Construction UK Construction Directory
Time and date
CONSTRUCTION DIRECTORY
Share this page
Construction News
15/08/2024

HS2 Moves 1,600 Steel And Concrete Bridge Into Place In Birmingham

Construction News Image
HS2 has moved a 1,600 tonne steel and concrete bridge into place in Saltley, Birmingham in just five hours.

The new Aston Church Road bridge, which is 84 metres long and 21 metres wide, was moved over the existing Birmingham to Derby railway line. It will also sit above the new HS2 tracks as high speed trains travel in and out of Birmingham.

The bridge provides an upgraded, safer section of Aston Church Road including cycleways, which connects Saltley, Washwood Heath and Nechells in north-east Birmingham.

Starting at 10pm on Saturday 10 August, it took five hours for the team to move the bridge into place, reaching its final position at 3am on Sunday morning. The operation was delivered by HS2’s main works contractor in the Midlands, Balfour Beatty VINCI (BBV) and their specialist bridge move contractor Mammoet, during a Network Rail blockade. The railway was handed back to Network Rail five hours earlier than planned.



The technique of building the structure on land next to the existing railway and moving it into position in one operation over one weekend, significantly minimises disruption to rail passengers.

-- Advertisement --
hss

Heavy lifting engineering experts Mammoet moved the bridge into place using two 128-wheeled self-propelled modular transporters (SPMTs) across a matting bed put down over the tracks by Pod-Trak to provide a level surface.

The new bridge was designed by a Design Joint Venture of Mott MacDonald and Systra working for HS2’s main works contractor in the Midlands, Balfour Beatty VINCI (BBV).

The design incorporates local feedback, with a wide pedestrian walkway creating enough space for cyclists, an LED lighting strategy to enhance safety, and new woodland planting around the bridge. Public feedback resulted in the stainless steel finish being replaced with weathered steel panels incorporating a perforated pattern to maximise light and views, making the bridge feel warmer and improving the pedestrian experience.

The composite bridge is made of a concrete deck cast over steel girders with glass reinforced plastic panels used as permanent formwork. One of the UK’s leading concrete frame specialists, MPB delivered the reinforced concrete works.

To prepare for the bridge move, a 9,000m2 platform was made and 62 piles constructed to support concrete structures. Around 4,000m3 concrete and 490 tonnes of reinforced steel has been used in the construction operation.

The bridge now sits on three structures - an abutment to the West of the existing rail tracks, a pier consisting of two columns on the East of the existing tracks, and an abutment to the East of the pier.

In the coming weeks, all the other structures around the bridge, along with the steel assembly of the parapet panels, will be completed.

Over the next 14 months, the original Aston Church Road bridge will be demolished to create the extra space for the HS2 line to pass through, and works will get underway to connect the new bridge to the existing road network.

Latest Construction News

21/11/2024

Stepnell has opened its new office in Liverpool, marking a significant step in the company's expansion into the North West. Building on its extensive experience delivering projects across the East and West Midlands as well as South of England, Stepnell is well positioned to serve a broader range ...
21/11/2024

Kier has announced a partnership with Sunbelt Rentals, naming the company as its official supplier of Hydrotreated Vegetable Oil (HVO) fuel. The move marks a significant step in Kier's efforts to reduce its carbon footprint and enhance sustainability across its operations. Over the next year, ...
21/11/2024

Esh Construction has been appointed to lead the next stage of one of the UK's most ambitious urban regeneration initiatives, Riverside Sunderland. In collaboration with Sunderland City Council, the company will deliver a £5.7 million package of infrastructure upgrades to drive forward this ...
21/11/2024

Europe's leading online cleanroom consumables supplier, Cleanroomshop, has recently launched a brand-new website, giving its users an improved user experience. The new website continues to offer over 2,000 products from more than 40 brands, whilst incorporating a new look and more efficient ...
21/11/2024

At Ecomerchant, we offer a carefully curated selection of sustainable weatherproofing solutions, including natural lime renders, mineral finishes, and vapour-open waterproofing materials. They help prevent structural damage while ensuring your building can breathe naturally. Our eco-friendly ...
20/11/2024

Construction firm Willmott Dixon has partnered with Westminster City Council on a £36 million project to restore the historic Seymour Centre in Marylebone, a Grade II listed building dating back to the 1930s. The project, procured through the SCF framework, will see the three-storey centre undergo ...
20/11/2024

The Hill Group has commenced work on a new development in Billericay, Essex, which will deliver 179 high-quality homes across a 20-acre site. Designed to blend with Billericay's scenic countryside while addressing the pressing demand for sustainable housing, the project is located on Kennel Lane ...
20/11/2024

Extensive groundwork is underway for a new housing development in Maidstone, where Vistry Group, in partnership with Legal & General Affordable Homes, is set to build 272 properties on the site of the former Tovil Quarry off Farleigh Hill. The project will include 37 affordable homes for low-cost ...
20/11/2024

Stonewater has scooped a new energy efficiency retrofit contract with compliance and energy services provider Correct Contract Services. This work, funded through the Social Housing Decarbonisation Fund (SHDF) Wave 2, will include a range of energy-saving upgrades. Measures such as loft ...
20/11/2024

Kier has been appointed by Cambridgeshire County Council to deliver building, mechanical, and electrical maintenance services across the Council's portfolio of 160 corporate buildings. The contract, which began in November 2024, will run until 2027, with the possibility of two one-year extensions ...
Stuart CanvasAqua Direct LtdBRICOFLOR UKThink Construction Skills Ltd.T & D Glazing And Installation LimitedLakeside HireEfco UK LtdFSW Security Products LtdNetwork Cable & Pipe Supports LtdSpray Pumps UK
Terms and Conditions
2024/11/21 15:44:40