Work To Prepare Ground For HS2's NICC Moves Forward
Work to prepare the ground for HS2’s new Network Integrated Control Centre (NICC) and train maintenance depot in Washwood Heath, North Birmingham, has taken a significant step forward, as the team passed a huge earthworks milestone.
Balfour Beatty VINCI (BBV), HS2's construction partner for the region, led the operation to excavate over one million cubic metres of earth at the Washwood Heath site. As part of a cut and fill exercise, the recycled material has been cleaned and reused to level the ground, paving the way for detailed design and construction of the new maintenance depot and control centre to start next year.
The NICC, effectively the 'nerve centre' for the HS2 network, will accommodate around one hundred staff that will control the real time operation of the railway. The site also includes a stabling yard, with 14 tracks, a maintenance building for the preparation of HS2's fleet of trains, and facilities for staff who will drive and service the trains. Once operational, the site is expected to support around 550 jobs.
In preparation for the works, BBV also diverted Wash Brook, which ran north – south through the site. The brook, which connects to the River Tame, is just one of the environmental design features planned for the site to provide local wildlife habitats and enhance its aesthetic appeal.
The Washwood Heath site has a long-standing rail history, dating back to the early 1900s, when it was first used as a railway sidings and marshalling yard. Its heavy industrial use over the last century meant the ground was highly contaminated, and specialist contractors, including Coventry-based Duo Group, have led the intense programme of work to clean up the site ready for its new beginnings at the heart of the new high-speed network.
BBV's recycle and reuse approach to the ground remediation and earthworks programme eliminated the need to import and export aggregate materials. Approximately 27,200 road wagons or 54,400 vehicle movements are estimated to have been avoided to date, minimising the impact of HS2’s work on local communities.
Alvin Pedzai, HS2 Project Manager responsible for main works civils delivery at Washwood Heath commented: "We're absolutely delighted with the progress made on site. The earthworks and ground remediation programme for Washwood Heath is nearing completion, and we’re on track to handover to HS2’s Rail Systems team, who will lead the next stage in this exciting programme of work to bring this once-derelict site back to life."
Balfour Beatty VINCI (BBV), HS2's construction partner for the region, led the operation to excavate over one million cubic metres of earth at the Washwood Heath site. As part of a cut and fill exercise, the recycled material has been cleaned and reused to level the ground, paving the way for detailed design and construction of the new maintenance depot and control centre to start next year.
The NICC, effectively the 'nerve centre' for the HS2 network, will accommodate around one hundred staff that will control the real time operation of the railway. The site also includes a stabling yard, with 14 tracks, a maintenance building for the preparation of HS2's fleet of trains, and facilities for staff who will drive and service the trains. Once operational, the site is expected to support around 550 jobs.
In preparation for the works, BBV also diverted Wash Brook, which ran north – south through the site. The brook, which connects to the River Tame, is just one of the environmental design features planned for the site to provide local wildlife habitats and enhance its aesthetic appeal.
The Washwood Heath site has a long-standing rail history, dating back to the early 1900s, when it was first used as a railway sidings and marshalling yard. Its heavy industrial use over the last century meant the ground was highly contaminated, and specialist contractors, including Coventry-based Duo Group, have led the intense programme of work to clean up the site ready for its new beginnings at the heart of the new high-speed network.
BBV's recycle and reuse approach to the ground remediation and earthworks programme eliminated the need to import and export aggregate materials. Approximately 27,200 road wagons or 54,400 vehicle movements are estimated to have been avoided to date, minimising the impact of HS2’s work on local communities.
Alvin Pedzai, HS2 Project Manager responsible for main works civils delivery at Washwood Heath commented: "We're absolutely delighted with the progress made on site. The earthworks and ground remediation programme for Washwood Heath is nearing completion, and we’re on track to handover to HS2’s Rail Systems team, who will lead the next stage in this exciting programme of work to bring this once-derelict site back to life."
29/01/2025
Caddick Construction has been awarded a £43 million contract to deliver the first phase of Cole Waterhouse's flagship regeneration scheme in Digbeth, Birmingham.
The project, known as Upper Trinity Street, marks a significant step in the area’s transformation.
Spanning 182,986 square feet, the re
29/01/2025
McLaren Construction has been appointed by O&H Properties to deliver the first phase of a £60 million Foster & Partners-designed development at the corner of New Bond Street and Grafton Street in London’s West End.
The seven-storey, 5,400 square metre prime retail and office scheme will feature ret
29/01/2025
GMI Construction Group has been awarded a contract to develop three high-specification warehouse units totalling over 175,000 square feet at Precedent Drive, Milton Keynes.
The £20 million project, commissioned by DV5 Last Mile Developments (UK) Ltd, a joint venture between Coltham and Delancey Re
29/01/2025
Plans for 106 sustainable new homes in Southville, a neighbourhood in South Bristol, have been approved as the city seeks to increase housing delivery to address growing demand.
Top 10 award-winning housebuilder The Hill Group will create a £60 million development on Raleigh Road, on land that was
29/01/2025
Bouygues UK has reached a major milestone in the fourth phase of the Hallsville Quarter regeneration project in Canning Town, London.
The project, part of the £3.7 billion Canning Town and Custom House Regeneration Programme, recently held a topping out ceremony, marking the completion of the 11-s
29/01/2025
Willmott Dixon Interiors is carrying out a significant upgrade to the roof of the National Maritime Museum in Greenwich, one of London's most iconic cultural landmarks.
As part of the £12 million project, the company is installing over 23,000 square feet of sun-protected glazing above the museum’s
29/01/2025
Equans has been appointed by Babergh and Mid Suffolk District Councils to carry out crucial decarbonisation work across the councils' housing stock, using funding secured through the Social Housing Decarbonisation Fund (SHDF).
The councils used the South East Consortium's Zero Carbon Framework to s
29/01/2025
In the world of construction, the quest for energy efficiency and sustainability is ever-evolving. Among the array of solutions available, EPS (Expanded Polystyrene) insulation stands out as a versatile and effective option for enhancing the thermal performance of buildings, particularly when used f
29/01/2025
BCP Council has completed significant coastal protection works at Hamworthy Park, ensuring its resilience against erosion for the next 20 years.
A 200-metre stretch of sea wall along the eastern promenade has been reinforced using low-carbon concrete, while new steps have been constructed to improv
29/01/2025
Geo-environmental consultancy and remediation contractor, The LK Group, has strengthened its team with a trio of recruits.
The multidisciplinary company's latest raft of hires comprises a new director, associate director and remediation manager.
The geo-environmental specialist, headquartered i