CIS has completed a major pile-driving operation in conjunction with construction of a new $240 million state-of-the-art phosphates terminal in Jordan.
The terminal is purpose-built to export and handle upwards of six million tonnes of rock phosphate in bulk annually. It is located in the South Port section of the New Port of Aqaba, and features storage facilities, off-loading systems and handling and ship-loading equipment.
The Acteon company that installs conductors and piles for the oil and gas and nearshore marine construction industries performed a series of pile-driving operations to form the foundations of the new terminal, which features a new dry bulk export jetty, and dust and spillage control facilities. The storage plant, load transfer building, and berthing maritime terminal for exporting phosphates are located onshore. Offshore, the complex is comprised of a 190m-piloted berthing area with two parallel-to-coastline structures that support two loading bays, two mooring dolphins, an access bridge and two bridges that connect the structures.
With one of its S-150 hydraulic hammers situated offshore on a crane barge in depths of up to 23 meters (75.45 feet) and a second positioned onshore, the CIS crew operated the two hammers simultaneously. As a result, 16 piles measuring Ø914mm (36 inches) were driven to a maximum penetration of 25 metres (85.02 feet) to ensure that the essential onshore facilities would be built on solid foundations.
Following completion of the pile-driving phase carried out as part of the construction of the onshore portion of the jetty approach, CIS began working on the offshore construction phase. This involved driving 149 jetty support piles measuring Ø914mm (36 inches) as part of the construction of berthing structure and three bridges. Again, CIS drove the jetty support piles with pinpoint accuracy with the aid of surveyors and the hydraulic hammer on the piling crane. Every pile was safely driven to its intended target depth without incurring a single Lost Time Incident (LTI). All 165 piles were driven safely and efficiently, well within the requisite timeframe for completion.
Operating for the first time in Jordan, the operational aspects of the job were challenging.
"The logistics of working simultaneously onshore and offshore was in and of itself a challenge, compounded by the extremely high temperatures in Jordan," said James Chadd, Managing Director of CIS. "To address this, our engineers dedicated a great deal of time to developing a highly detailed pile-driving plan, with complete guidance on coordinating the onshore team with the crane barge. This detailed plan was finalised well in advance of the scheduled start date, paving the way for completing the job on schedule.
"The success of the operation should also be attributed to the experience of our crew and its meticulous attention to executing that plan to the letter. Plus, maintaining clear communications with the customer and all parties involved. The entire operation was completed on time without a single LTI and this illustrates our ability to work safely and efficiently. We look forward to executing many more pile-driving operations, as we gear up to expand our activities in this dynamic and challenging market."
To support the operation, CIS drew upon the expertise of its personnel and state-of-the-art hammer equipment based at the company's global headquarters in Great Yarmouth, England.
Time and date
CONSTRUCTION DIRECTORY
Latest Construction News
21/11/2024
Europe's leading online cleanroom consumables supplier, Cleanroomshop, has recently launched a brand-new website, giving its users an improved user experience. The new website continues to offer over 2,000 products from more than 40 brands, whilst incorporating a new look and more efficient ...
21/11/2024
At Ecomerchant, we offer a carefully curated selection of sustainable weatherproofing solutions, including natural lime renders, mineral finishes, and vapour-open waterproofing materials. They help prevent structural damage while ensuring your building can breathe naturally. Our eco-friendly ...
20/11/2024
Construction firm Willmott Dixon has partnered with Westminster City Council on a £36 million project to restore the historic Seymour Centre in Marylebone, a Grade II listed building dating back to the 1930s. The project, procured through the SCF framework, will see the three-storey centre undergo ...
20/11/2024
The Hill Group has commenced work on a new development in Billericay, Essex, which will deliver 179 high-quality homes across a 20-acre site. Designed to blend with Billericay's scenic countryside while addressing the pressing demand for sustainable housing, the project is located on Kennel Lane ...
20/11/2024
Extensive groundwork is underway for a new housing development in Maidstone, where Vistry Group, in partnership with Legal & General Affordable Homes, is set to build 272 properties on the site of the former Tovil Quarry off Farleigh Hill. The project will include 37 affordable homes for low-cost ...
20/11/2024
Stonewater has scooped a new energy efficiency retrofit contract with compliance and energy services provider Correct Contract Services. This work, funded through the Social Housing Decarbonisation Fund (SHDF) Wave 2, will include a range of energy-saving upgrades. Measures such as loft ...
20/11/2024
Kier has been appointed by Cambridgeshire County Council to deliver building, mechanical, and electrical maintenance services across the Council's portfolio of 160 corporate buildings. The contract, which began in November 2024, will run until 2027, with the possibility of two one-year extensions ...
20/11/2024
Builders use water for various functions on the job, they utilise this resource for worker hygiene, hydration, concrete batching, grouting, dust suppression, drilling and piling. If companies mismanage this water use, they can increase their environmental impact. When the industry comes ...
20/11/2024
Edmond Shipway has been appointed to a pioneering initiative tackling homelessness in Greater Manchester, providing project management and cost consultancy services on the second phase of Embassy Village. Set to deliver 40 purpose-built homes for men facing homelessness in Manchester, Embassy ...
20/11/2024
West Sussex County Council is inviting residents to share their views on proposed transport improvements at the Hazelwick and Tushmore junctions on the A2011 Crawley Avenue. The proposals aim to make walking, cycling, and public transport more appealing for short journeys. This initiative is part ...