Rail engineers have completed upgrade work at Birmingham's New Street Station.
Platforms 5 and 6 have now reopened to passengers as one of the final parts of a £7.8m investment to upgrade and strengthen the original 1960s concrete deck which supports the station concourse.
The project which began in early 2023 saw all 12 platforms closed in pairs, for four weeks at a time, while engineers accessed the concrete structure above the platforms to carry out key repairs to supporting beams. The vital improvements will ensure that Birmingham New Street is fit for the future.
Over 500 repairs were made to the concrete, which involved the installation of over 5,000 steel bolts into the concrete beams, followed by fixing nearly 900 steel plates.
Network Rail worked closely with train operators to minimise disruption to passengers as much as possible. Closing the platforms in phases has allowed trains to continue running safely and reliably for passengers throughout the project.
Federica Labanca, Principal Route Engineer for Network Rail, said: "We are delighted to have reopened all of the platforms at Birmingham New Street after this major improvement work. This project is part of a wider programme to keep the iconic station running safely and reliably.
"We appreciate that the temporary platform closures meant changes to train services for some passengers and I’d like to thank station users for their patience while this important work took place."
Some final finishing touches are being made over the coming weeks but this is not expected to impact train services running through the station.
Construction News
09/02/2024
Upgrade Work Complete At Birmingham's New Street Station


23/04/2025
Electro-Wind Limited are excited to announce that international shopping is now available on all orders – no matter where you are in the world.
Whether you're across the street or across the ocean, your favourite products can now be delivered to your location.

22/04/2025
Construction company Kier has completed the redevelopment of Crescent at Temple Quay in Bristol, delivering a modern, sustainability-focused workspace on behalf of investment and development firm CEG.
The transformation includes a striking new two-storey façade, a rooftop extension, and three priva

22/04/2025
McPhillips has been awarded a £10 million contract by Hereford Council to construct the city’s new Transport Hub.
The project is part of a broader strategy to improve travel and connectivity across the city, encouraging a shift away from car dependency and supporting more sustainable transport opti

22/04/2025
Network Rail has delivered a wide-ranging programme of engineering works across south London, Kent and Sussex over the Easter weekend, completing critical upgrades aimed at improving safety, reliability and long-term performance of the railway network.
Despite the scale of the operation, more than

22/04/2025
Indurent has submitted a planning application for the final phase of development at Indurent Park Longbridge West, marking a major milestone in the ongoing regeneration of one of Birmingham's most historically significant industrial sites.
Located 12km south-west of Birmingham city centre, the site

22/04/2025
Notting Hill Genesis has agreed to sell 10,000 square feet of new high-quality workspace to long-term partner Bow Arts Trust in the heart of Hackney Wick.
The space will deliver 38 affordable studio units, designed to support local creatives and small enterprises.
Currently under construction and

22/04/2025
Ireland's largest independent manufacturer of concrete products Kilsaran, have entrusted Wilsons Auctions to sell over 150 assets of quarry equipment and construction machinery this May.
The upcoming auction is set to take place on Friday 16th May at Wilsons Auctions Dublin, with the first lot gett

22/04/2025
Developer Chancerygate has appointed Caddick Construction as the main contractor for its latest urban logistics development, T45, located just off the A63 in Leeds.
The project is expected to complete in early 2026 and will deliver 23 state-of-the-art commercial units to support the growing needs

22/04/2025
Construction firm G F Tomlinson has completed the complex and highly specialised task of removing and replacing the original roof of the Grade II Listed Central Building at the University of Nottingham\s Castle Meadow Campus.
The project is part of a major refurbishment to safeguard and enhance the

22/04/2025
Broadland District Councillor Caroline Karimi-Ghovanlou and Chairman of Sprowston Town Council Bill Couzens officially reopened the Viking Community Building, marking the beginning of a new era for the historic site.
Originally built in 1956 as the Viking Pub, the building has undergone a major tra