GRAHAM Selected To Deliver New Bridge And Link Road
![Construction News Image](https://www.construction.co.uk/newsimages/1_284508_Graham.jpg)
GRAHAM has been selected as the Principal Contractor to deliver a new bridge and link road as part of the Chelmsford East Beaulieu S278 Works (RDR Phase 3) project.
The £16.77 million project will connect the A130 Essex Regiment Way and the Beaulieu and Channels housing developments, on the west side of the Great Eastern Main Line (GEML) railway lines to the A12 Boreham interchange on the east side of the railway.
The scheme will see the delivery of new highways infrastructure to facilitate future phases of development at the Beaulieu Development in Chelmsford for the client Countryside and L&Q..
The works comprise of a new three-span bridge over the Great Eastern Main Line railway and A12 slip-road; and approach embankments on either side linking into the new Radial Distributor Road (RDR) and the existing Boreham Interchange.
The infrastructure will also form part of a local bus route and the principal HGV traffic route between the A12 and Braintree and provide a link between the proposed new Beaulieu railway station on the east side of the railway.
GRAHAM has already delivered the pre-construction phase of the contract, which required a fully coordinated design and installation methodology to meet the approval and standards of Highways England and Network Rail.
As part of the contract, GRAHAM will provide the construction of a range of new highway infrastructure, including:
• A new three-span highway bridge structure
• Piling
• Earthworks
• Soil retaining walls
• Bearings
• Stormwater (SUDS) drainage
• Road construction to include provision for pedestrians
• Traffic signs and road markings
• Traffic signal loops
• Street lighting
• Fencing
• Vehicle restraint systems.
• Utility ducts
• Temporary works
• Other ancillary works
• Coordination with and programming of the works of statutory undertakers to carry out required diversion/protection works on the public highway
• All associated Traffic Management Works
The new Beaulieu Rail Bridge will be a 161m long three-span structure of composite weathering steel fabricated plate girders on in-situ reinforced concrete column abutments and piers, with reinforced concrete pile-caps and bored cast in place reinforced concrete piles. The girders will be a constant depth over their full length.
The superstructure will be constructed on site, off-line on adjacent land. GRAHAM will carry out the installation by raising the complete superstructure using Self Propelled Modular Transporters (SPMT) which will carry it to its final position before lowering it onto the permanent bearings.
This methodology has been used by GRAHAM successfully on previous bridge installations, notably on the Carpenter’s Land Bridge in 2020, a project that linked London's East Bank to its International Quarter.
The £16.77 million project will connect the A130 Essex Regiment Way and the Beaulieu and Channels housing developments, on the west side of the Great Eastern Main Line (GEML) railway lines to the A12 Boreham interchange on the east side of the railway.
The scheme will see the delivery of new highways infrastructure to facilitate future phases of development at the Beaulieu Development in Chelmsford for the client Countryside and L&Q..
The works comprise of a new three-span bridge over the Great Eastern Main Line railway and A12 slip-road; and approach embankments on either side linking into the new Radial Distributor Road (RDR) and the existing Boreham Interchange.
The infrastructure will also form part of a local bus route and the principal HGV traffic route between the A12 and Braintree and provide a link between the proposed new Beaulieu railway station on the east side of the railway.
GRAHAM has already delivered the pre-construction phase of the contract, which required a fully coordinated design and installation methodology to meet the approval and standards of Highways England and Network Rail.
As part of the contract, GRAHAM will provide the construction of a range of new highway infrastructure, including:
• A new three-span highway bridge structure
• Piling
• Earthworks
• Soil retaining walls
• Bearings
• Stormwater (SUDS) drainage
• Road construction to include provision for pedestrians
• Traffic signs and road markings
• Traffic signal loops
• Street lighting
• Fencing
• Vehicle restraint systems.
• Utility ducts
• Temporary works
• Other ancillary works
• Coordination with and programming of the works of statutory undertakers to carry out required diversion/protection works on the public highway
• All associated Traffic Management Works
The new Beaulieu Rail Bridge will be a 161m long three-span structure of composite weathering steel fabricated plate girders on in-situ reinforced concrete column abutments and piers, with reinforced concrete pile-caps and bored cast in place reinforced concrete piles. The girders will be a constant depth over their full length.
