Construction News
09/02/2009
Welsh Steel To Support London 2012 Aquatics Centre Roof
The Olympic Delivery Authority (ODA) has published new images showing the final preparations for the lift of the 2,800-tonne Aquatics Centre roof.
Thirty pairs of temporary support trestles up to 20m high have been put in place to support the huge steel trusses that will form the sweeping wave-shaped roof of the Aquatics Centre, which will be the 'gateway' to the Olympic Park during the London 2012 Games.
The steel roof of the Zaha Hadid designed venue will start to be lifted into place next month. After the 160m long roof is in place, which will be longer than the span of Heathrow Terminal Five, it will be lowered into its permanent position on three concrete supports.
Over 20,000 tonnes of concrete have been poured to complete the southern roof support and on the two northern roof supports which are almost complete.
Newport based company Rowecord is supplying the fabricated steel for the trusses and the roof beams to the construction contractor in a deal worth over £10m. The roof steel is being rolled in Gateshead, Motherwell and Scunthorpe by two different companies.
ODA Chief Executive David Higgins said: "With the Olympic Stadium, Olympic Village, Aquatics Centre, bridges and energy facilities coming out of the ground the Olympic Park is starting to take shape. Work on the Aquatics Centre is on track and final preparations are underway to lift the huge steel roof - one of the most challenging construction and engineering jobs on the Park. The sweeping wave-shaped roof will be a fantastic gateway to the Games and the venue will provide swimming and diving facilities in legacy that London does not currently have.
"Steel fabricated in Wales and rolled in the north of England and Scotland is an integral part of successfully completing this challenging lift and demonstrates the role that companies across the UK are playing in helping deliver the venues and infrastructure for the London 2012 Games."
(CD/JM)
Thirty pairs of temporary support trestles up to 20m high have been put in place to support the huge steel trusses that will form the sweeping wave-shaped roof of the Aquatics Centre, which will be the 'gateway' to the Olympic Park during the London 2012 Games.
The steel roof of the Zaha Hadid designed venue will start to be lifted into place next month. After the 160m long roof is in place, which will be longer than the span of Heathrow Terminal Five, it will be lowered into its permanent position on three concrete supports.
Over 20,000 tonnes of concrete have been poured to complete the southern roof support and on the two northern roof supports which are almost complete.
Newport based company Rowecord is supplying the fabricated steel for the trusses and the roof beams to the construction contractor in a deal worth over £10m. The roof steel is being rolled in Gateshead, Motherwell and Scunthorpe by two different companies.
ODA Chief Executive David Higgins said: "With the Olympic Stadium, Olympic Village, Aquatics Centre, bridges and energy facilities coming out of the ground the Olympic Park is starting to take shape. Work on the Aquatics Centre is on track and final preparations are underway to lift the huge steel roof - one of the most challenging construction and engineering jobs on the Park. The sweeping wave-shaped roof will be a fantastic gateway to the Games and the venue will provide swimming and diving facilities in legacy that London does not currently have.
"Steel fabricated in Wales and rolled in the north of England and Scotland is an integral part of successfully completing this challenging lift and demonstrates the role that companies across the UK are playing in helping deliver the venues and infrastructure for the London 2012 Games."
(CD/JM)
29/01/2025
Caddick Construction has been awarded a £43 million contract to deliver the first phase of Cole Waterhouse's flagship regeneration scheme in Digbeth, Birmingham.
The project, known as Upper Trinity Street, marks a significant step in the area’s transformation.
Spanning 182,986 square feet, the re
29/01/2025
McLaren Construction has been appointed by O&H Properties to deliver the first phase of a £60 million Foster & Partners-designed development at the corner of New Bond Street and Grafton Street in London’s West End.
The seven-storey, 5,400 square metre prime retail and office scheme will feature ret
29/01/2025
GMI Construction Group has been awarded a contract to develop three high-specification warehouse units totalling over 175,000 square feet at Precedent Drive, Milton Keynes.
The £20 million project, commissioned by DV5 Last Mile Developments (UK) Ltd, a joint venture between Coltham and Delancey Re
29/01/2025
Plans for 106 sustainable new homes in Southville, a neighbourhood in South Bristol, have been approved as the city seeks to increase housing delivery to address growing demand.
Top 10 award-winning housebuilder The Hill Group will create a £60 million development on Raleigh Road, on land that was
29/01/2025
Bouygues UK has reached a major milestone in the fourth phase of the Hallsville Quarter regeneration project in Canning Town, London.
The project, part of the £3.7 billion Canning Town and Custom House Regeneration Programme, recently held a topping out ceremony, marking the completion of the 11-s
29/01/2025
Willmott Dixon Interiors is carrying out a significant upgrade to the roof of the National Maritime Museum in Greenwich, one of London's most iconic cultural landmarks.
As part of the £12 million project, the company is installing over 23,000 square feet of sun-protected glazing above the museum’s
29/01/2025
Equans has been appointed by Babergh and Mid Suffolk District Councils to carry out crucial decarbonisation work across the councils' housing stock, using funding secured through the Social Housing Decarbonisation Fund (SHDF).
The councils used the South East Consortium's Zero Carbon Framework to s
29/01/2025
In the world of construction, the quest for energy efficiency and sustainability is ever-evolving. Among the array of solutions available, EPS (Expanded Polystyrene) insulation stands out as a versatile and effective option for enhancing the thermal performance of buildings, particularly when used f
29/01/2025
BCP Council has completed significant coastal protection works at Hamworthy Park, ensuring its resilience against erosion for the next 20 years.
A 200-metre stretch of sea wall along the eastern promenade has been reinforced using low-carbon concrete, while new steps have been constructed to improv
29/01/2025
Geo-environmental consultancy and remediation contractor, The LK Group, has strengthened its team with a trio of recruits.
The multidisciplinary company's latest raft of hires comprises a new director, associate director and remediation manager.
The geo-environmental specialist, headquartered i