HS2 has established a rebar threading facility to address materials shortages at its Copthall tunnel construction site in Hillingdon - creating jobs, cutting waste and reducing lorry movements.
The new facility will make 92,000 rebar couplers, needed to construct the Copthall tunnel.
The Skanska Costain STRABAG joint venture (SCS JV) team constructing the tunnel were faced with delays due to a shortfall of available prefabricated fatigue rated rebar couplers, after suppliers had exited the market. To address this, the team has constructed a threading facility on site to produce the required quantities of the materials themselves.
As well as addressing supply shortfall, the threading facility has resulted in a significant financial saving on the project by reducing waste, costs and lorry movements, and overall creating a more efficient way of working.
To construct the 880 metre long cut and cover Copthall tunnel, 92,000 fatigue rated couplers are required. A team of 14 will work at the facility six days a week, 8 hours a day for three years to meet the supply needs for the tunnel.
The process to get the facility up and running took 20 weeks in total, with the team gaining CARES certification (assured certification for the constructional steels industry) for the work and securing the required equipment from Sheffield based company, Leviat. It is only the second time CARES certification has been given for this activity to happen onsite.
The team purchase stock rebar and then complete processing operations on site, before taking it through the four-step threading process and delivering it to the Copthall tunnel construction area. All the work is taking place within the site boundary reducing unnecessary lorry movements, supporting HS2 Net Zero Carbon targets.
The solution was devised by Ray Moloney, Senior Project Manager for SCS JV, who explains his approach: "Uncertainties in the market and the need to meet the requirements of the HS2 construction programme meant that we had to look at an innovative solution for supplying fatigue rated mechanical reinforcement connections. In mid-2022 we started engaging with partners including Leviat and CARES to develop an on-site processing scheme and within 20 weeks, we were processing our first order.
"The solution has created new jobs, offered new training opportunities for engineers and means that we can remove the risk of any delays in construction due to supply shortages."
Time and date
CONSTRUCTION DIRECTORY
Latest Construction News
22/11/2024
GMI Construction Group has reached a major milestone ahead of schedule in the construction of a £15.7 million waste-to-energy facility in County Durham. The steel framework of the 75,000 sq ft high-temperature thermal treatment plant has been completed, marking significant progress in the ...
22/11/2024
Cure has secured planning permission for a large new residential development in Keynsham, located along Bath Road. The project will deliver 208 homes designed with energy efficiency, community living, and sustainability in mind. The development will include a mix of 168 houses and 40 flats, with ...
22/11/2024
Morgan Sindall Construction has completed the restoration of West Bromwich Town Hall and Library, revitalising the iconic Grade II listed building for the community. Delivered five weeks ahead of schedule, the project preserves the historic site's architectural heritage while ensuring its future ...
22/11/2024
British Steel has unveiled a state-of-the-art rail stocking facility at its headquarters in Scunthorpe, marking a £10-million investment to bolster the UK's rail infrastructure. The new hub is the largest of its kind in the country and is set to play a pivotal role in supporting the rail ...
22/11/2024
Manchester City Council is seeking developers to transform a surplus multi-storey car park on Church Street into a landmark project in the heart of the city's iconic Northern Quarter. Named St Paul's, after the historic church that once stood on the site, the 1.54-acre (0.62-hectare) location ...
22/11/2024
A £500,000 project to refurbish the gateway to Tadcaster is set to begin next month, aimed at enhancing the town's appeal to visitors and supporting local businesses. The improvements will focus on upgrading the bus station, public toilets, and adding visitor amenities to make the area more ...
22/11/2024
Wandsworth Council has approved plans for 50% affordable housing. The changes to the local plan would require developers to deliver 50% affordable housing on all new schemes, with a majority to be council housing. The Local Plan formalises how the council works with developers to create and ...
22/11/2024
Homebuilder Thakeham has handed over the first nine homes at its Holmhurst St Mary development near Hastings, East Sussex, to Southern Housing. Addressing the need for affordable homes in the local community, Holmhurst Gardens is a 100% affordable housing scheme comprising both homes for rent and ...
22/11/2024
Thames Water has announced the completion of a £9.7 million upgrade to Benson Sewage Treatment Works, boosting its capacity and improving environmental outcomes. The project, which began in June 2022, was finished at the end of 2023 and has increased the site's treatment capacity by 29%, from 58 ...
22/11/2024
Dean Clough, the award-winning, 22-acre mixed use commercial destination in Halifax, has agreed new deals to let regional office space to two global operators. Severn Glocon, a global leader in industrial valve engineering and manufacturing, has secured a 2,460 sq ft of office space in Crossley ...