Balfour Beatty VINCI have worked around the clock to move HS2's huge 5,600 tonne bridge into place under the Coventry to Leamington Spa railway in Warwickshire.
The operation to slide the 22 metres long and 11 metres wide bridge into position took 5.5 hours and was completed 27 hours ahead of schedule.
From the start of blockade on Saturday 29 July, 113 metres of the existing rail track and 188 rail sleepers were removed by the team, then 15,000 cubic metres of ground including hard sandstone material was excavated to create the space for the bridge to be moved into.
It was moved into place using five 3.8 tonne jacks on a sliding surface, designed by specialist civil and structural engineering company Freyssinet, which allowed the bridge to be jacked on a guiding raft slab over a distance of 47 metres.
It moved at around 9 meters per hour and took 5.5 hours to be moved into its final position at 03.30 on Monday 31 July. This innovative construction method allows the bridge to be moved in one movement, which dramatically reduces disruption for rail passengers.
In the coming days, the team working 24/7 will backfill around the structure and put the rail track back in place above it, ready for the railway to be re-opened at 08.30 on Sunday 6 August.
The structure will allow the high speed railway to pass underneath the existing Coventry to Leamington Spa line. In the short term it will also allow construction traffic to pass under this line, reducing the number of lorries on the public highways. The structure also features an adjoining access bridge for a nearby farmer, which will start construction shortly.
This is the third major bridge move undertaken by HS2 in the last two weeks, as construction ramps up on all the structures, including bridges and viaducts, where HS2 will intersect with existing railway lines and roads in the West Midlands.
On 17 July, a 6,200 tonne bridge was moved into place by an 840-wheeled transporter at Fulfen Wood near Lichfield under the existing West Coast Main Line. On 28 July, a 2,600 tonne bridge was also driven under the existing South Staffordshire freight railway line at nearby Streethay.
James Briggs, HS2's Project Manager said: "The team have done a brilliant job moving this 5,600 tonne bridge way ahead of schedule, and I'd like to thank everyone for pulling together to deliver such an efficient and safe operation.
"The bridge was built on-site adjacent to the existing railway – an innovative approach which means it takes days, not months, to safely complete our works, keeping disruption to a minimum for rail passengers.
HS2's civils contracts Balfour Beatty VINCI is delivering the construction work, and a Design JV of Mott MacDonald and Systra delivered the design.
Shamus Banaghan, Project Manager for Balfour Beatty VINCI (BBV) said: "I am particularly proud to work alongside such an experienced team, who have worked around the clock to successfully slide the bridge into position under the Coventry to Leamington Spa railway line.
"Over the last two and a half years through design development to implementation, we have remained focused on delivering this critical bridge move during the fixed Network Rail blockade. I would like to extend my thanks to everyone who has contributed to us achieving this latest feat of engineering ahead of schedule."
HS2 Ltd works closely with Network Rail to plan for HS2 works which require access to the existing rail network. Wherever possible, work programmes are aligned, so HS2 works and Network Rail's ongoing upgrade and maintenance works are delivered simultaneously.
John Emery, Senior Sponsor for Network Rail, said: "This is a fantastic milestone for HS2 who we have worked with closely to combine their major construction work with a project to strengthen a historic railway viaduct near Leamington Spa which will help to secure the future of this key route for passengers and freight services.
"I'd like to thank passengers for their patience this week and urge people travelling between now and Sunday 6 August to plan their journeys in advance with their train operator or visit www.nationalrail.co.uk."
The Fulfen Wood bridge operation, completed on Monday 17 July, was the UK's heaviest bridge drive to install an intersection bridge structure beneath the West Coast Main Line at Fulfen Wood near Lichfield.
The 56 metre long and 19 metre wide structure will allow Britain's new high-speed railway to pass beneath the busy existing railway line, on its route going north of Birmingham Curzon Street Station up to Crewe.
The giant 6,200-tonne concrete structure, which was built adjacent to the WCML over the last six months, was slowly manoeuvred into place on self-propelled modular transporters. Specially designed for very heavy lifting, the 840-wheeled transporter with four carrier beams was controlled by a remote steering system.
On Friday 28 July, the Streethay bridge was driven into place under the South Staffordshire freight railway on the same self-propelled modular transporters (SPMTs) that were used for the Fulfen Wood drive, but with 344 wheels for the lighter 2,600 tonnes structure.
Time and date
CONSTRUCTION DIRECTORY
Latest Construction News
21/11/2024
Stepnell has opened its new office in Liverpool, marking a significant step in the company's expansion into the North West. Building on its extensive experience delivering projects across the East and West Midlands as well as South of England, Stepnell is well positioned to serve a broader range ...
21/11/2024
Kier has announced a partnership with Sunbelt Rentals, naming the company as its official supplier of Hydrotreated Vegetable Oil (HVO) fuel. The move marks a significant step in Kier's efforts to reduce its carbon footprint and enhance sustainability across its operations. Over the next year, ...
21/11/2024
Esh Construction has been appointed to lead the next stage of one of the UK's most ambitious urban regeneration initiatives, Riverside Sunderland. In collaboration with Sunderland City Council, the company will deliver a £5.7 million package of infrastructure upgrades to drive forward this ...
21/11/2024
Families in Penarth will soon benefit from a new £22 million school designed specifically for pupils with Additional Learning Needs (ALNs). Named Ysgol Llyn Derw by its students, the project is being delivered by Morgan Sindall Construction after the previous contractor, ISG, entered ...
21/11/2024
Europe's leading online cleanroom consumables supplier, Cleanroomshop, has recently launched a brand-new website, giving its users an improved user experience. The new website continues to offer over 2,000 products from more than 40 brands, whilst incorporating a new look and more efficient ...
21/11/2024
At Ecomerchant, we offer a carefully curated selection of sustainable weatherproofing solutions, including natural lime renders, mineral finishes, and vapour-open waterproofing materials. They help prevent structural damage while ensuring your building can breathe naturally. Our eco-friendly ...
21/11/2024
The Transpennine Route Upgrade (TRU) has launched a public consultation on its proposal to close the Moorgate Halt level crossing in Uppermill, Saddleworth, and replace it with an upgraded public right of way. The TRU project aims to transform rail journeys across the North of England by offering ...
21/11/2024
The GRAHAM Hydrogen Conference recently brought together leading voices in the construction industry to explore hydrogen’s potential as a cornerstone of a net-zero future. The event drew positive feedback from attendees and the critical role hydrogen can play in achieving sustainability goals. The ...
20/11/2024
Construction firm Willmott Dixon has partnered with Westminster City Council on a £36 million project to restore the historic Seymour Centre in Marylebone, a Grade II listed building dating back to the 1930s. The project, procured through the SCF framework, will see the three-storey centre undergo ...
20/11/2024
The Hill Group has commenced work on a new development in Billericay, Essex, which will deliver 179 high-quality homes across a 20-acre site. Designed to blend with Billericay's scenic countryside while addressing the pressing demand for sustainable housing, the project is located on Kennel Lane ...