Heysham 1 Unit 2 Returns To Service
Four nuclear reactors at Heysham 1 and Hartlepool nuclear power stations, which provide around 2,350 megawatts of electricity generation in the UK, have been returned to service following a 17-month outage.
Reactor 2 at Heysham 1 power station, the last of the four reactors to return to service, has begun supplying power to the grid.
The four reactors were taken out of service in October 2007 after a planned inspection revealed some corrosion on wires which are part of the boiler closure units. Following a 17-month programme encompassing more than 3 million man hours of work the four reactors have been returned to service. The first three units are operating at full load and the fourth reactor is being increased to full load in a planned power increase.
Vincent de Rivaz, CEO of EDF Energy, recently visited both sites to see the work and meet the employees.
He said: "This large, complicated modification project has been managed professionally and carried out skilfully and is an illustration of the expertise and commitment of the station staff and all of the British Energy team who supported their work.
"This project demonstrates the value and importance of the British Energy acquisition to EDF Group and also to the country.
"We will continue to invest in all the nuclear power plants to improve their performance and seek to extend their lives.
"The value to investors of having large scale, secure, low carbon electricity generation as part of their portfolio will continue to increase in coming years as climate change and security of supply issues become more pressing."
Whilst the reactors were out of service, British Energy took the opportunity to bring forward maintenance work, including the replacement of a generator stator and main generator transformer at Hartlepool and the replacement of some 3km of cast iron cooling water pipe work at both stations.
(CD/JM)
Reactor 2 at Heysham 1 power station, the last of the four reactors to return to service, has begun supplying power to the grid.
The four reactors were taken out of service in October 2007 after a planned inspection revealed some corrosion on wires which are part of the boiler closure units. Following a 17-month programme encompassing more than 3 million man hours of work the four reactors have been returned to service. The first three units are operating at full load and the fourth reactor is being increased to full load in a planned power increase.
Vincent de Rivaz, CEO of EDF Energy, recently visited both sites to see the work and meet the employees.
He said: "This large, complicated modification project has been managed professionally and carried out skilfully and is an illustration of the expertise and commitment of the station staff and all of the British Energy team who supported their work.
"This project demonstrates the value and importance of the British Energy acquisition to EDF Group and also to the country.
"We will continue to invest in all the nuclear power plants to improve their performance and seek to extend their lives.
"The value to investors of having large scale, secure, low carbon electricity generation as part of their portfolio will continue to increase in coming years as climate change and security of supply issues become more pressing."
Whilst the reactors were out of service, British Energy took the opportunity to bring forward maintenance work, including the replacement of a generator stator and main generator transformer at Hartlepool and the replacement of some 3km of cast iron cooling water pipe work at both stations.
(CD/JM)
29/01/2025
Caddick Construction has been awarded a £43 million contract to deliver the first phase of Cole Waterhouse's flagship regeneration scheme in Digbeth, Birmingham.
The project, known as Upper Trinity Street, marks a significant step in the area’s transformation.
Spanning 182,986 square feet, the re
29/01/2025
McLaren Construction has been appointed by O&H Properties to deliver the first phase of a £60 million Foster & Partners-designed development at the corner of New Bond Street and Grafton Street in London’s West End.
The seven-storey, 5,400 square metre prime retail and office scheme will feature ret
29/01/2025
GMI Construction Group has been awarded a contract to develop three high-specification warehouse units totalling over 175,000 square feet at Precedent Drive, Milton Keynes.
The £20 million project, commissioned by DV5 Last Mile Developments (UK) Ltd, a joint venture between Coltham and Delancey Re
29/01/2025
Plans for 106 sustainable new homes in Southville, a neighbourhood in South Bristol, have been approved as the city seeks to increase housing delivery to address growing demand.
Top 10 award-winning housebuilder The Hill Group will create a £60 million development on Raleigh Road, on land that was
29/01/2025
Bouygues UK has reached a major milestone in the fourth phase of the Hallsville Quarter regeneration project in Canning Town, London.
The project, part of the £3.7 billion Canning Town and Custom House Regeneration Programme, recently held a topping out ceremony, marking the completion of the 11-s
29/01/2025
Willmott Dixon Interiors is carrying out a significant upgrade to the roof of the National Maritime Museum in Greenwich, one of London's most iconic cultural landmarks.
As part of the £12 million project, the company is installing over 23,000 square feet of sun-protected glazing above the museum’s
29/01/2025
Equans has been appointed by Babergh and Mid Suffolk District Councils to carry out crucial decarbonisation work across the councils' housing stock, using funding secured through the Social Housing Decarbonisation Fund (SHDF).
The councils used the South East Consortium's Zero Carbon Framework to s
29/01/2025
In the world of construction, the quest for energy efficiency and sustainability is ever-evolving. Among the array of solutions available, EPS (Expanded Polystyrene) insulation stands out as a versatile and effective option for enhancing the thermal performance of buildings, particularly when used f
29/01/2025
BCP Council has completed significant coastal protection works at Hamworthy Park, ensuring its resilience against erosion for the next 20 years.
A 200-metre stretch of sea wall along the eastern promenade has been reinforced using low-carbon concrete, while new steps have been constructed to improv
29/01/2025
Geo-environmental consultancy and remediation contractor, The LK Group, has strengthened its team with a trio of recruits.
The multidisciplinary company's latest raft of hires comprises a new director, associate director and remediation manager.
The geo-environmental specialist, headquartered i