The superstructure will be constructed on site, off-line on adjacent land. GRAHAM will carry out the installation by raising the complete superstructure using Self Propelled Modular Transporters (SPMT) which will carry it to its final position before lowering it onto the permanent bearings.
This methodology has been used by GRAHAM successfully on previous bridge installations, notably on the Carpenter’s Land Bridge in 2020, a project that linked London's East Bank to its International Quarter.
![](https://www.construction.co.uk/newsimages/1_315943_stockport.jpg)
05/02/2025
Stockport Mayoral Development Corporation (MDC) and ECF, a joint venture between Homes England, Legal & General, and Muse, have selected Vinci as the preferred contractor for Phase 1 of Stockport 8, a £350 million residential development west of Stockport town centre.
The decision follows a competi
![](https://www.construction.co.uk/newsimages/1_315945_vistry.jpg)
05/02/2025
Vistry Group has finalised contracts for a significant housing development in Hinckley, Leicestershire, securing outline planning permission to deliver 475 new homes in the area.
The development, located east of Stoke Road and north of Normandy Way in the town's northern region, has a projected val
![](https://www.construction.co.uk/newsimages/1_315947_gateway14.jpg)
05/02/2025
Wilten Construction has been awarded a second Design and Build contract at Gateway 14 by client Gateway 14 Ltd and Jaynic.
The project involves the development of a state-of-the-art, three-storey Skills and Innovation Centre spanning 35,000 sq ft in the heart of Gateway 14. Designed to achieve BREE
![](https://www.construction.co.uk/newsimages/1_315958_kirkby.jpg)
05/02/2025
Knowsley Council has approved a major housing development in Kirkby, giving the green light to 800 new energy-efficient homes in the town's centre.
The decision also secures £7.7 million in Section 106 contributions from developer Barratt David Wilson Homes, further boosting local investment.
The
![](https://www.construction.co.uk/newsimages/1_315954_keepmoat.jpg)
05/02/2025
Keepmoat Homes has announced plans to invest over £50 million in three new housing developments across Calderdale, aiming to deliver more than 200 new homes.
The developments, undertaken in partnership with Calderdale Council, form part of the North Halifax Transformation Programme, a local authori
![](https://www.construction.co.uk/newsimages/1_315951_driffield.jpg)
05/02/2025
Essential renewal work at Skerne Road level crossing in Driffield has been completed. Over a six-day period, engineers replaced decades-old equipment, installing a state-of-the-art operating system, replacing the level crossing deck, and resurfacing the road.
The newly installed operating system is
![](https://www.construction.co.uk/newsimages/1_315953_graham.jpg)
05/02/2025
Construction firm GRAHAM is currently carrying out essential restoration work at the National Railway Museum in York, replacing the Grade II listed roof structure at Station Hall.
Originally built between 1875 and 1877 as a goods station, Station Hall now houses the museum’s six royal carriages.
![](https://www.construction.co.uk/newsimages/1_315975_mezzanine.jpg)
05/02/2025
Mezzanine floors are commonly associated with additional storage or expanded floor space, but did you know they can also have a profound impact on employee productivity and morale? At Doity Engineering, we specialise in designing and installing mezzanine floors for
![](https://www.construction.co.uk/newsimages/1_315978_weeton.jpg)
05/02/2025
Construction work is commencing on a new solar array at Weeton Barracks in Lancashire that will generate over one third of the site’s energy needs.
The work has been funded under the British Army’s Project Prometheus, a scheme that is increasing renewable energy across the army estate through inst
![](https://www.construction.co.uk/newsimages/1_315977_hartlepool.jpg)
05/02/2025
The regeneration of Hartlepool's waterfront has reached a significant milestone with a £631,000 grant from The National Lottery Heritage Fund.
The funding will support the development phase of the 'Tides of Change' project, aimed at transforming the visitor experience at the Museum of Hartlepool a