M6 Smart Motorway Project Takes Significant Step Forward
Key work on the M6 J13-15 smart motorway project has brought the scheme a step closer to completion.
Kier Highways successfully installed three large cantilever gantries over a nine-night period while the motorway network remained open to customers.
Three gantries weighing 24 tonnes and 18m in width now span the carriageway on the M6 between J14 (Stafford) and J15 (Stoke) and were installed with a contraflow in operation. This meant that one lane of traffic was able to stay on the main motorway carriage travelling north on the southbound side. Traffic on the southbound side ran in three narrow lanes. Customers were able to continue travelling on their preferred route instead of being diverted along sensitive diversion routes around Stafford. A team of 57 people worked each of the nine nights to install the gantries along with six smaller MS4 gantries and 28 lighting columns.
This project is the first of its kind to operate under a full contraflow for the length of the works and its implementation is continuously increasing customer satisfaction through the roadworks. As work progresses to the opposite carriageway, the contraflow operation will switch in the New Year.
Richard French, project director at Kier Highways, said: "We are coming to the end of a section of work on the northbound M6 and this critical activity makes the end date significantly closer. All teams have planned their activities meticulously and collaboratively, so that the result is completion to plan and on programme. There is a large amount of personnel involved and I would like to thank everyone for their solid performance during this complex activity."
The M6 J13-15 smart motorway project is scheduled for completion by 2022.
Kier Highways successfully installed three large cantilever gantries over a nine-night period while the motorway network remained open to customers.
Three gantries weighing 24 tonnes and 18m in width now span the carriageway on the M6 between J14 (Stafford) and J15 (Stoke) and were installed with a contraflow in operation. This meant that one lane of traffic was able to stay on the main motorway carriage travelling north on the southbound side. Traffic on the southbound side ran in three narrow lanes. Customers were able to continue travelling on their preferred route instead of being diverted along sensitive diversion routes around Stafford. A team of 57 people worked each of the nine nights to install the gantries along with six smaller MS4 gantries and 28 lighting columns.
This project is the first of its kind to operate under a full contraflow for the length of the works and its implementation is continuously increasing customer satisfaction through the roadworks. As work progresses to the opposite carriageway, the contraflow operation will switch in the New Year.
Richard French, project director at Kier Highways, said: "We are coming to the end of a section of work on the northbound M6 and this critical activity makes the end date significantly closer. All teams have planned their activities meticulously and collaboratively, so that the result is completion to plan and on programme. There is a large amount of personnel involved and I would like to thank everyone for their solid performance during this complex activity."
The M6 J13-15 smart motorway project is scheduled for completion by 2022.
29/01/2025
Caddick Construction has been awarded a £43 million contract to deliver the first phase of Cole Waterhouse's flagship regeneration scheme in Digbeth, Birmingham.
The project, known as Upper Trinity Street, marks a significant step in the area’s transformation.
Spanning 182,986 square feet, the re
29/01/2025
McLaren Construction has been appointed by O&H Properties to deliver the first phase of a £60 million Foster & Partners-designed development at the corner of New Bond Street and Grafton Street in London’s West End.
The seven-storey, 5,400 square metre prime retail and office scheme will feature ret
29/01/2025
GMI Construction Group has been awarded a contract to develop three high-specification warehouse units totalling over 175,000 square feet at Precedent Drive, Milton Keynes.
The £20 million project, commissioned by DV5 Last Mile Developments (UK) Ltd, a joint venture between Coltham and Delancey Re
29/01/2025
Plans for 106 sustainable new homes in Southville, a neighbourhood in South Bristol, have been approved as the city seeks to increase housing delivery to address growing demand.
Top 10 award-winning housebuilder The Hill Group will create a £60 million development on Raleigh Road, on land that was
29/01/2025
Bouygues UK has reached a major milestone in the fourth phase of the Hallsville Quarter regeneration project in Canning Town, London.
The project, part of the £3.7 billion Canning Town and Custom House Regeneration Programme, recently held a topping out ceremony, marking the completion of the 11-s
29/01/2025
Willmott Dixon Interiors is carrying out a significant upgrade to the roof of the National Maritime Museum in Greenwich, one of London's most iconic cultural landmarks.
As part of the £12 million project, the company is installing over 23,000 square feet of sun-protected glazing above the museum’s
29/01/2025
Equans has been appointed by Babergh and Mid Suffolk District Councils to carry out crucial decarbonisation work across the councils' housing stock, using funding secured through the Social Housing Decarbonisation Fund (SHDF).
The councils used the South East Consortium's Zero Carbon Framework to s
29/01/2025
In the world of construction, the quest for energy efficiency and sustainability is ever-evolving. Among the array of solutions available, EPS (Expanded Polystyrene) insulation stands out as a versatile and effective option for enhancing the thermal performance of buildings, particularly when used f
29/01/2025
BCP Council has completed significant coastal protection works at Hamworthy Park, ensuring its resilience against erosion for the next 20 years.
A 200-metre stretch of sea wall along the eastern promenade has been reinforced using low-carbon concrete, while new steps have been constructed to improv
29/01/2025
Geo-environmental consultancy and remediation contractor, The LK Group, has strengthened its team with a trio of recruits.
The multidisciplinary company's latest raft of hires comprises a new director, associate director and remediation manager.
The geo-environmental specialist, headquartered i