Landslip Repair Work Complete To Shore Up Chiltern Main Line
Network Rail has completed major repair work to shore up a landslip on the Chiltern main line after storms and heavy rain destabilised a railway embankment in Bicester.
The railway between London Marylebone, Oxford and the Midlands reopened today, Tuesday 16 January, after rail engineers closed the line for two days to rebuild an embankment allowing trains to safely resume.
On Thursday 11 January 1,200 tonnes of earth moved from a railway embankment in the village of Launton after persistent heavy rainfall weakened the earth beneath it.
Although the landslip affected only one of two tracks, engineers needed to close the line entirely to safely repair and fully reopen the Chiltern main line for passengers and freight services.
Network Rail has worked round-the-clock with its contractor Murphy to drive 65 new steel piles into the ground next to the affected section of track. Approximately 3,000 tonnes of ballast (railway stone) has been used to rebuild the embankment and support the tracks above.
Adam Checkley, infrastructure director for Network Rail, said: "I'm sorry to passengers who’ve been affected by the closure of the Chiltern main line while we completed emergency repairs to the landslip near Bicester North station.
"I'm pleased to advise that we’ve reopened both tracks this morning – initially with a reduced speed limit – which means passenger and freight trains can run again. I want to thank passengers for their patience and ask those travelling to check www.nationalrail.co.uk for the latest journey information."
The railway between London Marylebone, Oxford and the Midlands reopened today, Tuesday 16 January, after rail engineers closed the line for two days to rebuild an embankment allowing trains to safely resume.
On Thursday 11 January 1,200 tonnes of earth moved from a railway embankment in the village of Launton after persistent heavy rainfall weakened the earth beneath it.
Although the landslip affected only one of two tracks, engineers needed to close the line entirely to safely repair and fully reopen the Chiltern main line for passengers and freight services.
Network Rail has worked round-the-clock with its contractor Murphy to drive 65 new steel piles into the ground next to the affected section of track. Approximately 3,000 tonnes of ballast (railway stone) has been used to rebuild the embankment and support the tracks above.
Adam Checkley, infrastructure director for Network Rail, said: "I'm sorry to passengers who’ve been affected by the closure of the Chiltern main line while we completed emergency repairs to the landslip near Bicester North station.
"I'm pleased to advise that we’ve reopened both tracks this morning – initially with a reduced speed limit – which means passenger and freight trains can run again. I want to thank passengers for their patience and ask those travelling to check www.nationalrail.co.uk for the latest journey information."
29/01/2025
Caddick Construction has been awarded a £43 million contract to deliver the first phase of Cole Waterhouse's flagship regeneration scheme in Digbeth, Birmingham.
The project, known as Upper Trinity Street, marks a significant step in the area’s transformation.
Spanning 182,986 square feet, the re
29/01/2025
McLaren Construction has been appointed by O&H Properties to deliver the first phase of a £60 million Foster & Partners-designed development at the corner of New Bond Street and Grafton Street in London’s West End.
The seven-storey, 5,400 square metre prime retail and office scheme will feature ret
29/01/2025
GMI Construction Group has been awarded a contract to develop three high-specification warehouse units totalling over 175,000 square feet at Precedent Drive, Milton Keynes.
The £20 million project, commissioned by DV5 Last Mile Developments (UK) Ltd, a joint venture between Coltham and Delancey Re
29/01/2025
Plans for 106 sustainable new homes in Southville, a neighbourhood in South Bristol, have been approved as the city seeks to increase housing delivery to address growing demand.
Top 10 award-winning housebuilder The Hill Group will create a £60 million development on Raleigh Road, on land that was
29/01/2025
Bouygues UK has reached a major milestone in the fourth phase of the Hallsville Quarter regeneration project in Canning Town, London.
The project, part of the £3.7 billion Canning Town and Custom House Regeneration Programme, recently held a topping out ceremony, marking the completion of the 11-s
29/01/2025
Willmott Dixon Interiors is carrying out a significant upgrade to the roof of the National Maritime Museum in Greenwich, one of London's most iconic cultural landmarks.
As part of the £12 million project, the company is installing over 23,000 square feet of sun-protected glazing above the museum’s
29/01/2025
Equans has been appointed by Babergh and Mid Suffolk District Councils to carry out crucial decarbonisation work across the councils' housing stock, using funding secured through the Social Housing Decarbonisation Fund (SHDF).
The councils used the South East Consortium's Zero Carbon Framework to s
29/01/2025
In the world of construction, the quest for energy efficiency and sustainability is ever-evolving. Among the array of solutions available, EPS (Expanded Polystyrene) insulation stands out as a versatile and effective option for enhancing the thermal performance of buildings, particularly when used f
29/01/2025
BCP Council has completed significant coastal protection works at Hamworthy Park, ensuring its resilience against erosion for the next 20 years.
A 200-metre stretch of sea wall along the eastern promenade has been reinforced using low-carbon concrete, while new steps have been constructed to improv
29/01/2025
Geo-environmental consultancy and remediation contractor, The LK Group, has strengthened its team with a trio of recruits.
The multidisciplinary company's latest raft of hires comprises a new director, associate director and remediation manager.
The geo-environmental specialist, headquartered i