Results from a new piece of research by the Chartered Institute of Building (CIOB) has revealed that a high proportion of complex construction projects are likely to be finished more than six months late, due to poor time control.
The CIOB's research was completed by more than 70 respondents in the UK and provided data on over 2000 projects. The research examined the construction industry’s methods to manage time on projects, in particular the techniques used and the competence of those engaged in the process.
Keith Pickavance CIOB Senior Vice President commented: "In the last ten years we have seen massive developments in hardware, software and communications that have made it virtually impossible to efficiently conduct any business without the use of computers and electronic services. The construction industry uses those facilities intensively in many areas including, design, manufacture, procurement, assembly and finance. In fact it uses them in virtually every field other than time-management, which currently does not use the available technology effectively.
"The growth in training, education and skill levels within the industry in the use of time-management techniques has not kept pace with the technology available. This should be of concern to many companies, as there is a trend towards developing contracts which are increasingly punitive if not executed efficiently.
"It should be recognised that the industry manages many projects very well indeed and the UK construction industry in particular is regarded around the world as a leading force; but we have to accept that respondents in this survey regarded the quality of time-management on construction projects as generally poor. Over half were familiar with only a master schedule being used, with no short term planning. Such schedules would typically be in bar chart form with no linked sequencing. In their experience, managers consequently would be unable to measure the impact slippage or the imposed changes on the works. Therefore managers would not be able to manage the effects of the delay on project completion, except intuitively."
According to the respondents certain types of project have a reasonable chance of being finished by, or before the completion date, using traditional methods of time-management and without modern methods of time control. These include, low-rise offices, and commercial, industrial, housing, schools and educational buildings, shops and shopping malls.
However, the results also show that more complex projects have a poor chance of being completed on time without advanced methods of project control being employed. These include hospital, clinic and health-related buildings, prisons and security infrastructure, stadia, railway and high-rise projects.
(JM/CD)
Time and date
CONSTRUCTION DIRECTORY
Latest Construction News
20/11/2024
Construction firm Willmott Dixon has partnered with Westminster City Council on a £36 million project to restore the historic Seymour Centre in Marylebone, a Grade II listed building dating back to the 1930s. The project, procured through the SCF framework, will see the three-storey centre undergo ...
20/11/2024
The Hill Group has commenced work on a new development in Billericay, Essex, which will deliver 179 high-quality homes across a 20-acre site. Designed to blend with Billericay's scenic countryside while addressing the pressing demand for sustainable housing, the project is located on Kennel Lane ...
20/11/2024
Extensive groundwork is underway for a new housing development in Maidstone, where Vistry Group, in partnership with Legal & General Affordable Homes, is set to build 272 properties on the site of the former Tovil Quarry off Farleigh Hill. The project will include 37 affordable homes for low-cost ...
20/11/2024
Stonewater has scooped a new energy efficiency retrofit contract with compliance and energy services provider Correct Contract Services. This work, funded through the Social Housing Decarbonisation Fund (SHDF) Wave 2, will include a range of energy-saving upgrades. Measures such as loft ...
20/11/2024
Kier has been appointed by Cambridgeshire County Council to deliver building, mechanical, and electrical maintenance services across the Council's portfolio of 160 corporate buildings. The contract, which began in November 2024, will run until 2027, with the possibility of two one-year extensions ...
20/11/2024
Builders use water for various functions on the job, they utilise this resource for worker hygiene, hydration, concrete batching, grouting, dust suppression, drilling and piling. If companies mismanage this water use, they can increase their environmental impact. When the industry comes ...
20/11/2024
Edmond Shipway has been appointed to a pioneering initiative tackling homelessness in Greater Manchester, providing project management and cost consultancy services on the second phase of Embassy Village. Set to deliver 40 purpose-built homes for men facing homelessness in Manchester, Embassy ...
20/11/2024
West Sussex County Council is inviting residents to share their views on proposed transport improvements at the Hazelwick and Tushmore junctions on the A2011 Crawley Avenue. The proposals aim to make walking, cycling, and public transport more appealing for short journeys. This initiative is part ...
19/11/2024
McLaren Construction has commenced works at the first UK industrial scheme in the East Midlands for a joint venture with Garbe Industrial Real Estate GmbH and Invesco Real Estate. McLaren will oversee all aspects of construction for the £30 million project located in Shireoaks, Worksop - in the ...
19/11/2024
Pennyfarthing Homes has submitted a planning application for 74 new homes in Fordingbridge as part of its plans to build a neighbourhood of 342 homes on the northern edge of the Hampshire market town. The new development which is part of the wider scheme known as Forde Valley and follows ...