Construction UK Construction Directory
Time and date
CONSTRUCTION DIRECTORY
Share this page
Construction News
18/11/2020

Collaborative Solutions For Water Treatment Works Upgrade

Construction News Image
Main contractor Murphy International, is currently undertaking a €40million contract, to upgrade the Lee Road Water Treatment Plant (WTP) in Cork city, on behalf of Irish Water.

The Lee Road WTP provides approximately 70% of Cork City’s total treated water supply and the upgraded plant will provide a more safe and secure water supply for the rapidly growing city.

The scope of works includes upgrading the existing WTP from its current capacity of 36,200m3 per day, to a new plant with approximately 40,000m3 over a 18 hour period, as well as associated testing, commissioning and operation of the plant for a one-year period.

The CSA scope of work includes construction of a treated water reservoir, filter washwater holding tank, raw water pumping station, ultraviolet (UV) chamber, filter blocks, sedimentation tank, admin building, sludge processing building, process building, process pipework, drainage & utilities, pavement construction, fencing and landscaping.

The 6no. underground reinforced concrete tanks require a number of major excavations which in turn, require structural support while the permanent works are carried out.

For this, Murphy International have employed Groundforce to supply its modular hydraulic props and waling beams, to support the steel sheet-piled cofferdam walls.

Groundforce equipment arrived on site in February of this year, when work started on the first cofferdam, which will accommodate the Reservoir Tank. Measuring 48m x 30m x 5m deep, this excavation was supported with a cofferdam, comprising 10m-long Larssen L605 steel sheet piles driven to a design toe depth, 4m below formation level.

To support the cofferdam, Groundforce supplied its hydraulic Super Mega Brace as a waling beam around the top of the excavation, and then installed four MP250 modular hydraulic props across each of the four corners to provide lateral support. A fifth MP250 prop spanning the full 30m width of the excavation was also installed. This unit employed Groundforce’s 1.2m-diameter “super tube” extensions, as an alternative to the standard 600mm-diameter tubes. The larger tubes provided the extra stiffness necessary to allow the prop, to span the full width of the excavation, without the need for any intermediate vertical support.

-- Advertisement --
hss

Dublin-based consulting engineer ByrneLooby, was employed by Murphy International to provide the temporary works design. Close collaboration between Murphy International, ByrneLooby and Groundforce succeeded in optimising the temporary works solution to provide an enhanced working environment and faster completion of the permanent works.

"Byrne Looby's design allowed for the removal of our frame, following installation of the 0.8m-thick base slab," explained Groundforce general manager Joseph Lenihan.

"This design feature was of considerable benefit to the scheme, because it led to reduced hire costs and provided for a clear opening, in which Murphy International could cast the reinforced concrete walls of the tank in one lift," he added.

Nick Peters, Senior Project Engineer with BryneLooby said: "Working closely with Groundforce allowed us to complete the design, meeting the client’s requirements to remove the support system following casting of the Reservoir Tank’s base slab. From experience of working on numerous schemes with Groundforce, our familiarity with the Groundforce systems made this design process all the easier. When difficulty arose in a section of the Reservoir Tank, we collaborated with Groundforce to propose a refinement to the design which met the client’s satisfaction."

The works involved the installation of 10m-long Larssen L605 steel sheet piles for the cofferdam which proved challenging due to the dense gravels encountered, made driving the sheet piles difficult. Pre-augering along the line of the sheetpiles to the toe depth, did help with the installation.

With the temporary works established and excavation progressing on the Reservoir Tank, work started in March on the second cofferdam for the Filter Washwater Holding Tank, measuring 32m x 15m x6m. This was followed in sequence by the 26m x 18m x 6m Raw Water Pumping Station cofferdam in June. Both excavations employed the same engineering solution as that used to good effect to support the Reservoir Tank cofferdam.

With three major excavations completed so far, Murphy International have two more excavations to complete over the coming months.

