Construction UK Construction Directory
Time and date
CONSTRUCTION DIRECTORY
Share this page
Construction News
18/08/2023

'Marathon' HS2 Bridge Construction Complete

Construction News Image
Balfour Beatty VINCI has completed a 'marathon' construction operation at Streethay near Lichfield as part of an innovative project to pave the way for Britain’s new high-speed line.

The operation – which utilised the latest low-carbon design – involved excavating 14,000 tonnes of earth, building a 140 metre retaining wall and moving a 2,600 tonne bridge deck 130 metres into place under the South Staffordshire freight railway.

The work was carried out during a 10 week blockade. It was completed Balfour Beatty VINCI, and designers Mott MacDonald as part of a Design Joint Venture with SYSTRA (MMSDJV), together with teams from 18 specialist supply chain companies.

At the end of July, the 2,600 tonne bridge deck, which had been cast on land adjacent to the railway was moved 130 metres into position using self-propelled modular transporters. Since then, each side of the bridge was backfilled, the rail tracks were reinstated, with the railway line was successfully handed back to Network Rail on Wednesday 16 August and now reopened.

The 25 metres long and 18 metres wide Streethay overbridge sits within HS2's Streethay cutting and will enable HS2 trains to travel under the existing railway between Birmingham and Crewe. Through design development, Mott MacDonald engineers were able to reduce the total length of wall structures for the railway at Streethay from 1.6 kilometres to 420 metres, meaning 80% less concrete is needed - saving around 420,000 tonnes of carbon, supporting HS2's ambition to cut carbon on the project.

The Streethay bridge sits on top of the larger 420 metre long retaining wall structure which will have two additional bridges crossing it – the south bound A38 slip road bridge, and the Rykneld Bridge which carries the A38 north bound slip road and the A38 north and south bound carriageway.

-- Advertisement --
hss

At its peak, over 150 people worked on the complex construction operation, with teams from 18 specialist companies, delivering design, surveys, piling works, bridge build, concrete pouring, crane operations, reinforcements, modular transportation, track and systems removal and reinstatement.

The work was delivered in parallel to the construction of the nearby Fulfen Wood bridge, which involved moving a giant 6,200 tonne single span structure under the West Coast Main Line - the UK's heaviest drive to install an intersection bridge.

David Millar, Rail Interface Manager at Balfour Beatty VINCI said: "The successful delivery of this complex and challenging piece of engineering near Lichfield is another proud moment for Balfour Beatty VINCI on the HS2 project.

"It's only been possible thanks to the skill, dedication and support shown by the project team over the past few years, including our supply chain. Together, we've had to work around existing transport infrastructure, including the South Staffordshire freight railway and the A38, making this achievement even more rewarding."

Caroline Warrington, Senior Project Manager at HS2 Ltd said: "This is a fantastic example of a project within a project at HS2, pulling together teams from 18 specialist supply chain companies from the West Midlands as well as other regions, to deliver a complex construction operation. These are some of the many companies that are helping to build Britain's new zero carbon railway, supporting thousands of jobs right across the country.

"Unlike the Fulfen Wood bridge structure, which was constructed entirely off site, the Streethay bridge walls under the railway embankment had to be constructed during the blockade. This required a 72 day blockade, making it more of a marathon than a sprint!"

Mark Jordan, Mainline Design Director at Mott MacDonald Systra Design Joint Venture: "We're immensely proud of the collaborative effort to get the design for this critical structure and operation ready for HS2. It's no small task to coordinate milestones like the Streethay bridge, with expertise from our geotechnical and structural engineering teams delivering design to meet the interfacing requirements of both HS2 and Network Rail, and innovation to enable off-site construction and transportation of the 2,600 tonne structure by Self Propelled Modular Transport."

Prior to the railway blockade, retaining walls were installed on either side of the railway, enabling the areas to be excavated. The bridge deck was constructed on land adjacent to the existing railway, 130 metres from its final position.

Once the railway was closed to freight trains, the track and embankment were removed. Bachy Soletanche Balfour Beatty Ground Engineering joint venture then installed an additional 76 secant piles measuring 1.3 metres diameter and 30 metres deep, linking to the piles they installed prior to the blockade, to create two retaining walls which act as the walls for the bridge.

A concrete capping beam was installed over the retaining walls, then the bridge was moved into place using self-propelled modular transporters with 344 wheels. Concrete was poured to attach the deck to the capping beam, the embankment was backfilled using 2,500 tonnes of structural backfill, on either side of the bridge, before the railway line was reinstated.

The next works in this area include the construction of two HS2 over bridges which will run under the A38.

Latest Construction News

03/12/2024

Birmingham Children's Hospital has celebrated a significant milestone in the construction of its new clinical building on Loveday Street with a topping-out ceremony. The event marked the completion of the building's steelwork framework. Attendees, including hospital staff, construction partners, ...
03/12/2024

A £6.8 million state-of-the-art Sherwood Observatory Planetarium & Science Centre in Sutton-in-Ashfield has opened its doors to the public. The project, delivered by G F Tomlinson through SCAPE, involved the transformation of a disused Victorian reservoir into a modern visitor attraction and ...
03/12/2024

Last Friday saw the National Access and Scaffolding Confederation (NASC) bring the scaffolding industry together at the ICC Belfast, to celebrate its high achievers. The Scaffolding Excellence Awards 2024 marked the culmination of the industry's first major conference and expo in Europe, Scaffex24, ...
03/12/2024

Barratt London and Places for London have exchanged contracts on a new development site in High Barnet. This is the second project unlocked by the West London Partnership, a collaboration established in June 2024 to deliver over 4,000 new homes across West London. The High Barnet development will ...
03/12/2024

Bellway Strategic Land has submitted a planning application to Durham County Council for a 149-home extension to the Seaham Garden Village development. The proposed development includes open space and wildlife improvements. Bellway conducted a public consultation process over the summer to gather ...
03/12/2024

The Chartered Institute of Building (CIOB) is set to launch its third global survey to investigate the mental health challenges faced by construction workers. The previous study, published in 2020, revealed alarming statistics, including: • 97% of construction workers experiencing high levels of ...
02/12/2024

Thames Water has awarded a £400 million framework to support its infrastructure upgrades over the next five years. The water company aims to address the challenges posed by ageing infrastructure and climate change. The framework will provide access to a range of professional services, including ...
02/12/2024

GRAHAM has been awarded a contract to design and build the first phase of the Cardiff Crossrail project. The ambitious project aims to transform Cardiff's transport infrastructure. As part of an early contractor involvement (ECI) deal, GRAHAM will work closely with Cardiff Council and Transport ...
02/12/2024

Watkin Jones has agreed to develop and deliver 295 new homes on behalf of Torus, the largest affordable housing provider in the North West of England, which will be partly funded by Homes England. The new scheme will result in the regeneration of an existing brownfield site, forming part of an ...
02/12/2024

Costain has been selected to provide programme management services to Thames Water as part of a new five-year framework. The contract will support the delivery of upgrades to the water company's infrastructure assets across the region. Thames Water anticipates a significant increase in its capital ...
T & D Glazing And Installation LimitedStuart CanvasLakeside HireBRICOFLOR UKAqua Direct LtdThink Construction Skills Ltd.Efco UK LtdForge Lifts LtdAtlas Winch & Hoist Services Ltd (UK)Landscaping Cambridge
Terms and Conditions
2024/12/03 17:29:19