Hinkley Point C First Reactor Building Topped Out
The world's largest crane has been used to lift a 47m wide dome into place on top of the first reactor building at Hinkley Point C.
The major milestone closes the roof on the first reactor building, allowing the first nuclear reactor to be installed next year. The power station's two nuclear reactors will provide reliable zero-carbon electricity for six million homes, boosting Britain's energy security for decades to come.
Engineering teams lifted the 245-tonne steel dome precisely into place on top of the reactor building. The achievement ends the year on a high as the 14-metre-tall dome sits on top of the 44-metre-high reactor building.
The lift, starting at 07:20, was carefully planned to take advantage of a weather window to allow the hour-and-a-half long manoeuvre to be completed in low wind conditions.
The dome is the top part of the reactor building's inner containment – a steel cylinder encased in concrete. Measuring 47m in diameter, it is wider than the dome of St Paul's Cathedral – and made up of 38 prefabricated panels which were shipped to Hinkley Point C and welded together in an onsite factory. Prefabrication and modular construction are key features of Hinkley Point C's construction.
Earlier this month, the 750 tonne "Polar Crane" was lifted into place in a single piece above the reactor building's third – and final – steel liner ring. This internal crane will rotate 360° above the reactor and be used for refuelling and installing equipment.
Simon Parsons, Nuclear Island Area Director, said: "Building the first nuclear power station in a generation is a challenging job and the success of this complex operation is due to the determination and commitment of our fantastic teams.
"Lifting the dome allows us to get on with the fitting of equipment, pipes and cables, including the first reactor which is on site and ready to be installed next year."
Nuclear Minister Andrew Bowie said: "This is a major milestone in building Britain's first nuclear reactor in a generation, and a key part of the UK Government's plans to revitalise nuclear.
"Generating enough zero-carbon power for six million homes, Hinkley Point C will reduce our reliance on imported energy and support our shift to net zero."
Big Carl's latest lift highlights the progress being made at Hinkley Point C, where 10,000 workers and 3,500 British companies are building a power station which is essential in helping Britian achieve Net Zero. Hinkley Point C will power 6-million homes with reliable zero carbon electricity made in the UK.
The major milestone closes the roof on the first reactor building, allowing the first nuclear reactor to be installed next year. The power station's two nuclear reactors will provide reliable zero-carbon electricity for six million homes, boosting Britain's energy security for decades to come.
Engineering teams lifted the 245-tonne steel dome precisely into place on top of the reactor building. The achievement ends the year on a high as the 14-metre-tall dome sits on top of the 44-metre-high reactor building.
The lift, starting at 07:20, was carefully planned to take advantage of a weather window to allow the hour-and-a-half long manoeuvre to be completed in low wind conditions.
The dome is the top part of the reactor building's inner containment – a steel cylinder encased in concrete. Measuring 47m in diameter, it is wider than the dome of St Paul's Cathedral – and made up of 38 prefabricated panels which were shipped to Hinkley Point C and welded together in an onsite factory. Prefabrication and modular construction are key features of Hinkley Point C's construction.
Earlier this month, the 750 tonne "Polar Crane" was lifted into place in a single piece above the reactor building's third – and final – steel liner ring. This internal crane will rotate 360° above the reactor and be used for refuelling and installing equipment.
Simon Parsons, Nuclear Island Area Director, said: "Building the first nuclear power station in a generation is a challenging job and the success of this complex operation is due to the determination and commitment of our fantastic teams.
"Lifting the dome allows us to get on with the fitting of equipment, pipes and cables, including the first reactor which is on site and ready to be installed next year."
Nuclear Minister Andrew Bowie said: "This is a major milestone in building Britain's first nuclear reactor in a generation, and a key part of the UK Government's plans to revitalise nuclear.
"Generating enough zero-carbon power for six million homes, Hinkley Point C will reduce our reliance on imported energy and support our shift to net zero."
Big Carl's latest lift highlights the progress being made at Hinkley Point C, where 10,000 workers and 3,500 British companies are building a power station which is essential in helping Britian achieve Net Zero. Hinkley Point C will power 6-million homes with reliable zero carbon electricity made in the UK.
29/01/2025
Caddick Construction has been awarded a £43 million contract to deliver the first phase of Cole Waterhouse's flagship regeneration scheme in Digbeth, Birmingham.
The project, known as Upper Trinity Street, marks a significant step in the area’s transformation.
Spanning 182,986 square feet, the re
29/01/2025
McLaren Construction has been appointed by O&H Properties to deliver the first phase of a £60 million Foster & Partners-designed development at the corner of New Bond Street and Grafton Street in London’s West End.
The seven-storey, 5,400 square metre prime retail and office scheme will feature ret
29/01/2025
GMI Construction Group has been awarded a contract to develop three high-specification warehouse units totalling over 175,000 square feet at Precedent Drive, Milton Keynes.
The £20 million project, commissioned by DV5 Last Mile Developments (UK) Ltd, a joint venture between Coltham and Delancey Re
29/01/2025
Plans for 106 sustainable new homes in Southville, a neighbourhood in South Bristol, have been approved as the city seeks to increase housing delivery to address growing demand.
Top 10 award-winning housebuilder The Hill Group will create a £60 million development on Raleigh Road, on land that was
29/01/2025
Bouygues UK has reached a major milestone in the fourth phase of the Hallsville Quarter regeneration project in Canning Town, London.
The project, part of the £3.7 billion Canning Town and Custom House Regeneration Programme, recently held a topping out ceremony, marking the completion of the 11-s
29/01/2025
Willmott Dixon Interiors is carrying out a significant upgrade to the roof of the National Maritime Museum in Greenwich, one of London's most iconic cultural landmarks.
As part of the £12 million project, the company is installing over 23,000 square feet of sun-protected glazing above the museum’s
29/01/2025
Equans has been appointed by Babergh and Mid Suffolk District Councils to carry out crucial decarbonisation work across the councils' housing stock, using funding secured through the Social Housing Decarbonisation Fund (SHDF).
The councils used the South East Consortium's Zero Carbon Framework to s
29/01/2025
In the world of construction, the quest for energy efficiency and sustainability is ever-evolving. Among the array of solutions available, EPS (Expanded Polystyrene) insulation stands out as a versatile and effective option for enhancing the thermal performance of buildings, particularly when used f
29/01/2025
BCP Council has completed significant coastal protection works at Hamworthy Park, ensuring its resilience against erosion for the next 20 years.
A 200-metre stretch of sea wall along the eastern promenade has been reinforced using low-carbon concrete, while new steps have been constructed to improv
29/01/2025
Geo-environmental consultancy and remediation contractor, The LK Group, has strengthened its team with a trio of recruits.
The multidisciplinary company's latest raft of hires comprises a new director, associate director and remediation manager.
The geo-environmental specialist, headquartered i