Seamus Corridan, CSA Project Manager for Murphy International said: "The Lee Road WTP site, located on the northern bank of the River Lee just upstream of Cork city centre, provided numerous engineering challenges, due to a tight site where some of the deep excavations were adjacent to the site boundaries, poor ground conditions, a high groundwater level, and highly permeable soils.

"As the project included the construction of 6no. underground RC tanks of varying plan dimensions & depths, the temporary works solution required an innovative approach. Murphy International engaged the services of Groundforce & Byrne Looby, at the outset of the project, to design a compliant, yet cost-effective temporary works solution.

"The detailed design for each of the cofferdams, involved the installation of sheetpiles, and a Groundforce shoring system. The Groundforce team were always extremely helpful to deal with, right through from design stage where they provided innovative & cost-effective solutions, to the installation / removal process where they were always available to provide guidance and hands-on experience."

Joseph Lenihan concluded: "Groundforce are delighted to be involved in the temporary works element of this critical infrastructure project. The temporary cofferdams required on this project are some of the largest seen on the island of Ireland in recent years. The solution proved economical thanks to effective collaboration between Murphy International, Byrne Looby and Groundforce."

Latest Construction News

20/11/2024

Construction firm Willmott Dixon has partnered with Westminster City Council on a £36 million project to restore the historic Seymour Centre in Marylebone, a Grade II listed building dating back to the 1930s. The project, procured through the SCF framework, will see the three-storey centre undergo ...
20/11/2024

The Hill Group has commenced work on a new development in Billericay, Essex, which will deliver 179 high-quality homes across a 20-acre site. Designed to blend with Billericay's scenic countryside while addressing the pressing demand for sustainable housing, the project is located on Kennel Lane ...
20/11/2024

Extensive groundwork is underway for a new housing development in Maidstone, where Vistry Group, in partnership with Legal & General Affordable Homes, is set to build 272 properties on the site of the former Tovil Quarry off Farleigh Hill. The project will include 37 affordable homes for low-cost ...
20/11/2024

Stonewater has scooped a new energy efficiency retrofit contract with compliance and energy services provider Correct Contract Services. This work, funded through the Social Housing Decarbonisation Fund (SHDF) Wave 2, will include a range of energy-saving upgrades. Measures such as loft ...
20/11/2024

Kier has been appointed by Cambridgeshire County Council to deliver building, mechanical, and electrical maintenance services across the Council's portfolio of 160 corporate buildings. The contract, which began in November 2024, will run until 2027, with the possibility of two one-year extensions ...
20/11/2024

Builders use water for various functions on the job, they utilise this resource for worker hygiene, hydration, concrete batching, grouting, dust suppression, drilling and piling. If companies mismanage this water use, they can increase their environmental impact. When the industry comes ...
20/11/2024

Edmond Shipway has been appointed to a pioneering initiative tackling homelessness in Greater Manchester, providing project management and cost consultancy services on the second phase of Embassy Village. Set to deliver 40 purpose-built homes for men facing homelessness in Manchester, Embassy ...
20/11/2024

West Sussex County Council is inviting residents to share their views on proposed transport improvements at the Hazelwick and Tushmore junctions on the A2011 Crawley Avenue. The proposals aim to make walking, cycling, and public transport more appealing for short journeys. This initiative is part ...
19/11/2024

McLaren Construction has commenced works at the first UK industrial scheme in the East Midlands for a joint venture with Garbe Industrial Real Estate GmbH and Invesco Real Estate. McLaren will oversee all aspects of construction for the £30 million project located in Shireoaks, Worksop - in the ...
19/11/2024

Pennyfarthing Homes has submitted a planning application for 74 new homes in Fordingbridge as part of its plans to build a neighbourhood of 342 homes on the northern edge of the Hampshire market town. The new development which is part of the wider scheme known as Forde Valley and follows ...
Think Construction Skills Ltd.Efco UK LtdAqua Direct LtdStuart CanvasBRICOFLOR UKLakeside HireT & D Glazing And Installation LimitedFoxtons Frames LtdGlass Block Installations LtdWelfare Unit Hire Ltd
Terms and Conditions
2024/11/21 10:50:58