Construction News
18/11/2020
Collaborative Solutions For Water Treatment Works Upgrade
Main contractor Murphy International, is currently undertaking a €40million contract, to upgrade the Lee Road Water Treatment Plant (WTP) in Cork city, on behalf of Irish Water.
The Lee Road WTP provides approximately 70% of Cork City’s total treated water supply and the upgraded plant will provide a more safe and secure water supply for the rapidly growing city.
The scope of works includes upgrading the existing WTP from its current capacity of 36,200m3 per day, to a new plant with approximately 40,000m3 over a 18 hour period, as well as associated testing, commissioning and operation of the plant for a one-year period.
The CSA scope of work includes construction of a treated water reservoir, filter washwater holding tank, raw water pumping station, ultraviolet (UV) chamber, filter blocks, sedimentation tank, admin building, sludge processing building, process building, process pipework, drainage & utilities, pavement construction, fencing and landscaping.
The 6no. underground reinforced concrete tanks require a number of major excavations which in turn, require structural support while the permanent works are carried out.
For this, Murphy International have employed Groundforce to supply its modular hydraulic props and waling beams, to support the steel sheet-piled cofferdam walls.
Groundforce equipment arrived on site in February of this year, when work started on the first cofferdam, which will accommodate the Reservoir Tank. Measuring 48m x 30m x 5m deep, this excavation was supported with a cofferdam, comprising 10m-long Larssen L605 steel sheet piles driven to a design toe depth, 4m below formation level.
To support the cofferdam, Groundforce supplied its hydraulic Super Mega Brace as a waling beam around the top of the excavation, and then installed four MP250 modular hydraulic props across each of the four corners to provide lateral support. A fifth MP250 prop spanning the full 30m width of the excavation was also installed. This unit employed Groundforce’s 1.2m-diameter “super tube” extensions, as an alternative to the standard 600mm-diameter tubes. The larger tubes provided the extra stiffness necessary to allow the prop, to span the full width of the excavation, without the need for any intermediate vertical support.
Dublin-based consulting engineer ByrneLooby, was employed by Murphy International to provide the temporary works design. Close collaboration between Murphy International, ByrneLooby and Groundforce succeeded in optimising the temporary works solution to provide an enhanced working environment and faster completion of the permanent works.
"Byrne Looby's design allowed for the removal of our frame, following installation of the 0.8m-thick base slab," explained Groundforce general manager Joseph Lenihan.
"This design feature was of considerable benefit to the scheme, because it led to reduced hire costs and provided for a clear opening, in which Murphy International could cast the reinforced concrete walls of the tank in one lift," he added.
Nick Peters, Senior Project Engineer with BryneLooby said: "Working closely with Groundforce allowed us to complete the design, meeting the client’s requirements to remove the support system following casting of the Reservoir Tank’s base slab. From experience of working on numerous schemes with Groundforce, our familiarity with the Groundforce systems made this design process all the easier. When difficulty arose in a section of the Reservoir Tank, we collaborated with Groundforce to propose a refinement to the design which met the client’s satisfaction."
The works involved the installation of 10m-long Larssen L605 steel sheet piles for the cofferdam which proved challenging due to the dense gravels encountered, made driving the sheet piles difficult. Pre-augering along the line of the sheetpiles to the toe depth, did help with the installation.
With the temporary works established and excavation progressing on the Reservoir Tank, work started in March on the second cofferdam for the Filter Washwater Holding Tank, measuring 32m x 15m x6m. This was followed in sequence by the 26m x 18m x 6m Raw Water Pumping Station cofferdam in June. Both excavations employed the same engineering solution as that used to good effect to support the Reservoir Tank cofferdam.
With three major excavations completed so far, Murphy International have two more excavations to complete over the coming months.
Seamus Corridan, CSA Project Manager for Murphy International said: "The Lee Road WTP site, located on the northern bank of the River Lee just upstream of Cork city centre, provided numerous engineering challenges, due to a tight site where some of the deep excavations were adjacent to the site boundaries, poor ground conditions, a high groundwater level, and highly permeable soils.
