Construction News
13/08/2021
Work Complete To Upgrade Runway At RAF Oldham
Improvement work has been completed to upgrade the runway and associated airfield lighting at RAF Odiham, home of the UK Chinook Force.
Amey’s Transport Infrastructure and Defence teams in conjunction with Levertech Aviation Services delivered the £5.5 million contract.
The work was carried out on behalf of the client, the Defence Infrastructure Organisation (DIO).
Funds comprising £2.9m for the runway and £2.6m for lighting were mobilised within 10 days to enable works to start just before Christmas.
The works, which were needed to increase the friction levels on the runway to maintain safe operations for fixed wing aircraft, saw the top 40mm of the runway removed and replaced with 8,500 tonnes of asphalt. This important project will extend the life of the runway for another 15 years.
All works were undertaken during the day, allowing the runway and RAF Odiham to remain operational for rotary aircraft movements throughout the surfacing works. This was achieved by splitting the runway into two halves, with Amey working on one half of the runway and RAF Odiham operating from the other. Once the first half of the runway had been resurfaced, operations switched so that work could commence on the second half. Amey also supported the Station by facilitating land movement of Chinooks, and over 1,000 asphalt delivery vehicles, through an alternative side gate to reduce the impact of the project on the main gate and the surrounding RAF Odiham Road network.
During work, the UK entered its third lockdown and modifications to the testing regime needed to be agreed. A pragmatic approach was taken by DIO’s subject matter experts to reduce the frequency of testing where social distancing rules could not take place, with the laboratory technicians working together in a bubble.
Consultation with private landowners had to take place for lighting works to replace all aeronautical ground lighting services for the runway, including elevated edge, threshold and end and both elevated approaches as approach masts are located within private farmland. Other work involved replacing existing constant current regulators, cabling and transformers alongside installation of two new standby package generators.
Tim Redfern, Amey's Managing Director Defence, said: "I'm delighted that once again, the collaborative efforts of Amey’s Transport Infrastructure and Defence teams has resulted in successful handover of upgraded runway works at this important site. By combining the expertise of both teams, we have delivered real benefit to the client, DIO, and have future proofed this vital asset for the Armed Forces."
Amey’s Transport Infrastructure and Defence teams in conjunction with Levertech Aviation Services delivered the £5.5 million contract.
The work was carried out on behalf of the client, the Defence Infrastructure Organisation (DIO).
Funds comprising £2.9m for the runway and £2.6m for lighting were mobilised within 10 days to enable works to start just before Christmas.
The works, which were needed to increase the friction levels on the runway to maintain safe operations for fixed wing aircraft, saw the top 40mm of the runway removed and replaced with 8,500 tonnes of asphalt. This important project will extend the life of the runway for another 15 years.
All works were undertaken during the day, allowing the runway and RAF Odiham to remain operational for rotary aircraft movements throughout the surfacing works. This was achieved by splitting the runway into two halves, with Amey working on one half of the runway and RAF Odiham operating from the other. Once the first half of the runway had been resurfaced, operations switched so that work could commence on the second half. Amey also supported the Station by facilitating land movement of Chinooks, and over 1,000 asphalt delivery vehicles, through an alternative side gate to reduce the impact of the project on the main gate and the surrounding RAF Odiham Road network.
During work, the UK entered its third lockdown and modifications to the testing regime needed to be agreed. A pragmatic approach was taken by DIO’s subject matter experts to reduce the frequency of testing where social distancing rules could not take place, with the laboratory technicians working together in a bubble.
Consultation with private landowners had to take place for lighting works to replace all aeronautical ground lighting services for the runway, including elevated edge, threshold and end and both elevated approaches as approach masts are located within private farmland. Other work involved replacing existing constant current regulators, cabling and transformers alongside installation of two new standby package generators.
Tim Redfern, Amey's Managing Director Defence, said: "I'm delighted that once again, the collaborative efforts of Amey’s Transport Infrastructure and Defence teams has resulted in successful handover of upgraded runway works at this important site. By combining the expertise of both teams, we have delivered real benefit to the client, DIO, and have future proofed this vital asset for the Armed Forces."
29/01/2025
Caddick Construction has been awarded a £43 million contract to deliver the first phase of Cole Waterhouse's flagship regeneration scheme in Digbeth, Birmingham.
The project, known as Upper Trinity Street, marks a significant step in the area’s transformation.
Spanning 182,986 square feet, the re
29/01/2025
McLaren Construction has been appointed by O&H Properties to deliver the first phase of a £60 million Foster & Partners-designed development at the corner of New Bond Street and Grafton Street in London’s West End.
The seven-storey, 5,400 square metre prime retail and office scheme will feature ret
29/01/2025
GMI Construction Group has been awarded a contract to develop three high-specification warehouse units totalling over 175,000 square feet at Precedent Drive, Milton Keynes.
The £20 million project, commissioned by DV5 Last Mile Developments (UK) Ltd, a joint venture between Coltham and Delancey Re
29/01/2025
Plans for 106 sustainable new homes in Southville, a neighbourhood in South Bristol, have been approved as the city seeks to increase housing delivery to address growing demand.
Top 10 award-winning housebuilder The Hill Group will create a £60 million development on Raleigh Road, on land that was
29/01/2025
Bouygues UK has reached a major milestone in the fourth phase of the Hallsville Quarter regeneration project in Canning Town, London.
The project, part of the £3.7 billion Canning Town and Custom House Regeneration Programme, recently held a topping out ceremony, marking the completion of the 11-s
29/01/2025
Willmott Dixon Interiors is carrying out a significant upgrade to the roof of the National Maritime Museum in Greenwich, one of London's most iconic cultural landmarks.
As part of the £12 million project, the company is installing over 23,000 square feet of sun-protected glazing above the museum’s
29/01/2025
Equans has been appointed by Babergh and Mid Suffolk District Councils to carry out crucial decarbonisation work across the councils' housing stock, using funding secured through the Social Housing Decarbonisation Fund (SHDF).
The councils used the South East Consortium's Zero Carbon Framework to s
29/01/2025
In the world of construction, the quest for energy efficiency and sustainability is ever-evolving. Among the array of solutions available, EPS (Expanded Polystyrene) insulation stands out as a versatile and effective option for enhancing the thermal performance of buildings, particularly when used f
29/01/2025
BCP Council has completed significant coastal protection works at Hamworthy Park, ensuring its resilience against erosion for the next 20 years.
A 200-metre stretch of sea wall along the eastern promenade has been reinforced using low-carbon concrete, while new steps have been constructed to improv
29/01/2025
Geo-environmental consultancy and remediation contractor, The LK Group, has strengthened its team with a trio of recruits.
The multidisciplinary company's latest raft of hires comprises a new director, associate director and remediation manager.
The geo-environmental specialist, headquartered i