Work Commences On New Shared Cycleway/Walkway Route
Construction work is to has started on a 2km-long shared cycleway/walkway route, connecting Findon Valley with the South Downs National Park gateway of Findon Village in West Sessex.
The new route will provide a link for those wanting to opt for a more active way of travelling to see one of the county's attractions – the South Downs. It also has the advantage of linking in with an existing cycleway south of the Findon Valley shops, towards the A27 and a signed route into Worthing town centre.
The cycleway/walkway will be paid for with money from a Government grant for Active Travel projects. It is part of the County Council’s Active Travel improvement proposals, which aim to:
• make walking and cycling to work, education and leisure activities more attractive
• improve health and wellbeing by offering eco-friendly travel choices
• broaden travel choices by offering safer, quick and easy walking and cycling options, particularly for short journeys
• support zero emission journeys and reduce reliance on car travel.
The shared cycle/footway will be built on the eastern side of the A24 from its junction with Findon High Street southwards to the May Tree Avenue junction.
A significant stretch of the route will be off-carriageway and on the eastern side of the A24, with the rest on quiet, residential roads.
The route will divert from the A24 behind the Findon Valley shops on-carriageway via May Tree Avenue and Lime Tree Avenue. The cycle route here will comprise traffic signage and cycle road markings only.
The scheme will be built in five phases, with the first starting on Tuesday – subject to unforeseen factors, such as severe weather.
Phase 1 High Street to Cross Lane.
Phase 2 Junction works at Cross Lane/A24 junction.
Phase 3 Junction works at Nepcote/A24 junction.
Phase 4 Nepcote to May Tree Avenue.
Phase 5 May Tree Avenue/ Lime Tree Avenue.
Single traffic lanes will be maintained on the dual carriageway A24 Findon Bypass for most of the project. Some tree works, carriageway surfacing, and kerbing works will require temporary traffic lights for the protection of both the public and workforce. These periods will be kept to a minimum and at off-peak times, where possible.
Construction of the shared path will require temporary closures to the eastern footpath along the A24 while works progress. However, the works will be done in phases to limit the closure lengths and the western footpath will remain open to pedestrians throughout.
The new route will provide a link for those wanting to opt for a more active way of travelling to see one of the county's attractions – the South Downs. It also has the advantage of linking in with an existing cycleway south of the Findon Valley shops, towards the A27 and a signed route into Worthing town centre.
The cycleway/walkway will be paid for with money from a Government grant for Active Travel projects. It is part of the County Council’s Active Travel improvement proposals, which aim to:
• make walking and cycling to work, education and leisure activities more attractive
• improve health and wellbeing by offering eco-friendly travel choices
• broaden travel choices by offering safer, quick and easy walking and cycling options, particularly for short journeys
• support zero emission journeys and reduce reliance on car travel.
The shared cycle/footway will be built on the eastern side of the A24 from its junction with Findon High Street southwards to the May Tree Avenue junction.
A significant stretch of the route will be off-carriageway and on the eastern side of the A24, with the rest on quiet, residential roads.
The route will divert from the A24 behind the Findon Valley shops on-carriageway via May Tree Avenue and Lime Tree Avenue. The cycle route here will comprise traffic signage and cycle road markings only.
The scheme will be built in five phases, with the first starting on Tuesday – subject to unforeseen factors, such as severe weather.
Phase 1 High Street to Cross Lane.
Phase 2 Junction works at Cross Lane/A24 junction.
Phase 3 Junction works at Nepcote/A24 junction.
Phase 4 Nepcote to May Tree Avenue.
Phase 5 May Tree Avenue/ Lime Tree Avenue.
Single traffic lanes will be maintained on the dual carriageway A24 Findon Bypass for most of the project. Some tree works, carriageway surfacing, and kerbing works will require temporary traffic lights for the protection of both the public and workforce. These periods will be kept to a minimum and at off-peak times, where possible.
Construction of the shared path will require temporary closures to the eastern footpath along the A24 while works progress. However, the works will be done in phases to limit the closure lengths and the western footpath will remain open to pedestrians throughout.
29/01/2025
Caddick Construction has been awarded a £43 million contract to deliver the first phase of Cole Waterhouse's flagship regeneration scheme in Digbeth, Birmingham.
The project, known as Upper Trinity Street, marks a significant step in the area’s transformation.
Spanning 182,986 square feet, the re
29/01/2025
McLaren Construction has been appointed by O&H Properties to deliver the first phase of a £60 million Foster & Partners-designed development at the corner of New Bond Street and Grafton Street in London’s West End.
The seven-storey, 5,400 square metre prime retail and office scheme will feature ret
29/01/2025
GMI Construction Group has been awarded a contract to develop three high-specification warehouse units totalling over 175,000 square feet at Precedent Drive, Milton Keynes.
The £20 million project, commissioned by DV5 Last Mile Developments (UK) Ltd, a joint venture between Coltham and Delancey Re
29/01/2025
Plans for 106 sustainable new homes in Southville, a neighbourhood in South Bristol, have been approved as the city seeks to increase housing delivery to address growing demand.
Top 10 award-winning housebuilder The Hill Group will create a £60 million development on Raleigh Road, on land that was
29/01/2025
Bouygues UK has reached a major milestone in the fourth phase of the Hallsville Quarter regeneration project in Canning Town, London.
The project, part of the £3.7 billion Canning Town and Custom House Regeneration Programme, recently held a topping out ceremony, marking the completion of the 11-s
29/01/2025
Willmott Dixon Interiors is carrying out a significant upgrade to the roof of the National Maritime Museum in Greenwich, one of London's most iconic cultural landmarks.
As part of the £12 million project, the company is installing over 23,000 square feet of sun-protected glazing above the museum’s
29/01/2025
Equans has been appointed by Babergh and Mid Suffolk District Councils to carry out crucial decarbonisation work across the councils' housing stock, using funding secured through the Social Housing Decarbonisation Fund (SHDF).
The councils used the South East Consortium's Zero Carbon Framework to s
29/01/2025
In the world of construction, the quest for energy efficiency and sustainability is ever-evolving. Among the array of solutions available, EPS (Expanded Polystyrene) insulation stands out as a versatile and effective option for enhancing the thermal performance of buildings, particularly when used f
29/01/2025
BCP Council has completed significant coastal protection works at Hamworthy Park, ensuring its resilience against erosion for the next 20 years.
A 200-metre stretch of sea wall along the eastern promenade has been reinforced using low-carbon concrete, while new steps have been constructed to improv
29/01/2025
Geo-environmental consultancy and remediation contractor, The LK Group, has strengthened its team with a trio of recruits.
The multidisciplinary company's latest raft of hires comprises a new director, associate director and remediation manager.
The geo-environmental specialist, headquartered i