"As the project included the construction of 6no. underground RC tanks of varying plan dimensions & depths, the temporary works solution required an innovative approach. Murphy International engaged the services of Groundforce & Byrne Looby, at the outset of the project, to design a compliant, yet cost-effective temporary works solution.
"The detailed design for each of the cofferdams, involved the installation of sheetpiles, and a Groundforce shoring system. The Groundforce team were always extremely helpful to deal with, right through from design stage where they provided innovative & cost-effective solutions, to the installation / removal process where they were always available to provide guidance and hands-on experience."
Joseph Lenihan concluded: "Groundforce are delighted to be involved in the temporary works element of this critical infrastructure project. The temporary cofferdams required on this project are some of the largest seen on the island of Ireland in recent years. The solution proved economical thanks to effective collaboration between Murphy International, Byrne Looby and Groundforce."
The Lee Road WTP provides approximately 70% of Cork City’s total treated water supply and the upgraded plant will provide a more safe and secure water supply for the rapidly growing city.
The scope of works includes upgrading the existing WTP from its current capacity of 36,200m3 per day, to a new plant with approximately 40,000m3 over a 18 hour period, as well as associated testing, commissioning and operation of the plant for a one-year period.
The CSA scope of work includes construction of a treated water reservoir, filter washwater holding tank, raw water pumping station, ultraviolet (UV) chamber, filter blocks, sedimentation tank, admin building, sludge processing building, process building, process pipework, drainage & utilities, pavement construction, fencing and landscaping.
The 6no. underground reinforced concrete tanks require a number of major excavations which in turn, require structural support while the permanent works are carried out.
For this, Murphy International have employed Groundforce to supply its modular hydraulic props and waling beams, to support the steel sheet-piled cofferdam walls.
Groundforce equipment arrived on site in February of this year, when work started on the first cofferdam, which will accommodate the Reservoir Tank. Measuring 48m x 30m x 5m deep, this excavation was supported with a cofferdam, comprising 10m-long Larssen L605 steel sheet piles driven to a design toe depth, 4m below formation level.
To support the cofferdam, Groundforce supplied its hydraulic Super Mega Brace as a waling beam around the top of the excavation, and then installed four MP250 modular hydraulic props across each of the four corners to provide lateral support. A fifth MP250 prop spanning the full 30m width of the excavation was also installed. This unit employed Groundforce’s 1.2m-diameter “super tube” extensions, as an alternative to the standard 600mm-diameter tubes. The larger tubes provided the extra stiffness necessary to allow the prop, to span the full width of the excavation, without the need for any intermediate vertical support.
Dublin-based consulting engineer ByrneLooby, was employed by Murphy International to provide the temporary works design. Close collaboration between Murphy International, ByrneLooby and Groundforce succeeded in optimising the temporary works solution to provide an enhanced working environment and faster completion of the permanent works.
"Byrne Looby's design allowed for the removal of our frame, following installation of the 0.8m-thick base slab," explained Groundforce general manager Joseph Lenihan.
"This design feature was of considerable benefit to the scheme, because it led to reduced hire costs and provided for a clear opening, in which Murphy International could cast the reinforced concrete walls of the tank in one lift," he added.
Nick Peters, Senior Project Engineer with BryneLooby said: "Working closely with Groundforce allowed us to complete the design, meeting the client’s requirements to remove the support system following casting of the Reservoir Tank’s base slab. From experience of working on numerous schemes with Groundforce, our familiarity with the Groundforce systems made this design process all the easier. When difficulty arose in a section of the Reservoir Tank, we collaborated with Groundforce to propose a refinement to the design which met the client’s satisfaction."
The works involved the installation of 10m-long Larssen L605 steel sheet piles for the cofferdam which proved challenging due to the dense gravels encountered, made driving the sheet piles difficult. Pre-augering along the line of the sheetpiles to the toe depth, did help with the installation.
With the temporary works established and excavation progressing on the Reservoir Tank, work started in March on the second cofferdam for the Filter Washwater Holding Tank, measuring 32m x 15m x6m. This was followed in sequence by the 26m x 18m x 6m Raw Water Pumping Station cofferdam in June. Both excavations employed the same engineering solution as that used to good effect to support the Reservoir Tank cofferdam.
