Tunnelling Machines Digging HS2's Longest Tunnels Pass Second Ventilation Shaft

Construction News Image
Two 2,000 tonne tunnelling machines digging HS2's longest tunnels passed the second of five ventilation shafts, four miles into their 10 mile drive under the Chilterns.

The milestone comes a week after the launch of another giant TBM in Ruislip which begin excavating the London tunnels for the high speed rail project linking the capital with the Midlands and the North.

Designed specifically for the geology of the Chilterns, the first TBMs – named Florence and Cecilia – were launched in Summer 2021 from the southern portal of the tunnels.

Each machine is a 170m long self-contained underground factory, digging the tunnel, lining it with concrete segments to form rings and grouting them into place as it moves forward.

More than 44,000 segments have been used to form the concrete rings that line the tunnels, with a further 68,000 set to be installed before the TBMs break out at the northern end of the tunnel in two years’ time.

-- Advertisement --
hss

The 46m deep shaft at Chalfont St Giles is one of four that will provide ventilation and emergency access to the ten-mile-long twin tunnels. A fifth will just provide emergency access. Once complete, the shaft will be covered by a headhouse designed to resemble local farm buildings.

More than 27,000 jobs are already being supported by HS2, which is designed to transform transport links between Britai'’s major cities, free up space on the rail network for more freight and local services and support the UK’s transition to net zero carbon emissions.

Martyn Noak, HS2 Ltd’s Head of Tunnel Engineering, said: "The Chiltern tunnel will take HS2 underneath the hills and safeguard the woodlands and wildlife habits above ground as well as significantly reducing disruption to communities during construction and operation of the new railway.

"It's great to see how much progress has been made by Florence and Cecilia – and the teams excavating the five shafts – and I’d like to thank everyone involved in getting us this far."

These first two TBMs on the HS2 project are operated by, Align – a joint venture formed of Bouygues Travaux Publics, Sir Robert McAlpine, and VolkerFitzpatrick.

Each machine has a crew of 17 people, working in shifts and supported by over 100 people on the surface, managing the logistics and maintaining the smooth progress of the tunnelling operation.

Latest Construction News

07/01/2025

Plans for a cutting-edge Day Case Surgery and Imaging Centre at Harrogate District Hospital are moving ahead, following the signing of a construction contract between Harrogate and District NHS Foundation Trust (HDFT) and Morgan Sindall Construction. The £50 million project, funded by HDFT and NHS ...
07/01/2025

Construction has begun on Max Spielman's new warehouse at Bromborough’s International Business Park, marking a significant milestone for the Timpson Group’s printing specialist. The facility will be the first owned and occupied premises for Max Spielman since the Timpson Group acquired the brand ...
07/01/2025

Winvic Construction Ltd has completed the third project awarded to it under the Lincolnshire County Council (LCC) highways framework contract. Major improvements on Dysart Road in Grantham, Lincolnshire, were completed a month ahead of schedule on 20th December, marking the end of a four-month ...
07/01/2025

Lambeth Council has taken a significant step forward to address the borough's housing crisis, announcing plans to partner with a Development Partner to deliver up to 450 new homes. The project, titled 'New Homes 6' (NH6), will see the construction of homes across six different sites in Lambeth. At ...
07/01/2025

Engineers are set to carry out essential improvements to Driffield's Skerne Road level crossing, aiming to boost rail reliability and enhance safety for pedestrians, motorists, and rail passengers. The upgrade work will take place from 7 am on Tuesday, January 28, to 7 am on Monday, February 3, ...
07/01/2025

Costain has appointed Eva Soto Pérez as engineering services general manager. Eva will be responsible for engineering design delivery and growth across the business. With more than 25 years' experience in engineering and infrastructure, Eva joins from Morgan Sindall Infrastructure where she was ...
07/01/2025

Vistry Group has joined forces with Paradigm Housing Group and Leaf Living to deliver 370 homes on a newly acquired site in Kidlington, near Oxford. The development, situated near Oxford Parkway station and Oxford Park and Ride, has outline planning permission. Vistry is collaborating with ...
07/01/2025

EDF has teamed up with with Hypervolt, a leading EV charge-point manufacturer and software provider. With EDF Wholesale Market Services' PowerShift technology, the collaboration will explore leveraging the capability of Hypervolt's UltraGrid software to enable a frequency response service from ...
06/01/2025

Persimmon Homes and Taylor Wimpey have announced that reserved matters approval has been secured for the first primary school within the Valley Park development in Didcot, marking a major milestone in the 4,254-home project. The new educational facility, located in the northern phase of Valley ...
06/01/2025

Engineers have successfully completed a challenging track renewal project through the narrow confines of Northchurch Tunnel, a Victorian-era structure on the West Coast Main Line, enhancing journeys for both passengers and freight. The work, led by Network Rail and its contractors, began on New ...
BRICOFLOR UKT & D Glazing And Installation LimitedEfco UK LtdStuart CanvasAqua Direct LtdLakeside HireThink Construction Skills Ltd.ContainexNo Hydro123v Plc
Terms and Conditions
2025/01/08 07:42:57