive, the scheme was completed on time and within budget.
Dave Croot, Project Manager for Chiltern Thrust Bore said: "Despite the short distance and relatively small diameter, adverse ground conditions resulted in extremely high pressures being encountered during the pilot process. Our experience resulted in us carrying out modifications to both the cutting head and the augers cases to ensure a successful installation. Despite these alterations, jacking forces reached around 100 tonnes; FP McCann's concrete jacking pipes were more than capable of withstanding the excessive pressure. The crossing was completed successfully and within programme."
(CM/MH)
The scheme was delivered on the site of a new large community housing development.
Olney-based drilling and boring specialists, Chiltern Thrust Bore undertook a 23 metres pipe-jacking drive for a construction and ground works company as part of the in-line flood management programme of works.
The 23 metres crossing could not be undertaken by conventional open-cut method as overhead power lines prohibited the use of ground excavation equipment.
FP McCann's DN450mm precast concrete jacking pipe was installed using Chiltern Thrust Bore's guided auger boring trenchless technology, typically utilised in deep pipeline drives.
Trenchless work is far less intrusive than the traditional open-cut method of pipe laying and is particularly suited to areas where utilities, water courses or transport infrastructure has to be crossed. From the construction of a five-metre deep shuttered drive and reception shaft, to the piloting of the tunnel and main auger drive, the scheme was completed on time and within budget.
Dave Croot, Project Manager for Chiltern Thrust Bore said: "Despite the short distance and relatively small diameter, adverse ground conditions resulted in extremely high pressures being encountered during the pilot process. Our experience resulted in us carrying out modifications to both the cutting head and the augers cases to ensure a successful installation. Despite these alterations, jacking forces reached around 100 tonnes; FP McCann's concrete jacking pipes were more than capable of withstanding the excessive pressure. The crossing was completed successfully and within programme."
(CM/MH)
29/01/2025
Caddick Construction has been awarded a £43 million contract to deliver the first phase of Cole Waterhouse's flagship regeneration scheme in Digbeth, Birmingham.
The project, known as Upper Trinity Street, marks a significant step in the area’s transformation.
Spanning 182,986 square feet, the re
29/01/2025
McLaren Construction has been appointed by O&H Properties to deliver the first phase of a £60 million Foster & Partners-designed development at the corner of New Bond Street and Grafton Street in London’s West End.
The seven-storey, 5,400 square metre prime retail and office scheme will feature ret
29/01/2025
GMI Construction Group has been awarded a contract to develop three high-specification warehouse units totalling over 175,000 square feet at Precedent Drive, Milton Keynes.
The £20 million project, commissioned by DV5 Last Mile Developments (UK) Ltd, a joint venture between Coltham and Delancey Re
29/01/2025
Plans for 106 sustainable new homes in Southville, a neighbourhood in South Bristol, have been approved as the city seeks to increase housing delivery to address growing demand.
Top 10 award-winning housebuilder The Hill Group will create a £60 million development on Raleigh Road, on land that was
29/01/2025
Bouygues UK has reached a major milestone in the fourth phase of the Hallsville Quarter regeneration project in Canning Town, London.
The project, part of the £3.7 billion Canning Town and Custom House Regeneration Programme, recently held a topping out ceremony, marking the completion of the 11-s
29/01/2025
Willmott Dixon Interiors is carrying out a significant upgrade to the roof of the National Maritime Museum in Greenwich, one of London's most iconic cultural landmarks.
As part of the £12 million project, the company is installing over 23,000 square feet of sun-protected glazing above the museum’s
29/01/2025
Equans has been appointed by Babergh and Mid Suffolk District Councils to carry out crucial decarbonisation work across the councils' housing stock, using funding secured through the Social Housing Decarbonisation Fund (SHDF).
The councils used the South East Consortium's Zero Carbon Framework to s
29/01/2025
In the world of construction, the quest for energy efficiency and sustainability is ever-evolving. Among the array of solutions available, EPS (Expanded Polystyrene) insulation stands out as a versatile and effective option for enhancing the thermal performance of buildings, particularly when used f
29/01/2025
BCP Council has completed significant coastal protection works at Hamworthy Park, ensuring its resilience against erosion for the next 20 years.
A 200-metre stretch of sea wall along the eastern promenade has been reinforced using low-carbon concrete, while new steps have been constructed to improv
29/01/2025
Geo-environmental consultancy and remediation contractor, The LK Group, has strengthened its team with a trio of recruits.
The multidisciplinary company's latest raft of hires comprises a new director, associate director and remediation manager.
The geo-environmental specialist, headquartered i