With three major excavations completed so far, Murphy International have two more excavations to complete over the coming months.
Seamus Corridan, CSA Project Manager for Murphy International said: "The Lee Road WTP site, located on the northern bank of the River Lee just upstream of Cork city centre, provided numerous engineering challenges, due to a tight site where some of the deep excavations were adjacent to the site boundaries, poor ground conditions, a high groundwater level, and highly permeable soils.
"As the project included the construction of 6no. underground RC tanks of varying plan dimensions & depths, the temporary works solution required an innovative approach. Murphy International engaged the services of Groundforce & Byrne Looby, at the outset of the project, to design a compliant, yet cost-effective temporary works solution.
"The detailed design for each of the cofferdams, involved the installation of sheetpiles, and a Groundforce shoring system. The Groundforce team were always extremely helpful to deal with, right through from design stage where they provided innovative & cost-effective solutions, to the installation / removal process where they were always available to provide guidance and hands-on experience."
Joseph Lenihan concluded: "Groundforce are delighted to be involved in the temporary works element of this critical infrastructure project. The temporary cofferdams required on this project are some of the largest seen on the island of Ireland in recent years. The solution proved economical thanks to effective collaboration between Murphy International, Byrne Looby and Groundforce."
29/01/2025
Caddick Construction has been awarded a £43 million contract to deliver the first phase of Cole Waterhouse's flagship regeneration scheme in Digbeth, Birmingham.
The project, known as Upper Trinity Street, marks a significant step in the area’s transformation.
Spanning 182,986 square feet, the re
29/01/2025
McLaren Construction has been appointed by O&H Properties to deliver the first phase of a £60 million Foster & Partners-designed development at the corner of New Bond Street and Grafton Street in London’s West End.
The seven-storey, 5,400 square metre prime retail and office scheme will feature ret
29/01/2025
GMI Construction Group has been awarded a contract to develop three high-specification warehouse units totalling over 175,000 square feet at Precedent Drive, Milton Keynes.
The £20 million project, commissioned by DV5 Last Mile Developments (UK) Ltd, a joint venture between Coltham and Delancey Re
29/01/2025
Plans for 106 sustainable new homes in Southville, a neighbourhood in South Bristol, have been approved as the city seeks to increase housing delivery to address growing demand.
Top 10 award-winning housebuilder The Hill Group will create a £60 million development on Raleigh Road, on land that was
29/01/2025
Bouygues UK has reached a major milestone in the fourth phase of the Hallsville Quarter regeneration project in Canning Town, London.
The project, part of the £3.7 billion Canning Town and Custom House Regeneration Programme, recently held a topping out ceremony, marking the completion of the 11-s
29/01/2025
Willmott Dixon Interiors is carrying out a significant upgrade to the roof of the National Maritime Museum in Greenwich, one of London's most iconic cultural landmarks.
As part of the £12 million project, the company is installing over 23,000 square feet of sun-protected glazing above the museum’s
29/01/2025
Equans has been appointed by Babergh and Mid Suffolk District Councils to carry out crucial decarbonisation work across the councils' housing stock, using funding secured through the Social Housing Decarbonisation Fund (SHDF).
The councils used the South East Consortium's Zero Carbon Framework to s
29/01/2025
In the world of construction, the quest for energy efficiency and sustainability is ever-evolving. Among the array of solutions available, EPS (Expanded Polystyrene) insulation stands out as a versatile and effective option for enhancing the thermal performance of buildings, particularly when used f
29/01/2025
BCP Council has completed significant coastal protection works at Hamworthy Park, ensuring its resilience against erosion for the next 20 years.
A 200-metre stretch of sea wall along the eastern promenade has been reinforced using low-carbon concrete, while new steps have been constructed to improv
29/01/2025
Geo-environmental consultancy and remediation contractor, The LK Group, has strengthened its team with a trio of recruits.
The multidisciplinary company's latest raft of hires comprises a new director, associate director and remediation manager.
The geo-environmental specialist, headquartered i