Balfour Beatty VINCI has completed a 'marathon' construction operation at Streethay near Lichfield as part of an innovative project to pave the way for Britain’s new high-speed line.
The operation – which utilised the latest low-carbon design – involved excavating 14,000 tonnes of earth, building a 140 metre retaining wall and moving a 2,600 tonne bridge deck 130 metres into place under the South Staffordshire freight railway.
The work was carried out during a 10 week blockade. It was completed Balfour Beatty VINCI, and designers Mott MacDonald as part of a Design Joint Venture with SYSTRA (MMSDJV), together with teams from 18 specialist supply chain companies.
At the end of July, the 2,600 tonne bridge deck, which had been cast on land adjacent to the railway was moved 130 metres into position using self-propelled modular transporters. Since then, each side of the bridge was backfilled, the rail tracks were reinstated, with the railway line was successfully handed back to Network Rail on Wednesday 16 August and now reopened.
The 25 metres long and 18 metres wide Streethay overbridge sits within HS2's Streethay cutting and will enable HS2 trains to travel under the existing railway between Birmingham and Crewe. Through design development, Mott MacDonald engineers were able to reduce the total length of wall structures for the railway at Streethay from 1.6 kilometres to 420 metres, meaning 80% less concrete is needed - saving around 420,000 tonnes of carbon, supporting HS2's ambition to cut carbon on the project.
The Streethay bridge sits on top of the larger 420 metre long retaining wall structure which will have two additional bridges crossing it – the south bound A38 slip road bridge, and the Rykneld Bridge which carries the A38 north bound slip road and the A38 north and south bound carriageway.
At its peak, over 150 people worked on the complex construction operation, with teams from 18 specialist companies, delivering design, surveys, piling works, bridge build, concrete pouring, crane operations, reinforcements, modular transportation, track and systems removal and reinstatement.
The work was delivered in parallel to the construction of the nearby Fulfen Wood bridge, which involved moving a giant 6,200 tonne single span structure under the West Coast Main Line - the UK's heaviest drive to install an intersection bridge.
David Millar, Rail Interface Manager at Balfour Beatty VINCI said: "The successful delivery of this complex and challenging piece of engineering near Lichfield is another proud moment for Balfour Beatty VINCI on the HS2 project.
"It's only been possible thanks to the skill, dedication and support shown by the project team over the past few years, including our supply chain. Together, we've had to work around existing transport infrastructure, including the South Staffordshire freight railway and the A38, making this achievement even more rewarding."
Caroline Warrington, Senior Project Manager at HS2 Ltd said: "This is a fantastic example of a project within a project at HS2, pulling together teams from 18 specialist supply chain companies from the West Midlands as well as other regions, to deliver a complex construction operation. These are some of the many companies that are helping to build Britain's new zero carbon railway, supporting thousands of jobs right across the country.
"Unlike the Fulfen Wood bridge structure, which was constructed entirely off site, the Streethay bridge walls under the railway embankment had to be constructed during the blockade. This required a 72 day blockade, making it more of a marathon than a sprint!"
Mark Jordan, Mainline Design Director at Mott MacDonald Systra Design Joint Venture: "We're immensely proud of the collaborative effort to get the design for this critical structure and operation ready for HS2. It's no small task to coordinate milestones like the Streethay bridge, with expertise from our geotechnical and structural engineering teams delivering design to meet the interfacing requirements of both HS2 and Network Rail, and innovation to enable off-site construction and transportation of the 2,600 tonne structure by Self Propelled Modular Transport."
Prior to the railway blockade, retaining walls were installed on either side of the railway, enabling the areas to be excavated. The bridge deck was constructed on land adjacent to the existing railway, 130 metres from its final position.
Once the railway was closed to freight trains, the track and embankment were removed. Bachy Soletanche Balfour Beatty Ground Engineering joint venture then installed an additional 76 secant piles measuring 1.3 metres diameter and 30 metres deep, linking to the piles they installed prior to the blockade, to create two retaining walls which act as the walls for the bridge.
A concrete capping beam was installed over the retaining walls, then the bridge was moved into place using self-propelled modular transporters with 344 wheels. Concrete was poured to attach the deck to the capping beam, the embankment was backfilled using 2,500 tonnes of structural backfill, on either side of the bridge, before the railway line was reinstated.
The next works in this area include the construction of two HS2 over bridges which will run under the A38.
Construction News
18/08/2023
'Marathon' HS2 Bridge Construction Complete


23/04/2025
Electro-Wind Limited are excited to announce that international shopping is now available on all orders – no matter where you are in the world.
Whether you're across the street or across the ocean, your favourite products can now be delivered to your location.

22/04/2025
Construction company Kier has completed the redevelopment of Crescent at Temple Quay in Bristol, delivering a modern, sustainability-focused workspace on behalf of investment and development firm CEG.
The transformation includes a striking new two-storey façade, a rooftop extension, and three priva

22/04/2025
McPhillips has been awarded a £10 million contract by Hereford Council to construct the city’s new Transport Hub.
The project is part of a broader strategy to improve travel and connectivity across the city, encouraging a shift away from car dependency and supporting more sustainable transport opti

22/04/2025
Network Rail has delivered a wide-ranging programme of engineering works across south London, Kent and Sussex over the Easter weekend, completing critical upgrades aimed at improving safety, reliability and long-term performance of the railway network.
Despite the scale of the operation, more than

22/04/2025
Indurent has submitted a planning application for the final phase of development at Indurent Park Longbridge West, marking a major milestone in the ongoing regeneration of one of Birmingham's most historically significant industrial sites.
Located 12km south-west of Birmingham city centre, the site

22/04/2025
Notting Hill Genesis has agreed to sell 10,000 square feet of new high-quality workspace to long-term partner Bow Arts Trust in the heart of Hackney Wick.
The space will deliver 38 affordable studio units, designed to support local creatives and small enterprises.
Currently under construction and

22/04/2025
Ireland's largest independent manufacturer of concrete products Kilsaran, have entrusted Wilsons Auctions to sell over 150 assets of quarry equipment and construction machinery this May.
The upcoming auction is set to take place on Friday 16th May at Wilsons Auctions Dublin, with the first lot gett

22/04/2025
Developer Chancerygate has appointed Caddick Construction as the main contractor for its latest urban logistics development, T45, located just off the A63 in Leeds.
The project is expected to complete in early 2026 and will deliver 23 state-of-the-art commercial units to support the growing needs

22/04/2025
Construction firm G F Tomlinson has completed the complex and highly specialised task of removing and replacing the original roof of the Grade II Listed Central Building at the University of Nottingham\s Castle Meadow Campus.
The project is part of a major refurbishment to safeguard and enhance the

22/04/2025
Broadland District Councillor Caroline Karimi-Ghovanlou and Chairman of Sprowston Town Council Bill Couzens officially reopened the Viking Community Building, marking the beginning of a new era for the historic site.
Originally built in 1956 as the Viking Pub, the building has undergone a major tra