Network Rail Has completed repair work on a landslip in Knottingley.
The line between Knottingley and Pontefract Monkhill has now reopened following seven weeks of round-the-clock work by engineers to rebuild an embankment after it slipped in early-March.
More than 2,000 tonnes of stone has been installed along with a new 30m retaining wall structure to strengthen the land. 60 metres of track has been removed and replaced, with engineers also carrying out signalling and telecommunications work.
Teams have been working around the clock to reopen the line for local communities, with Network Rail thanking passengers and residents for their patience and understanding while the work has been carried out.
The landslip is believed to have been caused by the recent prolonged period of wet weather. However, during investigations, minor voids were discovered beneath the railway embankment that are believed to relate to historic mineral mining in the area. This has meant that the work to reopen the line has taken longer and has been more complex to complete.
Extensive work has since been carried out to fill the voids while engineers have also worked to reinstate the railway infrastructure above to allow the line to be reopened.
Engineers will continue to monitor the embankment to make sure that the land remains safe for trains to run over, with a temporary speed restriction in place through the area.
A rail replacement service has operated by Northern throughout the closure to keep passengers connected.
Over the next five years, Network Rail is investing £60 million in Yorkshire and the North East to help tackle disruption brought by severe weather, with major drainage schemes taking place throughout the region and the creation of new dedicated drainage roles on the organisation's North & East route.
Jason Hamilton, Route Director for Network Rail's North & East route, said: "I want to say a huge thank you to our passengers and lineside neighbours for their understanding, patience, and acceptance during the disruption they have faced and of the need to work around-the-clock close to their homes.
"I'm delighted that we have completed this major repair work so that the people of Knottingley and the surrounding areas can once again travel freely by train.
"Our engineers have worked incredibly hard over the last seven weeks to carry out this work as quickly and as safely as possible and I want to thank them, also, for their dedication and work ethic.
"We will continue to monitor the embankment to make sure trains can continue to pass safely through the area."
Time and date
CONSTRUCTION DIRECTORY
Latest Construction News
20/11/2024
Construction firm Willmott Dixon has partnered with Westminster City Council on a £36 million project to restore the historic Seymour Centre in Marylebone, a Grade II listed building dating back to the 1930s. The project, procured through the SCF framework, will see the three-storey centre undergo ...
20/11/2024
The Hill Group has commenced work on a new development in Billericay, Essex, which will deliver 179 high-quality homes across a 20-acre site. Designed to blend with Billericay's scenic countryside while addressing the pressing demand for sustainable housing, the project is located on Kennel Lane ...
20/11/2024
Extensive groundwork is underway for a new housing development in Maidstone, where Vistry Group, in partnership with Legal & General Affordable Homes, is set to build 272 properties on the site of the former Tovil Quarry off Farleigh Hill. The project will include 37 affordable homes for low-cost ...
20/11/2024
Stonewater has scooped a new energy efficiency retrofit contract with compliance and energy services provider Correct Contract Services. This work, funded through the Social Housing Decarbonisation Fund (SHDF) Wave 2, will include a range of energy-saving upgrades. Measures such as loft ...
20/11/2024
Kier has been appointed by Cambridgeshire County Council to deliver building, mechanical, and electrical maintenance services across the Council's portfolio of 160 corporate buildings. The contract, which began in November 2024, will run until 2027, with the possibility of two one-year extensions ...
20/11/2024
Builders use water for various functions on the job, they utilise this resource for worker hygiene, hydration, concrete batching, grouting, dust suppression, drilling and piling. If companies mismanage this water use, they can increase their environmental impact. When the industry comes ...
20/11/2024
Edmond Shipway has been appointed to a pioneering initiative tackling homelessness in Greater Manchester, providing project management and cost consultancy services on the second phase of Embassy Village. Set to deliver 40 purpose-built homes for men facing homelessness in Manchester, Embassy ...
20/11/2024
West Sussex County Council is inviting residents to share their views on proposed transport improvements at the Hazelwick and Tushmore junctions on the A2011 Crawley Avenue. The proposals aim to make walking, cycling, and public transport more appealing for short journeys. This initiative is part ...
19/11/2024
McLaren Construction has commenced works at the first UK industrial scheme in the East Midlands for a joint venture with Garbe Industrial Real Estate GmbH and Invesco Real Estate. McLaren will oversee all aspects of construction for the £30 million project located in Shireoaks, Worksop - in the ...
19/11/2024
Pennyfarthing Homes has submitted a planning application for 74 new homes in Fordingbridge as part of its plans to build a neighbourhood of 342 homes on the northern edge of the Hampshire market town. The new development which is part of the wider scheme known as Forde Valley and follows ...