Network Rail has switched on 116 new state of the art digital signals on the railway across parts of south west London and Berkshire, as part of the four-year resignalling programme to improve reliability.
The railway reopened as planned on Saturday, 02 September, following a 14-day, three-part closure between Barnes and Virginia Water, Windsor & Eton Riverside and Hounslow, to allow Network Rail to switch on the newly installed signals.
Since Saturday 19 August, Network Rail’s team of engineers has worked around the clock to commission the 116 new signals – the railway’s traffic light system – and finish upgrading seven level crossings during this multistage closure.
Following the completion of this work, passengers will benefit from more reliable journeys and fewer delays on the Windsor Lines, which are a key route for commuters in and out of London.
The previous signalling system and track circuits – which tell signallers where trains are on the network – were controlled by the Feltham Area Signalling Centre and dated back to 1974 so needed upgrading as they had become less reliable and harder to maintain.
Control of this part of the railway has now moved to the Basingstoke Rail Operating Centre, a purpose-built rail hub that is shared with South Western Railway (SWR).
Over the past four years, as part of the wider £116m Feltham and Wokingham re-signalling programme, Network Rail’s engineers have installed 116 digital signals, 11km of new cabling housed in 14km of refurbished cable ducts, 27 new under-track cable routes to support the new technology and upgraded seven level crossings.
The Feltham and Wokingham re-signalling programme will be concluded in early 2024 with the completion of upgrades to key signalling equipment controlled by the Feltham Area Signalling Centre and Wokingham Signal Box, which jointly cover 80 miles of railway and 500 separate pieces of signalling equipment. A total of 13 level crossings will also have been renewed or upgraded, all with the aim of improving train performance and ensuring passengers enjoy more reliable journeys.
Time and date
CONSTRUCTION DIRECTORY
Latest Construction News
18/11/2024
A major milestone has been achieved in the transformation of Hayes Town Centre, as a topping out ceremony celebrated reaching the highest structural point in the first phase of two landmark housing developments. Delivered by Higgins Partnerships in collaboration with Hillingdon Council, the ...
18/11/2024
Haringey Council has approved the main construction contract for a transformative expansion and refurbishment of the borough's Civic Centre in Wood Green. The project includes a revitalised hub for council staff, residents, and community groups while preserving the heritage of the Grade II listed ...
18/11/2024
ISC has scooped a £34 million contract by the Cory Group (Cory) to build a Waste Transfer Station (WTS) facility by the River Thames in Barking. ISC, the contracting arm of materials group GRS, is the principal contractor for the River Road waste scheme, a key part of Cory’s Riverside 2 ...
18/11/2024
Anglian Water is kicking off the procurement process for a Programme Delivery Partner (PDP) to support its capital investment delivery over the next fifteen years. This will begin with the water company's biggest ever business plan for Asset Management Period 8 (AMP8) between 2025 and 2030 which, ...
18/11/2024
Kier has completed work on Mulberry Academy London Dock and has handed it over to London Borough of Tower Hamlets. The new energy efficient 11 – 19 co-educational comprehensive school is situated in the London Dock residential complex and provides 1150 new spaces for local students. It is partly ...
18/11/2024
The A10 at Foxton will be closed for seven days over the Christmas period to allow Network Rail to carry out vital repairs to a deteriorating level crossing and worn-out track. The closure will begin at 10pm on Tuesday, December 24, and last until 6am on Wednesday, January 1. During this time, ...
18/11/2024
Gleeds has announced the appointment of two new directors within its London project management arm. John Barnett and Ed Horne join the business from Avison Young Project Management to drive growth in Gleeds' major London projects division, bolstering the firm’s growing presence in the ...
18/11/2024
A £2 billion funding package has been secured to construct a 196km subsea and underground electricity cable between Scotland and northern England, the UK government has announced. The Eastern Green Link 1 (EGL1) project aims to strengthen energy security, lower consumer bills, and advance the ...
18/11/2024
Construction firm GRAHAM has completed the refurbishment and M&E installations of the Interventional Radiology Department at Queen's Medical Centre (QMC) which carries out life-saving Mechanical Thrombectomy procedures. The works for Nottingham University Hospitals NHS Trust, which were procured ...
18/11/2024
Joint venture partners BAM and Siemens Energy together with SSEN Transmission representatives came together to mark the official start of construction in Orkney of the £900 million Orkney-Caithness 220 kV Subsea Link project. The work will deliver a new electricity substation, which will help ...