Construction News
09/09/2009
Finning Power Back Up For UK's Biggest Pumping Station
Finning Power Systems, the sole UK supplier of Caterpillar equipment, has won a contract from Birse Water to supply the complete critical back up power for the main pumps at the UK’s largest pumping station as part of the Fens flood protection.
Due to come on stream in 2010, the £38 million new plant on the Middle level drain at St Germans, near Kings Lynn, will help protect 70,000 hectares of land and 25,000 homes from the North Sea. This land, stretching as far inland as Peterborough and Sawtry, is all close to or below sea level.
Finning is supplying six CAT 3500 series generators to power the six pumps. Three of these generator sets provide emergency power for three pumps, which would normally be mains powered. The other three generators are the sole source of power for the remaining three pumps. The generator sets provide a total of 8160kWe power, generating at 690V with non-standard alternators specifically designed and manufactured for the project.
The company is responsible for delivery to site, offloading, installation, commissioning and site testing of the complete solution prior to handover.
Each generator set will have a day fuel tank with a larger fuel storage tank providing back up. This would enable all six pumps to work continuously for ten days in the event of a complete mains power failure and serious flooding.
An additional auxiliary generator, supplied by Finning, provides a black start for the main generators plus power for the station’s other needs.
Each generator sits in its own plant room with Finning also supplying the plant room ventilation, sound attenuation system, complete exhaust systems and the day fuel storage tanks. The ventilation and sound attenuation system includes roof-mounted, penthouse inlet weather louvres and attenuators and wall-mounted, vertical discharge attenuators and weather louvres complete with automatic motorised weather dampers.
The project is the responsibility of the Middle Level Commissioners, a Cambridgeshire Local Authority responsible for Land Drainage and Navigation.
When operational, the new pumping station will be able to pump 100 tonnes of water per second, a 40 percent increase on the existing station. That equates to an Olympic sized swimming pool every 30 seconds.
The existing station, built in 1934, is at the end of its working life and experts fear that its pumps are not powerful enough to cope with rising sea levels and the increasing need to pump water 'uphill' against the tide as our climate changes.
David Thomas, Chief Engineer for Middle Level Commissioners said: "This project is very much a safety first approach and forms part of our flood defence. Whether any of the pumps are operational is weather dependent.
"Three pumps should be enough to cope with a typical annual flood, four would be needed for a serious one in ten years flood, while all six would only need to operate for catastrophic flooding, the sort of event that we would expect only once in a hundred years.
"Climate change is a major threat for the Fens so we had to act. This project has been designed to provide protection up to 2050 and takes this threat into account."
The new St Germans pumping station is expected to be fully operational by the summer of 2010. The existing station continues to operate in the meantime.
For further information about Finning Power Systems contact: Finning (UK) Ltd,
688-689 Stirling Road, Slough, Berkshire, SL1 4ST. Tel: 01753 497300
Fax: 01753 497301 or visit www.finning.co.uk/Power%20Systems/Default.aspx
Due to come on stream in 2010, the £38 million new plant on the Middle level drain at St Germans, near Kings Lynn, will help protect 70,000 hectares of land and 25,000 homes from the North Sea. This land, stretching as far inland as Peterborough and Sawtry, is all close to or below sea level.
Finning is supplying six CAT 3500 series generators to power the six pumps. Three of these generator sets provide emergency power for three pumps, which would normally be mains powered. The other three generators are the sole source of power for the remaining three pumps. The generator sets provide a total of 8160kWe power, generating at 690V with non-standard alternators specifically designed and manufactured for the project.
The company is responsible for delivery to site, offloading, installation, commissioning and site testing of the complete solution prior to handover.
Each generator set will have a day fuel tank with a larger fuel storage tank providing back up. This would enable all six pumps to work continuously for ten days in the event of a complete mains power failure and serious flooding.
An additional auxiliary generator, supplied by Finning, provides a black start for the main generators plus power for the station’s other needs.
Each generator sits in its own plant room with Finning also supplying the plant room ventilation, sound attenuation system, complete exhaust systems and the day fuel storage tanks. The ventilation and sound attenuation system includes roof-mounted, penthouse inlet weather louvres and attenuators and wall-mounted, vertical discharge attenuators and weather louvres complete with automatic motorised weather dampers.
