Project Overview
The concept for the new facilities was based on excavating the site to provide the extra room required for the development. This required a contiguous pile retaining wall to support the surrounding ground and neighbouring roads. Van Elle, one of the UK's leading piling and ground engineering specialists were contracted to carry out all the piling works on this technically challenging site, as their expertise had been proven on similar projects.
The piling works, awarded by main contractor Quibell, worth over £400k involved a total of 298 No. Duplex and CFA piles.
In addition to the piling works, Van Elle's geotechnical team carried out a series of boreholes - as only limited information was available during the early tender stages. This gave a better picture of the actual ground conditions enabling Van Elle's engineers to make an informed choice of piling method.
The issues and the solutions
Not only is the school on a steep hillside surrounded by historic buildings, there is also a convent within 4m of the piling site and an adjacent main road. Lincoln itself sits on a rocky outcrop of Lincolnshire limestone with made ground above, making the ground conditions as challenging to work with as the site itself.
Because of these issues the use of Duplex piles was the only economical and practical solution. The Duplex piling method allowed the piles to be temporary cased through the made ground and socketed a minimum of 5m below dredge level into the bedrock.
The site was live during term time and as well as restricted access to and on site, deliveries could not be accepted before 9.30am and after 3.30pm to ensure the safety of the students and parents. This meant rig choice and logistics were crucial. Rigs were selected based on their size, weight and manoeuvrability as well as their suitability for the job. Well planned logistics and pre-ordered deliveries meant that there were no delays waiting for materials to arrive.
Construction
188 No. Duplex piles were drilled to form the contiguous wall, 660mm diameter temporary casing was drilled 5m onto the rock then the rock was drilled out using rotary percussive and Down The Hole Hammer techniques. The bore was then tremied with concrete, reinforcement was installed and the temporary casing removed.
The site investigation showed potential shallow mine workings at 1-2m deep along the south and east sides of the site. Van Elle solved this problem by pumping in a weak concrete grout, allowing it to set then re-boring through the concrete to form the Duplex piles.
The contract was complete within the anticipated programme and budget, even with the several unexpected challenges which arose during construction.
The retaining wall has now been excavated out by main contractor Quibell, and the steel frame is also being erected. The project is due for completion in 2010 when the students will be able to enjoy their new facilities.
Time and date
CONSTRUCTION DIRECTORY
Construction News
26/02/2009
New State-Of-The-Art Facilities For Lincoln Minster School Relies On A Contiguous Piled Wall Solution
Latest Construction News
21/11/2024
Europe's leading online cleanroom consumables supplier, Cleanroomshop, has recently launched a brand-new website, giving its users an improved user experience. The new website continues to offer over 2,000 products from more than 40 brands, whilst incorporating a new look and more efficient ...
21/11/2024
At Ecomerchant, we offer a carefully curated selection of sustainable weatherproofing solutions, including natural lime renders, mineral finishes, and vapour-open waterproofing materials. They help prevent structural damage while ensuring your building can breathe naturally. Our eco-friendly ...
20/11/2024
Construction firm Willmott Dixon has partnered with Westminster City Council on a £36 million project to restore the historic Seymour Centre in Marylebone, a Grade II listed building dating back to the 1930s. The project, procured through the SCF framework, will see the three-storey centre undergo ...
20/11/2024
The Hill Group has commenced work on a new development in Billericay, Essex, which will deliver 179 high-quality homes across a 20-acre site. Designed to blend with Billericay's scenic countryside while addressing the pressing demand for sustainable housing, the project is located on Kennel Lane ...
20/11/2024
Extensive groundwork is underway for a new housing development in Maidstone, where Vistry Group, in partnership with Legal & General Affordable Homes, is set to build 272 properties on the site of the former Tovil Quarry off Farleigh Hill. The project will include 37 affordable homes for low-cost ...
20/11/2024
Stonewater has scooped a new energy efficiency retrofit contract with compliance and energy services provider Correct Contract Services. This work, funded through the Social Housing Decarbonisation Fund (SHDF) Wave 2, will include a range of energy-saving upgrades. Measures such as loft ...
20/11/2024
Kier has been appointed by Cambridgeshire County Council to deliver building, mechanical, and electrical maintenance services across the Council's portfolio of 160 corporate buildings. The contract, which began in November 2024, will run until 2027, with the possibility of two one-year extensions ...
20/11/2024
Builders use water for various functions on the job, they utilise this resource for worker hygiene, hydration, concrete batching, grouting, dust suppression, drilling and piling. If companies mismanage this water use, they can increase their environmental impact. When the industry comes ...
20/11/2024
Edmond Shipway has been appointed to a pioneering initiative tackling homelessness in Greater Manchester, providing project management and cost consultancy services on the second phase of Embassy Village. Set to deliver 40 purpose-built homes for men facing homelessness in Manchester, Embassy ...
20/11/2024
West Sussex County Council is inviting residents to share their views on proposed transport improvements at the Hazelwick and Tushmore junctions on the A2011 Crawley Avenue. The proposals aim to make walking, cycling, and public transport more appealing for short journeys. This initiative is part ...