Network Rail has announced an extension of it working hours on Oxford Station upgrade works to make up for delays caused by historic discoveries at the worksite.
A Victorian brick archway and a hand grenade are among some of the unique challenges that temporarily paused progress on the major project, with round the clock shifts now set to begin.
Work on the £161m Oxford station and railway upgrade had to be paused in June, after contractors unearthed an inverted brick arch under the road at Botley Road bridge.
Ground investigations have since revealed the historic arch is far larger than previously known - reaching a metre deep and stretching around 100 metres - the full length between Mill Street and Frideswide Square.
Archaeologists believe the arch is part of a Victorian water system, designed to keep river water away from the railway and city.
A new work schedule has had to be drawn up to safely remove the brick arch before Network Rail and contractors, Kier Group, can continue to divert the utilities below Botley Road. This will involve the installation of piles to support the bridge and a switch to 24/7 working hours. During this work, a temporary drainage system will be in place to manage groundwater, before a new permanent pumping system is installed later in the project.
From the week commencing Monday 14 August, the team on site will be working from 7am until 7pm, seven days a week. Starting on Saturday 2 September, around the clock work will be carried out on site. To reduce disturbance to those in the area, the nosiest work will be carried out during the day. This revised approach has been agreed with Oxford City Council, in consultation with Oxfordshire County Council.
The multi-million-pound project to upgrade the station, the railway and the surrounding local road network will boost passengers' travel experience whilst better connecting rail links to the East of Oxford. Once complete, the station and railway upgrades - part of the Oxfordshire Connect programme – will provide travellers with a bigger and better Oxford station and an expanded railway which will enable more services for passengers and freight, with reduced journey times.
The road network near the station will also be improved, with safer junctions with Botley Road and more opportunities for sustainable transport, including enhanced bus travel as well as more space for cyclists and pedestrians through the addition of a four-metre cycle and footway on each side of the main road.
Philip Morton, project manager at Network Rail said: "Whilst we knew the arch was there, it's much larger than our original ground surveys identified, which has added a unique layer of complexity to our ongoing work to upgrade of Oxford station and surrounding areas.
"Due to its potential significance in supporting the bridge, removing the arch from beneath Botley Road is now our biggest challenge, but we're addressing it as safely and efficiently as possible.
"Following further investigations, our new work plan involves installing piles to stabilise the bridge while we excavate the brickwork before we can continue to divert the utilities.
"Going forward, we will be working day and night so we can gain back some of the time lost, with the majority of the noisy work planned to take place during the day, to minimise disruption for the local community. As ever, we appreciate everyone's patience while we manage this unexpected challenge."
Mark Dodd of Oxford Archaeology, said: "The historic city of Oxford contains archaeological remains dating back to the prehistoric period, so there's always the potential to discover a bit of history beneath the ground.
"Owing to the existing road, the site itself wasn't an ideal location for archaeology, so the best approach was for us to be on site whilst the works are underway. It's likely the arch was used to help manage the groundwater owing to its low-lying position close to the river Thames and this is an excellent example of a Victorian engineering solution, as seen elsewhere throughout Britain at this time."
Work was also paused on Thursday 20 July, when a nearby area had to be evacuated following the discovery of a WWII era hand grenade within the work site, near to the railway tracks. Officers from British Transport Police attended the incident, alongside personnel from Explosives Ordinance Disposal.
Time and date
CONSTRUCTION DIRECTORY
Latest Construction News
21/11/2024
Europe's leading online cleanroom consumables supplier, Cleanroomshop, has recently launched a brand-new website, giving its users an improved user experience. The new website continues to offer over 2,000 products from more than 40 brands, whilst incorporating a new look and more efficient ...
21/11/2024
At Ecomerchant, we offer a carefully curated selection of sustainable weatherproofing solutions, including natural lime renders, mineral finishes, and vapour-open waterproofing materials. They help prevent structural damage while ensuring your building can breathe naturally. Our eco-friendly ...
20/11/2024
Construction firm Willmott Dixon has partnered with Westminster City Council on a £36 million project to restore the historic Seymour Centre in Marylebone, a Grade II listed building dating back to the 1930s. The project, procured through the SCF framework, will see the three-storey centre undergo ...
20/11/2024
The Hill Group has commenced work on a new development in Billericay, Essex, which will deliver 179 high-quality homes across a 20-acre site. Designed to blend with Billericay's scenic countryside while addressing the pressing demand for sustainable housing, the project is located on Kennel Lane ...
20/11/2024
Extensive groundwork is underway for a new housing development in Maidstone, where Vistry Group, in partnership with Legal & General Affordable Homes, is set to build 272 properties on the site of the former Tovil Quarry off Farleigh Hill. The project will include 37 affordable homes for low-cost ...
20/11/2024
Stonewater has scooped a new energy efficiency retrofit contract with compliance and energy services provider Correct Contract Services. This work, funded through the Social Housing Decarbonisation Fund (SHDF) Wave 2, will include a range of energy-saving upgrades. Measures such as loft ...
20/11/2024
Kier has been appointed by Cambridgeshire County Council to deliver building, mechanical, and electrical maintenance services across the Council's portfolio of 160 corporate buildings. The contract, which began in November 2024, will run until 2027, with the possibility of two one-year extensions ...
20/11/2024
Builders use water for various functions on the job, they utilise this resource for worker hygiene, hydration, concrete batching, grouting, dust suppression, drilling and piling. If companies mismanage this water use, they can increase their environmental impact. When the industry comes ...
20/11/2024
Edmond Shipway has been appointed to a pioneering initiative tackling homelessness in Greater Manchester, providing project management and cost consultancy services on the second phase of Embassy Village. Set to deliver 40 purpose-built homes for men facing homelessness in Manchester, Embassy ...
20/11/2024
West Sussex County Council is inviting residents to share their views on proposed transport improvements at the Hazelwick and Tushmore junctions on the A2011 Crawley Avenue. The proposals aim to make walking, cycling, and public transport more appealing for short journeys. This initiative is part ...