The project is the responsibility of the Middle Level Commissioners, a Cambridgeshire Local Authority responsible for Land Drainage and Navigation.
When operational, the new pumping station will be able to pump 100 tonnes of water per second, a 40 percent increase on the existing station. That equates to an Olympic sized swimming pool every 30 seconds.
The existing station, built in 1934, is at the end of its working life and experts fear that its pumps are not powerful enough to cope with rising sea levels and the increasing need to pump water 'uphill' against the tide as our climate changes.
David Thomas, Chief Engineer for Middle Level Commissioners said: "This project is very much a safety first approach and forms part of our flood defence. Whether any of the pumps are operational is weather dependent.
"Three pumps should be enough to cope with a typical annual flood, four would be needed for a serious one in ten years flood, while all six would only need to operate for catastrophic flooding, the sort of event that we would expect only once in a hundred years.
"Climate change is a major threat for the Fens so we had to act. This project has been designed to provide protection up to 2050 and takes this threat into account."
The new St Germans pumping station is expected to be fully operational by the summer of 2010. The existing station continues to operate in the meantime.
For further information about Finning Power Systems contact: Finning (UK) Ltd,
688-689 Stirling Road, Slough, Berkshire, SL1 4ST. Tel: 01753 497300
Fax: 01753 497301 or visit www.finning.co.uk/Power%20Systems/Default.aspx
17/01/2025
Leeds Trinity University has officially opened its newly refurbished City Campus at 1 Trevelyan Square in Leeds.
Completed by GRAHAM Interior Fit-Out, the transformation of the central Leeds site introduces state-of-the-art facilities designed to improve learning and collaborate with industry partn
17/01/2025
Trammell Crow Company (TCC) has secured planning permission for a Grade A logistics scheme in Heywood, Greater Manchester, following a successful planning appeal.
The development will feature two state-of-the-art industrial and logistics buildings. One building will house two units measuring 4,796
17/01/2025
Poole-based developer AJC Group has celebrated a record-breaking 2024, delivering 100 affordable homes, a significant increase from the 72 units completed in the previous year.
Since 2023, AJC Group has completed and handed over 172 affordable homes across five sites.
In 2024 alone, the developer
17/01/2025
Plans for one of the most ambitious parks projects in London have taken a significant step forward, with Haringey Council securing nearly two additional acres of land around The Paddock nature reserve in Tottenham Hale.
The agreement with Thames Water marks a major milestone in the transformation o
17/01/2025
Islington Council has unveiled two draft guidance documents aimed at helping residents, businesses, and developers combat climate change by making buildings more energy efficient and fostering a greener, healthier borough.
The consultation seeks feedback on the draft Climate Action Supplementary Pl
17/01/2025
The City of Wolverhampton Council has unveiled a £98 million investment plan over the next five years to develop around 500 new homes across the city.
The proposal, part of the Housing Revenue Account (HRA) Business Plan, received Cabinet approval this week and now moves to Full Council for final
17/01/2025
Croydon Council has announced a significant milestone in the redevelopment of the Purley Pool site, with revised proposals submitted for a new leisure centre, later living housing, and the regeneration of the surrounding area.
A planning application for the site was initially submitted in 2024, pro
17/01/2025
The City of Wolverhampton Council has announced that demolition work has commenced on the New Park Village estate, marking the start of a major £40 million redevelopment project to transform outdated council housing.
Contractor DSM Demolition has begun pulling down poor-quality bungalows on Valley
17/01/2025
Hillingdon Council has acquired 12 new homes at Carpenters Court in Uxbridge.
Leader of Hillingdon Council, Cllr Ian Edwards and Cllr Steve Tuckwell, Cabinet Member for Planning, Housing and Growth, visited the site to officially mark the handover of the properties from local developer Kearns Devel
17/01/2025
Organisers of UK Construction Week (UKCW) have announced another major coup for the show's 10th anniversary year, with the news that UKCW London will be co-locating with the 14th edition of The Stone Show & Hard Surfaces, the principal industry event for surface design.
Established 26 years ago, th